Skip to main content

Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor

Solid concrete wall elements
Item number
26.77.3
Analysis basis
18 Cum
Priced inputs
13
Derived rate
₹2,720.30/ CUM
D-01/RATE ANALYSISITEM 26.77.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.77.3 (Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor Solid concrete wall elements) is derived from 13 priced inputs for 18 Cum and works out to ₹2,720.30 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Considering volume of different type of
  • elements
  • wall elements = 15 cum (13 nos)
  • Beams / portal = 3 cum (02 nos)
  • Total no of elements = 15 nos
  • Labour cost
ANALYSIS OF RATES · ITEM 26.77.3DETAIL OF COST FOR 18 CUM. / DAY
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0072MACHCost for crane (50 MT) duration 01 dayCost for crane having capacity 50MTday19,500.009,500.00
9999MATShifting of elementsL.S.4342.27985.18
9999MATHire charges of props & Misc for 3 days (3x3 = 9 / pc)L.S.7802.271,770.60
1027MATErection Bolts ( Minimum 04 nos for each element)each6025.001,500.00
0070MACHGenrator hiring 100kvaGenerator 100 KVA/125 KVAhour8350.002,800.00
0111LABCarpenter 1st classday2897.001,794.00
0112LABCarpenter 2nd classday2816.001,632.00
0116LABFitter (grade 1)day2897.001,794.00
0130LABMistryday3897.002,691.00
0116LABFitter (grade 1)day2897.001,794.00
0114LABBeldarday8736.005,888.00
9999MATScaffolding, hire charge of drill machine etc.L.S.5002.271,135.00
9999MATSundries (Miscellaneous tools and lifting slings)L.S.5002.271,135.00
BUILD-UP TO RATE
TOTAL
34,418.78
Add 1 % Water charges on “W”
+344.19
TOTAL
34,762.97
Add GST on “X” (multiplying factor 0.2127)
+7,394.08
TOTAL
42,157.05
Add 15% CPOH on “Y”
+6,323.56
TOTAL
48,480.61
Add Cess @ 1% on “Z”
+484.81
Cost for 18 cum
48,965.42
Cost of 1 cum
2,720.30
SAY
₹2,720.30
D-02/SOURCEPRINTED PAGE 2018
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
2018

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2018. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.