Skip to main content

CPWD Analysis of Rates · New Technologies and Materials

Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor

Prestressed hollow core slab above 200 mm up to 400 mm thickness

Item number
26.77.2
Analysis basis
Detail of cost for 120 Sqm.
Priced inputs
9
Derived rate
345.15 / Sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.77.2 Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor Prestressed hollow core slab above 200 mm up to 400 mm thickness — is derived from 9 priced inputs for 120 Sqm and works out to ₹345.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Length of element can be more than 8.00
  • metre and upto 14.00 metres.
  • Labour cost for erection
CodeInputUnitQuantityRate (INR)Amount (INR)
0067Cost for crane upto 80 tonne capacityMachineryday116,800.0016,800.00
9999Hire charges of props & MiscMaterialL.S.3472.27787.69
0070Genrator hiring 100kvaGenerator 100 KVA/125 KVAMachineryhour8350.002,800.00
0111Carpenter 1st classLabourday1897.00897.00
0112Carpenter 2nd classLabourday2816.001,632.00
0116Fitter (grade 1)Labourday2897.001,794.00
0130MistryLabourday2897.001,794.00
0114BeldarLabourday2736.001,472.00
9999Sundries (Miscellaneous tools and lifting slings)MaterialL.S.5002.271,135.00
TOTAL
29,111.69
Add 1 % Water charges on “W”
291.12
TOTAL
29,402.81
Add GST on “X” (multiplying factor 0.2127)
6,253.98
TOTAL
35,656.79
Add 15% CPOH on “Y”
5,348.52
TOTAL
41,005.31
Add Cess @ 1% on “Z”
410.05
Cost for 120 Sqm
41,415.36
Cost of 1 Sqm
345.13
Say
345.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2018. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works