Transportation of Precast Elements by flat bed Trailor (Double / Triple axle 40ft Length with proper accessories like A frame etc) from factory, including the cost of loading , unloading & stacking at site with the help of required capacity cranes
- Item number
- 26.76.1
- Priced inputs
- 7
- Derived rate
- ₹540.85/ MT
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.76.1 (Transportation of Precast Elements by flat bed Trailor (Double / Triple axle 40ft Length with proper accessories like A frame etc) from factory, including the cost of loading , unloading & stacking at site with the help of required capacity cranes Lead within 15km) is derived from 7 priced inputs and works out to ₹540.85 per mt after water charges, GST, CPOH and cess. The full build-up is below.
- Trailors having capcity 22MT
- Hire charges of truck trailors
- Number of trips in working day of 8 hours
- N=8/{(2L/S)+2)}. Where L=Lead in Km.,
- S=Speed in Km.per hour, 1 hour is allowed
- for loading & 1 hour for unloading.
- L= 15 km .
- S= 15 km / hr
- N=8/{(30/15)+2)}=02 Trips / day
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 9999 | MAT | Charges of Trailors having capcity 22MT including cost of fuel & driver cost and maintenance | L.S. | 1,738 | 2.27 | 3,945.26 |
| 0028 | MACH | Hire charges of Crane capacity of 30MT for loading from stock yard and unloading at site for 120 MTHire and running charges of crane 20 tonne capacity | day | 0.367 | 7,850.00 | 2,880.95 |
| 0128 | LAB | Mate | day | 0.5 | 816.00 | 408.00 |
| 0114 | LAB | Beldar | day | 0.5 | 736.00 | 368.00 |
| 9999 | MAT | wooden battens for tranporatation | L.S. | 57.8 | 2.27 | 131.21 |
| 9999 | MAT | Chain for packing & binding precast elements | L.S. | 57.8 | 2.27 | 131.21 |
| 9999 | MAT | sundries | L.S. | 220 | 2.27 | 499.40 |
- TOTAL
- 8,364.03
- Add 1 % Water charges on “W”
- +83.64
- TOTAL
- 8,447.67
- Add GST on “X” (multiplying factor 0.2127)
- +1,796.82
- TOTAL
- 10,244.49
- Add 15% CPOH on “Y”
- +1,536.67
- TOTAL
- 11,781.16
- Add Cess @ 1% on “Z”
- +117.81
- Cost for 22 MT
- 11,898.97
- Cost of 1 MT
- 540.86
- SAY
- ₹540.85
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 2016
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2016. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.