Providing and fixing at Bamboo Mat board conforming to IS:13958-1994 for partition to frame by bucking or studding with screws etc. complete (Frames, backing or studding to be paid separately)

4mm thickness
Item number
26.6D.2
Analysis basis
Details of cost for 3.5mx2m = 7.0 sqm
Priced inputs
5
Derived rate
₹3,332.00
D-01/RATE ANALYSISITEM 26.6D.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.6D.2 (Providing and fixing at Bamboo Mat board conforming to IS:13958-1994 for partition to frame by bucking or studding with screws etc. complete (Frames, backing or studding to be paid separately) 4mm thickness) is derived from 5 priced inputs and works out to ₹3,332.00 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Partition area = 7.0sqm, Add wastage @ 5%
  • = 0.35sqm, Total area = 7.35 sqm
  • MATERIAL:
  • Weight: 7.35sqm x 3.70 kgs/sqm =27.195
  • kgs = 0.03 tonne.
  • LABOUR:
ANALYSIS OF RATES · ITEM 26.6D.2DETAILS OF COST FOR 3.5MX2M = 7.0 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8147MAT4mm thick Bamboo Mat Board conforming to IS 13958:19944 mm thick Bamboo Mat Board conforming to IS 13958:1994sqm7.351,950.0014,332.50
2358MATCarriage of 4mm thick Bamboo mat board and accessoriesCarriage of Bamboo Mat corrugated sheets and accessoriestonne0.0317,700.00531.00
9999MATSundries and screwsL.S.26.912.2761.09
0112LABCarpenter 2nd classday0.9816.00734.40
0114LABBeldarday1736.00736.00
BUILD-UP TO RATE
TOTAL
16,394.99
Add 1 % Water charges on “W”
+163.95
TOTAL
16,558.94
Add GST on “X” (multiplying factor 0.2127)
+3,522.09
TOTAL
20,081.03
Add 15% CPOH on “Y”
+3,012.15
TOTAL
23,093.18
Add Cess @ 1% on “Z”
+230.93
Cost of 7 sqm
23,324.11
Cost of 1sqm
3,332.02
SAY
₹3,332.00
D-02/SOURCEPRINTED PAGE 1914
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1914

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1914. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.