CPWD Analysis of Rates · New Technologies and Materials

Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor

Prestressed hollow core Slab up to 200 mm thickness

Item number
26.77.1
Analysis basis
Detail of cost for 150 Sqm.
Priced inputs
9
Derived rate
203.50 / Sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.77.1 Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor Prestressed hollow core Slab up to 200 mm thickness — is derived from 9 priced inputs for 150 Sqm and works out to ₹203.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Length of element can be upto 8.00 metres.
  • Mobile crane (Tyre mounted) upto 25m
  • height 100 feet boom
  • Labour cost for erection
CodeInputUnitQuantityRate (INR)Amount (INR)
0044Cost for crane upto 40 tonne capacityHire & running charge for crane upto 40 tonne capacityMachineryday18,950.008,950.00
9999Hire charges of props & MiscMaterialL.S.4342.27985.18
0070Genrator hiring 100kvaGenerator 100 KVA/125 KVAMachineryhour8350.002,800.00
0111Carpenter 1st classLabourday1897.00897.00
0112Carpenter 2nd classLabourday2816.001,632.00
0116Fitter (grade 1)Labourday2897.001,794.00
0130MistryLabourday2897.001,794.00
0114BeldarLabourday2736.001,472.00
9999Sundries (Miscellaneous tools and lifting slings)MaterialL.S.5002.271,135.00
TOTAL
21,459.18
Add 1 % Water charges on “W”
214.59
TOTAL
21,673.77
Add GST on “X” (multiplying factor 0.2127)
4,610.01
TOTAL
26,283.78
Add 15% CPOH on “Y”
3,942.57
TOTAL
30,226.35
Add Cess @ 1% on “Z”
302.26
Cost for 150 Sqm
30,528.61
Cost of 1 Sqm
203.52
Say
203.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2017. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works