CPWD Analysis of Rates · New Technologies and Materials
Providing and laying rigid EPS (cellular plastic material) blocks conforming to ASTM standards/ specifications of minimum density 21.60 Kg/cum on floors, steps, stage etc. of required size and shape as per direction of the Engineer-in-Charge. This shall include the following operation. The EPS blocks shall be cut to required shape and sizes including cuttings for passing of services, joined together with synthetic resin adhesives as per relevant specifications and packed/placed in position for stepped floor or platform formation. The top and sides surfaces to be provided with GI woven wire mesh of aperture 5.45 mm (with wire dia 0.90 mm) secured to EPS blocks with wire pins/clips. Horizontal top surface to be provided with 20 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate upto 6mm chippings) and vertical surface to be provided with 12mm cement plaster 1:4 (1 cement : 4 coarse sand). The concrete/plastered surfaces so prepared shall be scratched with wire brushes to form burrs, so as to act as base for flooring or veneering/panelling to be done later as per approved design (which shall be paid for separately complete as per direction of the Engineer-in-Charge
- Item number
- 26.82
- Analysis basis
- Details of cost for a Lecture Hall of area
- Priced inputs
- 10
- Derived rate
- ₹2,293.30 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.82 — Providing and laying rigid EPS (cellular plastic material) blocks conforming to ASTM standards/ specifications of minimum density 21.60 Kg/cum on floors, steps, stage etc. of required size and shape as per direction of the Engineer-in-Charge. This shall include the following operation. The EPS blocks shall be cut to required shape and sizes including cuttings for passing of services, joined together with synthetic resin adhesives as per relevant specifications and packed/placed in position for stepped floor or platform formation. The top and sides surfaces to be provided with GI woven wire mesh of aperture 5.45 mm (with wire dia 0.90 mm) secured to EPS blocks with wire pins/clips. Horizontal top surface to be provided with 20 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate upto 6mm chippings) and vertical surface to be provided with 12mm cement plaster 1:4 (1 cement : 4 coarse sand). The concrete/plastered surfaces so prepared shall be scratched with wire brushes to form burrs, so as to act as base for flooring or veneering/panelling to be done later as per approved design (which shall be paid for separately complete as per direction of the Engineer-in-Charge — is derived from 10 priced inputs for a Lecture and works out to ₹2,293.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 8.40 x 16.00= 134.40 Sqm
- Assuming stepped floor for a Lecture Hall
- having 8 rows and each row by 100mm
- higher than the previous one. (Assuming 8
- rows 1.50 meter wide and four columns also
- 1.5 meter wide with 1.2 meter wide passage
- between row 1 and 2, 3 and 4 and front
- lecturer pedestrian.
- EPS blocks in sizes of = 1.20x1.20x0.10 m
- 8.40 m x 12 m x 0.45 m = 45.90 cum
- 8.40 m x 3 m x 0.15 m = 3.78 cum
- 49.68 cum Say = 50.00 cum
- 50 cum @ 21.60 Kg/cum. Total = 1080.00
- kg
- GI woven mesh of aperture 5.45 mm (with
- wire of dia 0.90 mm = 134.40 sqm + 13.60
- sqm = 150.00 sqm @ 1.61 Kg/sqm. Total =
- 241.50 kgs
- considering 1/6th area for adhesive i.e. 84
- sqm @ 100 Gm/sqm. Total = 8.50 kgs
- Labour:- For cutting arranging & packing the
- EPS blocks in position including jointing with
- SR adhesive and making arranging/cutting
- for fixing of services and fixing IRC welded
- mesh to EPS blocks.
- Cement concrete 1:2:4 (1 cement : 2 cement sand : 4 graded stone clippings upto 6
- mm size)
- 134.4x0.025 = 3.36 cum
- 12mm cement plaster 1:4 (1 cement : 4
- coarse sand)
- Total surface area to be joined 504 sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 5744 | EPS blocksMaterial | kg | 1,080 | 160.00 | 1,72,800.00 |
| 5745 | GI woven mesh of aperture 5.45 mm (with wire of dia 0.90 mmGI woven mesh of aperture 5.45 mm (with wire of dia 0.90 mm)Material | kg | 241.5 | 65.00 | 15,697.50 |
| 5746 | SR adhesive for joining EPS blocksMaterial | kg | 8.5 | 190.00 | 1,615.00 |
| 9999 | Wire pins/clips to secure IRC mesh to EPS blocksMaterial | L.S. | 675 | 2.27 | 1,532.25 |
| 9999 | T&P sundries i/c cutting tools etc.Material | L.S. | 340 | 2.27 | 771.80 |
| 0156 | Fitter/Carpenter (average)Carpenter (average)Labour | day | 2 | 857.00 | 1,714.00 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
| Rate as per item no 4.1.3 SH:4 (Cement Concrete)Rate as per item 4.1.3Sub-analysis | cum | 3.36 | 7,878.50 | 26,471.76 | |
| Rate as per item no 13.4.1 SH:13 (Finishing)Rate as per item 13.4.1Sub-analysis | sqm | 9.24 | 357.35 | 3,301.91 | |
| 0155 | Mason (average) for making burrsMason (average)Labour | day | 1 | 857.00 | 857.00 |
- Total
- 2,25,497.22
- Add 1 % Water charges on “W-A”
- 1,957.24
- TOTAL
- 2,27,454.46
- Add GST on “X-A” (multiplying factor 0.2127)
- 42,046.70
- TOTAL
- 2,69,501.16
- Add 15% CPOH on “Y-A”
- 35,959.12
- TOTAL
- 3,05,460.28
- Add Cess @ 1% on “Z-A”
- 2,756.87
- Cost of 134.40 sqm
- 3,08,217.15
- Cost of 1 sqm
- 2,293.28
- Say
- 2,293.30
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2022. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works