Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor
- Item number
- 26.77.3
- Analysis basis
- 18 Cum
- Priced inputs
- 13
- Derived rate
- ₹2,720.30/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.77.3 (Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor Solid concrete wall elements) is derived from 13 priced inputs for 18 Cum and works out to ₹2,720.30 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Considering volume of different type of
- elements
- wall elements = 15 cum (13 nos)
- Beams / portal = 3 cum (02 nos)
- Total no of elements = 15 nos
- Labour cost
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0072 | MACH | Cost for crane (50 MT) duration 01 dayCost for crane having capacity 50MT | day | 1 | 9,500.00 | 9,500.00 |
| 9999 | MAT | Shifting of elements | L.S. | 434 | 2.27 | 985.18 |
| 9999 | MAT | Hire charges of props & Misc for 3 days (3x3 = 9 / pc) | L.S. | 780 | 2.27 | 1,770.60 |
| 1027 | MAT | Erection Bolts ( Minimum 04 nos for each element) | each | 60 | 25.00 | 1,500.00 |
| 0070 | MACH | Genrator hiring 100kvaGenerator 100 KVA/125 KVA | hour | 8 | 350.00 | 2,800.00 |
| 0111 | LAB | Carpenter 1st class | day | 2 | 897.00 | 1,794.00 |
| 0112 | LAB | Carpenter 2nd class | day | 2 | 816.00 | 1,632.00 |
| 0116 | LAB | Fitter (grade 1) | day | 2 | 897.00 | 1,794.00 |
| 0130 | LAB | Mistry | day | 3 | 897.00 | 2,691.00 |
| 0116 | LAB | Fitter (grade 1) | day | 2 | 897.00 | 1,794.00 |
| 0114 | LAB | Beldar | day | 8 | 736.00 | 5,888.00 |
| 9999 | MAT | Scaffolding, hire charge of drill machine etc. | L.S. | 500 | 2.27 | 1,135.00 |
| 9999 | MAT | Sundries (Miscellaneous tools and lifting slings) | L.S. | 500 | 2.27 | 1,135.00 |
- TOTAL
- 34,418.78
- Add 1 % Water charges on “W”
- +344.19
- TOTAL
- 34,762.97
- Add GST on “X” (multiplying factor 0.2127)
- +7,394.08
- TOTAL
- 42,157.05
- Add 15% CPOH on “Y”
- +6,323.56
- TOTAL
- 48,480.61
- Add Cess @ 1% on “Z”
- +484.81
- Cost for 18 cum
- 48,965.42
- Cost of 1 cum
- 2,720.30
- SAY
- ₹2,720.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 2018
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2018. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.