Transportation of Precast Elements by flat bed Trailor (Double / Triple axle 40ft Length with proper accessories like A frame etc) from factory, including the cost of loading , unloading & stacking at site with the help of required capacity cranes

Lead within 15km

Item number
26.76.1
Priced inputs
7
Derived rate
540.85 / MT

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.76.1 Transportation of Precast Elements by flat bed Trailor (Double / Triple axle 40ft Length with proper accessories like A frame etc) from factory, including the cost of loading , unloading & stacking at site with the help of required capacity cranes Lead within 15km — is derived from 7 priced inputs and works out to ₹540.85 per mt after water charges, GST, CPOH and cess. The full build-up is below.

  • Trailors having capcity 22MT
  • Hire charges of truck trailors
  • Number of trips in working day of 8 hours
  • N=8/{(2L/S)+2)}. Where L=Lead in Km.,
  • S=Speed in Km.per hour, 1 hour is allowed
  • for loading & 1 hour for unloading.
  • L= 15 km .
  • S= 15 km / hr
  • N=8/{(30/15)+2)}=02 Trips / day
CodeInputUnitQuantityRate (INR)Amount (INR)
9999Charges of Trailors having capcity 22MT including cost of fuel & driver cost and maintenanceMaterialL.S.1,7382.273,945.26
0028Hire charges of Crane capacity of 30MT for loading from stock yard and unloading at site for 120 MTHire and running charges of crane 20 tonne capacityMachineryday0.3677,850.002,880.95
0128MateLabourday0.5816.00408.00
0114BeldarLabourday0.5736.00368.00
9999wooden battens for tranporatationMaterialL.S.57.82.27131.21
9999Chain for packing & binding precast elementsMaterialL.S.57.82.27131.21
9999sundriesMaterialL.S.2202.27499.40
TOTAL
8,364.03
Add 1 % Water charges on “W”
83.64
TOTAL
8,447.67
Add GST on “X” (multiplying factor 0.2127)
1,796.82
TOTAL
10,244.49
Add 15% CPOH on “Y”
1,536.67
TOTAL
11,781.16
Add Cess @ 1% on “Z”
117.81
Cost for 22 MT
11,898.97
Cost of 1 MT
540.86
Say
540.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2016. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.