Skip to main content

Providing and installation of factory made Structural Stay in place form work system with double faced panels for walls, single faced panels for roof/ floor slabs, L-shaped single faced panels for corners, with necessary scaffolding, struts, bracing etc. Complete as per CPWD specification and directions of the Engineer in Charge. Design of walls and other members to be provided by the supplier & shall be duly vetted by any engineering institute of National repute such as IITs, NITs etc. and nothing extra shall be payable on this account (Additional steel reinforcement/dowels, design mix concrete of specified grade, electrical and plumbing conduits insert for services and plastering on either side of walls shall be paid for separately). Note:- This item shall be adopted for building upto G+3 Storeys only excluding seismic zone V

Double panel of required thickness (110mm & above) with minimum weight of panel as 11.05 kg per sqm for walls with corresponding corners and jambs strips
Item number
26.95.1
Analysis basis
450 sqm
Priced inputs
11
Derived rate
₹3,189.10/ SQM
D-01/RATE ANALYSISITEM 26.95.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.95.1 (Providing and installation of factory made Structural Stay in place form work system with double faced panels for walls, single faced panels for roof/ floor slabs, L-shaped single faced panels for corners, with necessary scaffolding, struts, bracing etc. Complete as per CPWD specification and directions of the Engineer in Charge. Design of walls and other members to be provided by the supplier & shall be duly vetted by any engineering institute of National repute such as IITs, NITs etc. and nothing extra shall be payable on this account (Additional steel reinforcement/dowels, design mix concrete of specified grade, electrical and plumbing conduits insert for services and plastering on either side of walls shall be paid for separately). Note:- This item shall be adopted for building upto G+3 Storeys only excluding seismic zone V Double panel of required thickness (110mm & above) with minimum weight of panel as 11.05 kg per sqm for walls with corresponding corners and jambs strips) is derived from 11 priced inputs for 450 sqm and works out to ₹3,189.10 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Assuming Strengthening of panels material
  • (structs,bracis and propes) will become unserviceable after use of 40 times, adding for
  • maintenance @ 10% of cost, taking salvage
  • value after full use of material @ 30% cost.
  • For diagonal Bracing on outer face 60mm
  • dia M.S Pipe (5 to 6 m long) = 600 metre @
  • 5.54 kg/m = 3324 kg
  • 50mm dia, M.S pipes for shorter length outer bracing and internal bracing. = 650 metre
  • @ 3.96 kg/m = 2574 kg
  • Total Weight = 5898 kg
  • Quantity for using Once = 5898 / 40 =
  • 147.45 kg
ANALYSIS OF RATES · ITEM 26.95.1DETAILS OF COST FOR 450 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8991MATStandard double panel of design width, height and thicknessStandard double panel of design width, height and thickness with minimum weight of panel as 11.05 kg per sqmsqm4402,071.009,11,240.00
8992MATCorner pieces L-Shapesqm10813.008,130.00
8993MATFlat strips for soffits (L.S.)Flat strips for soffitssqm20832.0016,640.00
9999MATTransportation of panelL.S.2,122.642.274,818.39
4009MATMile Steel tubes hot finished welded typeMild steel tubes hot finished welded typekg147.4572.0010,616.40
8724MAT12 mm thick marine plywood12 mm thick marine plywood conforming to IS: 710sqm12785.009,420.00
8994MATG.I binding wireKg2566.001,650.00
1219MATNails 75 mmM.S. Wire nailsKg1558.00870.00
0116LABFitter (Grade-I)Fitter (grade 1)Day20897.0017,940.00
0114LABBeldarDay40736.0029,440.00
9999MATSundriesL.S54.242.27123.12
BUILD-UP TO RATE
Add Maintenance charges @ 10% of P
+1,061.64
Deduct salvage value @ 30% of bare cost of material on P
-3,184.92
TOTAL
10,08,764.63
Add 1 % Water charges on “W”
+10,087.65
TOTAL
10,18,852.28
Add GST on “X” (multiplying factor 0.2127)
+2,16,709.88
TOTAL
12,35,562.16
Add 15% CPOH on “Y”
+1,85,334.32
TOTAL
14,20,896.48
Add Labour Cess @ 1% on “Z”
+14,208.96
Cost for 450 sqm
14,35,105.44
Cost of 1 sqm
3,189.12
SAY
₹3,189.10
D-02/SOURCEPRINTED PAGE 2051
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
2051

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2051. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.