Providing and placing “Stay in Place PVC Wall formwork” made up of extruded Unplasticised Poly Vinyl Chloride (uPVC) consisting of Main panel, 3 way Connector, Starter Channel, Joint Panel, Connection Panels, Door/Window frame/trim panels etc. all complete as per manufacturer design and for all heights as per direction of Engineer-in-charge. (Note: Suitable for in fill walls with appropriate Structural system)

165 mm wide Stay in Place PVC Wallform made of minimum 2.50 mm thick sections and minimum weight 29.00 kg /sqm of formwork
Item number
26.96.2
Analysis basis
20 sqm
Priced inputs
6
Derived rate
₹3,805.05/ SQM
D-01/RATE ANALYSISITEM 26.96.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.96.2 (Providing and placing “Stay in Place PVC Wall formwork” made up of extruded Unplasticised Poly Vinyl Chloride (uPVC) consisting of Main panel, 3 way Connector, Starter Channel, Joint Panel, Connection Panels, Door/Window frame/trim panels etc. all complete as per manufacturer design and for all heights as per direction of Engineer-in-charge. (Note: Suitable for in fill walls with appropriate Structural system) 165 mm wide Stay in Place PVC Wallform made of minimum 2.50 mm thick sections and minimum weight 29.00 kg /sqm of formwork) is derived from 6 priced inputs for 20 sqm and works out to ₹3,805.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • in Place (PVC) wall forms)
  • Labour for Installation
  • Cost of Raw Materials for 20/2 = 10 sqm of
ANALYSIS OF RATES · ITEM 26.96.2DETAIL OF COST FOR 20 SQM (165 MM WIDE STAY
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8996MAT165 mm wide Stay in Place Wallform 2.50 mm thick of extruded Unplasticised Poly Vinyl Chloride (uPVC)125 mm / 165 mm wide Stay in Place Wallform 2.50 mm thick of extruded Unplasticised Poly Vinyl Chloride (uPVC).———
OTHER165 mm Wallforms @29.00 kg/sqm 290.00 kg + 5% wastage (14.50 kg) = 304.50 kgkg304.5160.0048,720.00
9999MATTransportation ChargesL.S.684.92.271,554.72
0123LABMason 1st ClassMason 1st classday1897.00897.00
0115LABBeldarCoolieday3736.002,208.00
9999MATSundriesL.S.502.27113.50
BUILD-UP TO RATE
TOTAL
53,493.22
Add 1% Water charges on “W”
+534.93
TOTAL
54,028.15
Add GST on “X” (multiplying factor 0.2127)
+11,491.79
TOTAL
65,519.94
Add 15% CPOH on “Y”
+9,827.99
TOTAL
75,347.93
Add Cess @ 1% on “Z”
+753.48
Cost of 20 sqm
76,101.41
Cost for 1 sqm
3,805.07
SAY
₹3,805.05
D-02/SOURCEPRINTED PAGE 2054
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
2054

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2054. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.