CPWD Analysis of Rates · New Technologies and Materials

Providing and fixing Scaffolding net of required width made of high density Polyethylene UV stabilized knitted on warp knitting machines having density 100grams/sqm and shading coefficient minimum 75% around the construction site/ for vertical extension as per requirement including fastening/tying with building/scaffolding pipes or with any other fixtures etc. complete as per direction of Engineer-in-Charge. (One time payment shall be made for providing Scaffolding net from start of work till completion of work including shifting if any. The Scaffolding net shall be the property of the contractor on completion of the work)

Item number
26.81
Analysis basis
Details of cost for 300 sqm.
Priced inputs
4
Derived rate
29.25 / Sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.81 Providing and fixing Scaffolding net of required width made of high density Polyethylene UV stabilized knitted on warp knitting machines having density 100grams/sqm and shading coefficient minimum 75% around the construction site/ for vertical extension as per requirement including fastening/tying with building/scaffolding pipes or with any other fixtures etc. complete as per direction of Engineer-in-Charge. (One time payment shall be made for providing Scaffolding net from start of work till completion of work including shifting if any. The Scaffolding net shall be the property of the contractor on completion of the work) — is derived from 4 priced inputs for 300 sqm and works out to ₹29.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • MATERIALS:
  • LABOUR:
CodeInputUnitQuantityRate (INR)Amount (INR)
8761Scaffolding netScaffolding net made of high density polyethylene UV stabilized having density 100 gm/sqmMaterialsqm30024.007,200.00
9999CarriageMaterialL.S.32.276.81
0114BeldarLabourday1736.00736.00
9999Sundries for tying the netMaterialL.S.102.2722.70
Less Salvage value taken 25% on (P)
-1,800.00
Total
6,165.51
Add 1% for water charges
61.66
Total
6,227.17
Add GST on “X” (multiplying factor 0.2127)
1,324.52
Total
7,551.69
Add CPOH @ 15% on “Y”
1,132.75
Total
8,684.44
Add Cess @ 1% on “Z”
86.84
Cost of 300 Sqm.
8,771.28
Cost of 1 Sqm.
29.24
Say
29.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2021. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.