Skip to main content

Fabrication and manufacturing of solid precast concrete element with provisions of shear keys, connecting loops, dowel tubes and proper lifting accessories for walls, beams, slabs, stairs, column etc, of various thickness, shape and size of different concrete grades manufactured in controlled factory environment with approved methodology including moulds (Pallet system, Tilts form, table moulds, battery moulds, vertical moulds, beam moulds, column moulds, staircase moulds, Facade mould, etc.), mixing, transporting and placing of concrete, vibrating, curing, finishing, making necessary cutout/holes of required sizes for services, yard handling & stacking all complete as per IS 11447:1985 and as per approved shop drawings and design mix as per the direction of Engineer-in-Charge (Cost of reinforcement, Mechanical, Electrical and Plumbing inserts will be paid separately). Note: Excess/less cement over the specified cement content used as per design mix is payable/recoverable separately)

Extra for using M-40 (Cement content 400 kg) instead of M-35
Item number
26.74.2
Priced inputs
2
Derived rate
₹245.65/ CUM
D-01/RATE ANALYSISITEM 26.74.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.74.2 (Fabrication and manufacturing of solid precast concrete element with provisions of shear keys, connecting loops, dowel tubes and proper lifting accessories for walls, beams, slabs, stairs, column etc, of various thickness, shape and size of different concrete grades manufactured in controlled factory environment with approved methodology including moulds (Pallet system, Tilts form, table moulds, battery moulds, vertical moulds, beam moulds, column moulds, staircase moulds, Facade mould, etc.), mixing, transporting and placing of concrete, vibrating, curing, finishing, making necessary cutout/holes of required sizes for services, yard handling & stacking all complete as per IS 11447:1985 and as per approved shop drawings and design mix as per the direction of Engineer-in-Charge (Cost of reinforcement, Mechanical, Electrical and Plumbing inserts will be paid separately). Note: Excess/less cement over the specified cement content used as per design mix is payable/recoverable separately) Extra for using M-40 (Cement content 400 kg) instead of M-35) is derived from 2 priced inputs and works out to ₹245.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement for M-35 Mix = 0.370 T
  • Cement for M-40 Mix = 0.400 T
  • Difference 0.030 T
  • Plasticizer for M-35 Mix =7.400 Kgs
  • Plasticizer for M-40 Mix = 8.000 Kgs
  • Difference 0.600Kgs
ANALYSIS OF RATES · ITEM 26.74.2
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.035,156.00154.68
7318MATPlasticizer or Super Plasticizer 2% of cement contentPlasticizer / super plasticizerkg0.630.0018.00
BUILD-UP TO RATE
TOTAL
172.68
Add 1 % Water charges on “W”
+1.73
TOTAL
174.41
Add GST on “X” (multiplying factor 0.2127)
+37.10
TOTAL
211.51
Add 15% CPOH on “Y”
+31.73
TOTAL
243.24
Add Cess @ 1% on “Z”
+2.43
Cost of 1.00 Cum
245.67
SAY
₹245.65
D-02/SOURCEPRINTED PAGE 2013
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
2013

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2013. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.