Skip to main content

Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor

Prestressed hollow core slab above 200 mm up to 400 mm thickness
Item number
26.77.2
Analysis basis
120 Sqm
Priced inputs
9
Derived rate
₹345.15/ SQM
D-01/RATE ANALYSISITEM 26.77.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.77.2 (Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor Prestressed hollow core slab above 200 mm up to 400 mm thickness) is derived from 9 priced inputs for 120 Sqm and works out to ₹345.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Length of element can be more than 8.00
  • metre and upto 14.00 metres.
  • Labour cost for erection
ANALYSIS OF RATES · ITEM 26.77.2DETAIL OF COST FOR 120 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0067MACHCost for crane upto 80 tonne capacityday116,800.0016,800.00
9999MATHire charges of props & MiscL.S.3472.27787.69
0070MACHGenrator hiring 100kvaGenerator 100 KVA/125 KVAhour8350.002,800.00
0111LABCarpenter 1st classday1897.00897.00
0112LABCarpenter 2nd classday2816.001,632.00
0116LABFitter (grade 1)day2897.001,794.00
0130LABMistryday2897.001,794.00
0114LABBeldarday2736.001,472.00
9999MATSundries (Miscellaneous tools and lifting slings)L.S.5002.271,135.00
BUILD-UP TO RATE
TOTAL
29,111.69
Add 1 % Water charges on “W”
+291.12
TOTAL
29,402.81
Add GST on “X” (multiplying factor 0.2127)
+6,253.98
TOTAL
35,656.79
Add 15% CPOH on “Y”
+5,348.52
TOTAL
41,005.31
Add Cess @ 1% on “Z”
+410.05
Cost for 120 Sqm
41,415.36
Cost of 1 Sqm
345.13
SAY
₹345.15
D-02/SOURCEPRINTED PAGE 2018
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
2018

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2018. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.