CPWD Analysis of Rates · New Technologies and Materials
Fabrication and manufacturing of solid precast concrete element with provisions of shear keys, connecting loops, dowel tubes and proper lifting accessories for walls, beams, slabs, stairs, column etc, of various thickness, shape and size of different concrete grades manufactured in controlled factory environment with approved methodology including moulds (Pallet system, Tilts form, table moulds, battery moulds, vertical moulds, beam moulds, column moulds, staircase moulds, Facade mould, etc.), mixing, transporting and placing of concrete, vibrating, curing, finishing, making necessary cutout/holes of required sizes for services, yard handling & stacking all complete as per IS 11447:1985 and as per approved shop drawings and design mix as per the direction of Engineer-in-Charge (Cost of reinforcement, Mechanical, Electrical and Plumbing inserts will be paid separately). Note: Excess/less cement over the specified cement content used as per design mix is payable/recoverable separately)
Extra for using M-50 (Cement content 425 kg) instead of M-35
- Item number
- 26.74.3
- Priced inputs
- 2
- Derived rate
- ₹450.40 / Cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.74.3 — Fabrication and manufacturing of solid precast concrete element with provisions of shear keys, connecting loops, dowel tubes and proper lifting accessories for walls, beams, slabs, stairs, column etc, of various thickness, shape and size of different concrete grades manufactured in controlled factory environment with approved methodology including moulds (Pallet system, Tilts form, table moulds, battery moulds, vertical moulds, beam moulds, column moulds, staircase moulds, Facade mould, etc.), mixing, transporting and placing of concrete, vibrating, curing, finishing, making necessary cutout/holes of required sizes for services, yard handling & stacking all complete as per IS 11447:1985 and as per approved shop drawings and design mix as per the direction of Engineer-in-Charge (Cost of reinforcement, Mechanical, Electrical and Plumbing inserts will be paid separately). Note: Excess/less cement over the specified cement content used as per design mix is payable/recoverable separately) Extra for using M-50 (Cement content 425 kg) instead of M-35 — is derived from 2 priced inputs and works out to ₹450.40 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Cement for M-35 Mix = 0.370 T
- Cement for M-50 Mix = 0.425 T
- Difference 0.055 T
- Plasticizer for M-35 Mix =7.400 Kgs
- Plasticizer for M-50 Mix = 8.500 Kgs
- Difference 1.100Kgs
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0367 | Portland CementPortland Cement (OPC-43 Grade)Material | tonne | 0.055 | 5,156.00 | 283.58 |
| 7318 | Plasticizer or Super Plasticizer 2% of cement contentPlasticizer / super plasticizerMaterial | kg | 1.1 | 30.00 | 33.00 |
- TOTAL
- 316.58
- Add 1 % Water charges on “W”
- 3.17
- TOTAL
- 319.75
- Add GST on “X” (multiplying factor 0.2127)
- 68.01
- TOTAL
- 387.76
- Add 15% CPOH on “Y”
- 58.16
- TOTAL
- 445.92
- Add Cess @ 1% on “Z”
- 4.46
- Cost of 1.00 Cum
- 450.38
- Say
- 450.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2014. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.