Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor
- Item number
- 26.77.2
- Analysis basis
- 120 Sqm
- Priced inputs
- 9
- Derived rate
- ₹345.15/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.77.2 (Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor Prestressed hollow core slab above 200 mm up to 400 mm thickness) is derived from 9 priced inputs for 120 Sqm and works out to ₹345.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Length of element can be more than 8.00
- metre and upto 14.00 metres.
- Labour cost for erection
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0067 | MACH | Cost for crane upto 80 tonne capacity | day | 1 | 16,800.00 | 16,800.00 |
| 9999 | MAT | Hire charges of props & Misc | L.S. | 347 | 2.27 | 787.69 |
| 0070 | MACH | Genrator hiring 100kvaGenerator 100 KVA/125 KVA | hour | 8 | 350.00 | 2,800.00 |
| 0111 | LAB | Carpenter 1st class | day | 1 | 897.00 | 897.00 |
| 0112 | LAB | Carpenter 2nd class | day | 2 | 816.00 | 1,632.00 |
| 0116 | LAB | Fitter (grade 1) | day | 2 | 897.00 | 1,794.00 |
| 0130 | LAB | Mistry | day | 2 | 897.00 | 1,794.00 |
| 0114 | LAB | Beldar | day | 2 | 736.00 | 1,472.00 |
| 9999 | MAT | Sundries (Miscellaneous tools and lifting slings) | L.S. | 500 | 2.27 | 1,135.00 |
- TOTAL
- 29,111.69
- Add 1 % Water charges on “W”
- +291.12
- TOTAL
- 29,402.81
- Add GST on “X” (multiplying factor 0.2127)
- +6,253.98
- TOTAL
- 35,656.79
- Add 15% CPOH on “Y”
- +5,348.52
- TOTAL
- 41,005.31
- Add Cess @ 1% on “Z”
- +410.05
- Cost for 120 Sqm
- 41,415.36
- Cost of 1 Sqm
- 345.13
- SAY
- ₹345.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 2018
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2018. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.