CPWD Analysis of Rates · New Technologies and Materials
Transportation of Precast Elements by flat bed Trailor (Double / Triple axle 40ft Length with proper accessories like A frame etc) from factory, including the cost of loading , unloading & stacking at site with the help of required capacity cranes
Add/Deduct over item 26.76.1 for every additional lead of 5 km
- Item number
- 26.76.2
- Priced inputs
- 2
- Derived rate
- ₹117.30 / MT
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.76.2 — Transportation of Precast Elements by flat bed Trailor (Double / Triple axle 40ft Length with proper accessories like A frame etc) from factory, including the cost of loading , unloading & stacking at site with the help of required capacity cranes Add/Deduct over item 26.76.1 for every additional lead of 5 km — is derived from 2 priced inputs and works out to ₹117.30 per mt after water charges, GST, CPOH and cess. The full build-up is below.
- Extra for lead 5 km
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 9999 | Charges of Trailors having capcity 22MT including cost of fuel & driver and maintenanceMaterial | L.S. | 579 | 2.27 | 1,314.33 |
| 9999 | sundriesMaterial | L.S. | 220 | 2.27 | 499.40 |
- TOTAL
- 1,813.73
- Add 1 % Water charges on “W”
- 18.14
- TOTAL
- 1,831.87
- Add GST on “X” (multiplying factor 0.2127)
- 389.64
- TOTAL
- 2,221.51
- Add 15% CPOH on “Y”
- 333.23
- TOTAL
- 2,554.74
- Add Cess @ 1% on “Z”
- 25.55
- Cost for 22 MT
- 2,580.29
- Cost of 1 MT
- 117.29
- Say
- 117.30
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2017. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works