Providing and placing “Stay in Place PVC Wall formwork” made up of extruded Unplasticised Poly Vinyl Chloride (uPVC) consisting of Main panel, 3 way Connector, Starter Channel, Joint Panel, Connection Panels, Door/Window frame/trim panels etc. all complete as per manufacturer design and for all heights as per direction of Engineer-in-charge. (Note: Suitable for in fill walls with appropriate Structural system)
- Item number
- 26.96.2
- Analysis basis
- 20 sqm
- Priced inputs
- 6
- Derived rate
- ₹3,805.05/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.96.2 (Providing and placing “Stay in Place PVC Wall formwork” made up of extruded Unplasticised Poly Vinyl Chloride (uPVC) consisting of Main panel, 3 way Connector, Starter Channel, Joint Panel, Connection Panels, Door/Window frame/trim panels etc. all complete as per manufacturer design and for all heights as per direction of Engineer-in-charge. (Note: Suitable for in fill walls with appropriate Structural system) 165 mm wide Stay in Place PVC Wallform made of minimum 2.50 mm thick sections and minimum weight 29.00 kg /sqm of formwork) is derived from 6 priced inputs for 20 sqm and works out to ₹3,805.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- in Place (PVC) wall forms)
- Labour for Installation
- Cost of Raw Materials for 20/2 = 10 sqm of
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8996 | MAT | 165 mm wide Stay in Place Wallform 2.50 mm thick of extruded Unplasticised Poly Vinyl Chloride (uPVC)125 mm / 165 mm wide Stay in Place Wallform 2.50 mm thick of extruded Unplasticised Poly Vinyl Chloride (uPVC). | — | — | — | |
| OTHER | 165 mm Wallforms @29.00 kg/sqm 290.00 kg + 5% wastage (14.50 kg) = 304.50 kg | kg | 304.5 | 160.00 | 48,720.00 | |
| 9999 | MAT | Transportation Charges | L.S. | 684.9 | 2.27 | 1,554.72 |
| 0123 | LAB | Mason 1st ClassMason 1st class | day | 1 | 897.00 | 897.00 |
| 0115 | LAB | BeldarCoolie | day | 3 | 736.00 | 2,208.00 |
| 9999 | MAT | Sundries | L.S. | 50 | 2.27 | 113.50 |
- TOTAL
- 53,493.22
- Add 1% Water charges on “W”
- +534.93
- TOTAL
- 54,028.15
- Add GST on “X” (multiplying factor 0.2127)
- +11,491.79
- TOTAL
- 65,519.94
- Add 15% CPOH on “Y”
- +9,827.99
- TOTAL
- 75,347.93
- Add Cess @ 1% on “Z”
- +753.48
- Cost of 20 sqm
- 76,101.41
- Cost for 1 sqm
- 3,805.07
- SAY
- ₹3,805.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 2054
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2054. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.