Providing and fixing Scaffolding net of required width made of high density Polyethylene UV stabilized knitted on warp knitting machines having density 100grams/sqm and shading coefficient minimum 75% around the construction site/ for vertical extension as per requirement including fastening/tying with building/scaffolding pipes or with any other fixtures etc. complete as per direction of Engineer-in-Charge. (One time payment shall be made for providing Scaffolding net from start of work till completion of work including shifting if any. The Scaffolding net shall be the property of the contractor on completion of the work)

Item number
26.81
Analysis basis
300 sqm
Priced inputs
4
Derived rate
₹29.25/ SQM
D-01/RATE ANALYSISITEM 26.81

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.81 (Providing and fixing Scaffolding net of required width made of high density Polyethylene UV stabilized knitted on warp knitting machines having density 100grams/sqm and shading coefficient minimum 75% around the construction site/ for vertical extension as per requirement including fastening/tying with building/scaffolding pipes or with any other fixtures etc. complete as per direction of Engineer-in-Charge. (One time payment shall be made for providing Scaffolding net from start of work till completion of work including shifting if any. The Scaffolding net shall be the property of the contractor on completion of the work)) is derived from 4 priced inputs for 300 sqm and works out to ₹29.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIALS:
  • LABOUR:
ANALYSIS OF RATES · ITEM 26.81DETAILS OF COST FOR 300 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8761MATScaffolding netScaffolding net made of high density polyethylene UV stabilized having density 100 gm/sqmsqm30024.007,200.00
9999MATCarriageL.S.32.276.81
0114LABBeldarday1736.00736.00
9999MATSundries for tying the netL.S.102.2722.70
BUILD-UP TO RATE
Less Salvage value taken 25% on (P)
-1,800.00
Total
6,165.51
Add 1% for water charges
+61.66
Total
6,227.17
Add GST on “X” (multiplying factor 0.2127)
+1,324.52
Total
7,551.69
Add CPOH @ 15% on “Y”
+1,132.75
Total
8,684.44
Add Cess @ 1% on “Z”
+86.84
Cost of 300 Sqm.
8,771.28
Cost of 1 Sqm.
29.24
SAY
₹29.25
D-02/SOURCEPRINTED PAGE 2021
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
2021

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2021. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.