Providing and fixing at Bamboo Mat board conforming to IS:13958-1994 for partition to frame by bucking or studding with screws etc. complete (Frames, backing or studding to be paid separately)
- Item number
- 26.6D.3
- Analysis basis
- Details of cost for 3.5mx2m = 7.0 sqm
- Priced inputs
- 5
- Derived rate
- ₹3,923.65
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.6D.3 (Providing and fixing at Bamboo Mat board conforming to IS:13958-1994 for partition to frame by bucking or studding with screws etc. complete (Frames, backing or studding to be paid separately) 6mm thickness) is derived from 5 priced inputs and works out to ₹3,923.65 after water charges, GST, CPOH and cess. The full build-up is below.
- Partition area = 7.0sqm, Add wastage @ 5%
- = 0.35sqm, Total area = 7.35 sqm
- MATERIAL:
- Weight: 7.35sqm x 5.40 kgs/sqm =39.69 kgs
- = 0.04 tonne.
- LABOUR:
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8148 | MAT | 6mm thick Bamboo Mat Board conforming to IS 13958:19946 mm thick Bamboo Mat Board conforming to IS 13958:1994 | sqm | 7.35 | 2,322.00 | 17,066.70 |
| 2358 | MAT | Carriage of 6mm thick Bamboo mat board and accessoriesCarriage of Bamboo Mat corrugated sheets and accessories | tonne | 0.04 | 17,700.00 | 708.00 |
| 9999 | MAT | Sundries and screws | L.S. | 26.91 | 2.27 | 61.09 |
| 0112 | LAB | Carpenter 2nd class | day | 0.9 | 816.00 | 734.40 |
| 0114 | LAB | Beldar | day | 1 | 736.00 | 736.00 |
- TOTAL
- 19,306.19
- Add 1 % Water charges on “W”
- +193.06
- TOTAL
- 19,499.25
- Add GST on “X” (multiplying factor 0.2127)
- +4,147.49
- TOTAL
- 23,646.74
- Add 15% CPOH on “Y”
- +3,547.01
- TOTAL
- 27,193.75
- Add Cess @ 1% on “Z”
- +271.94
- Cost of 7 sqm
- 27,465.69
- Cost of 1sqm
- 3,923.67
- SAY
- ₹3,923.65
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1915
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1915. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.