Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.79.1 (Providing & Laying of levelling sim pads required sizes (5x5cm to 10x10cm) of PVC / Rubber to adjust level of bearing surface of supporting members as per the direction of Engineer in charge 2mm thick) is derived from 4 priced inputs for 100 Nos and works out to ₹28.90 each after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 26.79.1DETAIL OF COST FOR 100 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0246MAT2 mm thick sim padeach10011.001,100.00
9977MATCarriage of materialL.S.52.2711.35
0116LABFitter (Grade-1)Fitter (grade 1)day1897.00897.00
9999MATSundriesL.S.102.2722.70
BUILD-UP TO RATE
TOTAL
2,031.05
Add 1 % Water charges on “W”
+20.31
TOTAL
2,051.36
Add GST on “X” (multiplying factor 0.2127)
+436.32
TOTAL
2,487.68
Add 15% CPOH on “Y”
+373.15
TOTAL
2,860.83
Add Cess @ 1% on “Z”
+28.61
Cost for100 Nos.
2,889.44
Cost of each
28.89
SAY
₹28.90
D-02/SOURCEPRINTED PAGE 2019
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
2019

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2019. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.