CPWD Analysis of Rates · New Technologies and Materials

Fabrication and manufacturing of solid precast concrete element with provisions of shear keys, connecting loops, dowel tubes and proper lifting accessories for walls, beams, slabs, stairs, column etc, of various thickness, shape and size of different concrete grades manufactured in controlled factory environment with approved methodology including moulds (Pallet system, Tilts form, table moulds, battery moulds, vertical moulds, beam moulds, column moulds, staircase moulds, Facade mould, etc.), mixing, transporting and placing of concrete, vibrating, curing, finishing, making necessary cutout/holes of required sizes for services, yard handling & stacking all complete as per IS 11447:1985 and as per approved shop drawings and design mix as per the direction of Engineer-in-Charge (Cost of reinforcement, Mechanical, Electrical and Plumbing inserts will be paid separately). Note: Excess/less cement over the specified cement content used as per design mix is payable/recoverable separately)

Extra for using M-60 (Cement content 440 kg) instead of M-35

Item number
26.74.4
Priced inputs
2
Derived rate
573.20 / Cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.74.4 Fabrication and manufacturing of solid precast concrete element with provisions of shear keys, connecting loops, dowel tubes and proper lifting accessories for walls, beams, slabs, stairs, column etc, of various thickness, shape and size of different concrete grades manufactured in controlled factory environment with approved methodology including moulds (Pallet system, Tilts form, table moulds, battery moulds, vertical moulds, beam moulds, column moulds, staircase moulds, Facade mould, etc.), mixing, transporting and placing of concrete, vibrating, curing, finishing, making necessary cutout/holes of required sizes for services, yard handling & stacking all complete as per IS 11447:1985 and as per approved shop drawings and design mix as per the direction of Engineer-in-Charge (Cost of reinforcement, Mechanical, Electrical and Plumbing inserts will be paid separately). Note: Excess/less cement over the specified cement content used as per design mix is payable/recoverable separately) Extra for using M-60 (Cement content 440 kg) instead of M-35 — is derived from 2 priced inputs and works out to ₹573.20 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement for M-35 Mix = 0.370 T
  • Cement for M-60 Mix = 0.440 T
  • Difference 0.070 T
  • Plasticizer for M-35 Mix =7.400 Kgs
  • Plasticizer for M-60 Mix = 8.800 Kgs
  • Difference 1.400Kgs
CodeInputUnitQuantityRate (INR)Amount (INR)
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.075,156.00360.92
7318Plasticizer or Super Plasticizer 2% of cement contentPlasticizer / super plasticizerMaterialkg1.430.0042.00
TOTAL
402.92
Add 1 % Water charges on “W”
4.03
TOTAL
406.95
Add GST on “X” (multiplying factor 0.2127)
86.56
TOTAL
493.51
Add 15% CPOH on “Y”
74.03
TOTAL
567.54
Add Cess @ 1% on “Z”
5.68
Cost of 1.00 Cum
573.22
Say
573.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2014. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.