Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor

Solid concrete wall elements

Item number
26.77.3
Analysis basis
Detail of cost for 18 Cum. / Day
Priced inputs
13
Derived rate
2,720.30 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.77.3 Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor Solid concrete wall elements — is derived from 13 priced inputs for 18 Cum and works out to ₹2,720.30 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Considering volume of different type of
  • elements
  • wall elements = 15 cum (13 nos)
  • Beams / portal = 3 cum (02 nos)
  • Total no of elements = 15 nos
  • Labour cost
CodeInputUnitQuantityRate (INR)Amount (INR)
0072Cost for crane (50 MT) duration 01 dayCost for crane having capacity 50MTMachineryday19,500.009,500.00
9999Shifting of elementsMaterialL.S.4342.27985.18
9999Hire charges of props & Misc for 3 days (3x3 = 9 / pc)MaterialL.S.7802.271,770.60
1027Erection Bolts ( Minimum 04 nos for each element)Materialeach6025.001,500.00
0070Genrator hiring 100kvaGenerator 100 KVA/125 KVAMachineryhour8350.002,800.00
0111Carpenter 1st classLabourday2897.001,794.00
0112Carpenter 2nd classLabourday2816.001,632.00
0116Fitter (grade 1)Labourday2897.001,794.00
0130MistryLabourday3897.002,691.00
0116Fitter (grade 1)Labourday2897.001,794.00
0114BeldarLabourday8736.005,888.00
9999Scaffolding, hire charge of drill machine etc.MaterialL.S.5002.271,135.00
9999Sundries (Miscellaneous tools and lifting slings)MaterialL.S.5002.271,135.00
TOTAL
34,418.78
Add 1 % Water charges on “W”
344.19
TOTAL
34,762.97
Add GST on “X” (multiplying factor 0.2127)
7,394.08
TOTAL
42,157.05
Add 15% CPOH on “Y”
6,323.56
TOTAL
48,480.61
Add Cess @ 1% on “Z”
484.81
Cost for 18 cum
48,965.42
Cost of 1 cum
2,720.30
Say
2,720.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2018. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works