Transportation of Precast Elements by flat bed Trailor (Double / Triple axle 40ft Length with proper accessories like A frame etc) from factory, including the cost of loading , unloading & stacking at site with the help of required capacity cranes

Add/Deduct over item 26.76.1 for every additional lead of 5 km
Item number
26.76.2
Priced inputs
2
Derived rate
₹117.30/ MT
D-01/RATE ANALYSISITEM 26.76.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.76.2 (Transportation of Precast Elements by flat bed Trailor (Double / Triple axle 40ft Length with proper accessories like A frame etc) from factory, including the cost of loading , unloading & stacking at site with the help of required capacity cranes Add/Deduct over item 26.76.1 for every additional lead of 5 km) is derived from 2 priced inputs and works out to ₹117.30 per mt after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Extra for lead 5 km
ANALYSIS OF RATES · ITEM 26.76.2
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
9999MATCharges of Trailors having capcity 22MT including cost of fuel & driver and maintenanceL.S.5792.271,314.33
9999MATsundriesL.S.2202.27499.40
BUILD-UP TO RATE
TOTAL
1,813.73
Add 1 % Water charges on “W”
+18.14
TOTAL
1,831.87
Add GST on “X” (multiplying factor 0.2127)
+389.64
TOTAL
2,221.51
Add 15% CPOH on “Y”
+333.23
TOTAL
2,554.74
Add Cess @ 1% on “Z”
+25.55
Cost for 22 MT
2,580.29
Cost of 1 MT
117.29
SAY
₹117.30
D-02/SOURCEPRINTED PAGE 2017
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
2017

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2017. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.