Providing and installation of factory made Structural Stay in place form work system with double faced panels for walls, single faced panels for roof/ floor slabs, L-shaped single faced panels for corners, with necessary scaffolding, struts, bracing etc. Complete as per CPWD specification and directions of the Engineer in Charge. Design of walls and other members to be provided by the supplier & shall be duly vetted by any engineering institute of National repute such as IITs, NITs etc. and nothing extra shall be payable on this account (Additional steel reinforcement/dowels, design mix concrete of specified grade, electrical and plumbing conduits insert for services and plastering on either side of walls shall be paid for separately). Note:- This item shall be adopted for building upto G+3 Storeys only excluding seismic zone V

Double panel of required thickness (110mm & above) with minimum weight of panel as 11.05 kg per sqm for walls with corresponding corners and jambs strips

Item number
26.95.1
Analysis basis
Details of cost for 450 sqm
Priced inputs
11
Derived rate
3,189.10 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.95.1 Providing and installation of factory made Structural Stay in place form work system with double faced panels for walls, single faced panels for roof/ floor slabs, L-shaped single faced panels for corners, with necessary scaffolding, struts, bracing etc. Complete as per CPWD specification and directions of the Engineer in Charge. Design of walls and other members to be provided by the supplier & shall be duly vetted by any engineering institute of National repute such as IITs, NITs etc. and nothing extra shall be payable on this account (Additional steel reinforcement/dowels, design mix concrete of specified grade, electrical and plumbing conduits insert for services and plastering on either side of walls shall be paid for separately). Note:- This item shall be adopted for building upto G+3 Storeys only excluding seismic zone V Double panel of required thickness (110mm & above) with minimum weight of panel as 11.05 kg per sqm for walls with corresponding corners and jambs strips — is derived from 11 priced inputs for 450 sqm and works out to ₹3,189.10 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Assuming Strengthening of panels material
  • (structs,bracis and propes) will become unserviceable after use of 40 times, adding for
  • maintenance @ 10% of cost, taking salvage
  • value after full use of material @ 30% cost.
  • For diagonal Bracing on outer face 60mm
  • dia M.S Pipe (5 to 6 m long) = 600 metre @
  • 5.54 kg/m = 3324 kg
  • 50mm dia, M.S pipes for shorter length outer bracing and internal bracing. = 650 metre
  • @ 3.96 kg/m = 2574 kg
  • Total Weight = 5898 kg
  • Quantity for using Once = 5898 / 40 =
  • 147.45 kg
CodeInputUnitQuantityRate (INR)Amount (INR)
8991Standard double panel of design width, height and thicknessStandard double panel of design width, height and thickness with minimum weight of panel as 11.05 kg per sqmMaterialsqm4402,071.009,11,240.00
8992Corner pieces L-ShapeMaterialsqm10813.008,130.00
8993Flat strips for soffits (L.S.)Flat strips for soffitsMaterialsqm20832.0016,640.00
9999Transportation of panelMaterialL.S.2,122.642.274,818.39
4009Mile Steel tubes hot finished welded typeMild steel tubes hot finished welded typeMaterialkg147.4572.0010,616.40
872412 mm thick marine plywood12 mm thick marine plywood conforming to IS: 710Materialsqm12785.009,420.00
8994G.I binding wireMaterialKg2566.001,650.00
1219Nails 75 mmM.S. Wire nailsMaterialKg1558.00870.00
0116Fitter (Grade-I)Fitter (grade 1)LabourDay20897.0017,940.00
0114BeldarLabourDay40736.0029,440.00
9999SundriesMaterialL.S54.242.27123.12
Add Maintenance charges @ 10% of P
1,061.64
Deduct salvage value @ 30% of bare cost of material on P
-3,184.92
TOTAL
10,08,764.63
Add 1 % Water charges on “W”
10,087.65
TOTAL
10,18,852.28
Add GST on “X” (multiplying factor 0.2127)
2,16,709.88
TOTAL
12,35,562.16
Add 15% CPOH on “Y”
1,85,334.32
TOTAL
14,20,896.48
Add Labour Cess @ 1% on “Z”
14,208.96
Cost for 450 sqm
14,35,105.44
Cost of 1 sqm
3,189.12
Say
3,189.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2051. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works