Providing and fixing at Bamboo Mat board conforming to IS:13958-1994 for partition to frame by bucking or studding with screws etc. complete (Frames, backing or studding to be paid separately)

12mm thickness

Item number
26.6D.5
Analysis basis
Details of cost for 3.5mx2m = 7.0 sqm
Priced inputs
5
Derived rate
5,601.55

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.6D.5 Providing and fixing at Bamboo Mat board conforming to IS:13958-1994 for partition to frame by bucking or studding with screws etc. complete (Frames, backing or studding to be paid separately) 12mm thickness — is derived from 5 priced inputs and works out to ₹5,601.55 after water charges, GST, CPOH and cess. The full build-up is below.

  • Partition area = 7.0sqm, Add wastage @ 5%
  • = 0.35sqm, Total area = 7.35 sqm
  • MATERIAL:
  • Weight: 7.35sqm x 10.00 kgs/sqm =73.50
  • kgs = 0.07 tonne.
  • LABOUR:
CodeInputUnitQuantityRate (INR)Amount (INR)
815012mm thick Bamboo Mat Board conforming to IS 13958:199412 mm thick Bamboo Mat Board conforming to IS 13958:1994Materialsqm7.353,373.0024,791.55
2358Carriage of 12mm thick Bamboo mat board and accessoriesCarriage of Bamboo Mat corrugated sheets and accessoriesMaterialtonne0.0717,700.001,239.00
9999Sundries and screwsMaterialL.S.26.912.2761.09
0112Carpenter 2nd classLabourday0.9816.00734.40
0114BeldarLabourday1736.00736.00
TOTAL
27,562.04
Add 1 % Water charges on “W”
275.62
TOTAL
27,837.66
Add GST on “X” (multiplying factor 0.2127)
5,921.07
TOTAL
33,758.73
Add 15% CPOH on “Y”
5,063.81
TOTAL
38,822.54
Add Cess @ 1% on “Z”
388.23
Cost of 7 sqm
39,210.77
Cost of 1sqm
5,601.54
Say
5,601.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1916. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.