Providing & Applying weather proof sealant on outer joints of approved make conforming to IS & directed by Engineer-in-charge

Sealant 25mmx10mm at joints
Item number
26.78.1
Priced inputs
4
Derived rate
₹178.95/ METRE
D-01/RATE ANALYSISITEM 26.78.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.78.1 (Providing & Applying weather proof sealant on outer joints of approved make conforming to IS & directed by Engineer-in-charge Sealant 25mmx10mm at joints) is derived from 4 priced inputs and works out to ₹178.95 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Detail of material required for = 1.00 metre
  • including 5 % wastage
ANALYSIS OF RATES · ITEM 26.78.1
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8646MATSilicon sealant (including 5% wastage)Weather Silicon sealantcartridge0.87125.00108.75
8654MATMasking tapemetre22.004.00
9999MATScaffolding, hire charge etc.L.S.2.872.276.51
9999MATSundriesL.S.2.872.276.51
BUILD-UP TO RATE
TOTAL
125.77
Add 1 % Water charges on “W”
+1.26
TOTAL
127.03
Add GST on “X” (multiplying factor 0.2127)
+27.02
TOTAL
154.05
Add 15% CPOH on “Y”
+23.11
TOTAL
177.16
Add Cess @ 1% on “Z”
+1.77
Cost of 1 metre
178.93
SAY
₹178.95
D-02/SOURCEPRINTED PAGE 2019
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
2019

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2019. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.