Skip to main content

CPWD Analysis of Rates · New Technologies and Materials

Providing and fixing in position ridges of 3.5 to 4 mm thick bamboo mat ridge cap (BMRC) as per IS: 15476-2004 in roofing with self drilling screws along with EPDM washers complete or with galvanized iron J or L hooks 8mm dia G.I. plain and bitumen washers etc, all complete as per direction of Engineer-in-Charge

Item number
26.6B
Analysis basis
Details of cost for length of ridge 18.50
Priced inputs
6
Derived rate
4,830.10 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.6B Providing and fixing in position ridges of 3.5 to 4 mm thick bamboo mat ridge cap (BMRC) as per IS: 15476-2004 in roofing with self drilling screws along with EPDM washers complete or with galvanized iron J or L hooks 8mm dia G.I. plain and bitumen washers etc, all complete as per direction of Engineer-in-Charge — is derived from 6 priced inputs for length of and works out to ₹4,830.10 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • metre (pair of 43cm width each)
  • Consider a shed of 18mx9m (external
  • dimensions of plinth). Length of ridge 18.50
  • metre.
  • MATERIAL:
  • Ridges (Male & female) of size: 1.05m
  • length required = 20 sets x 1.05m = 21.00
  • metre, Add wastage @ 5% = 1.05 metre,
  • Total length = 22.05 metre.
  • LABOUR:
CodeInputUnitQuantityRate (INR)Amount (INR)
8145Bamboo Mat Ridge cap 3.5 to 4mm thick conforming to IS 15476:2004Bamboo Mat Ridge cap 3.5 to 4 mm thick conforming to IS 15476:2004Materialmetre22.052,810.0061,960.50
9977Carriage (The ridges to be fixed with the same hooks as the sheets)MaterialL.S.19.432.2744.11
9999SundriesMaterialL.S.9.712.2722.04
0130MistryLabourday0.2897.00179.40
0112Carpenter 2nd classLabourday0.2816.00163.20
0114BeldarLabourday0.6736.00441.60
TOTAL
62,810.85
Add 1 % Water charges on “W”
628.11
TOTAL
63,438.96
Add GST on “X” (multiplying factor 0.2127)
13,493.47
TOTAL
76,932.43
Add 15% CPOH on “Y”
11,539.86
TOTAL
88,472.29
Add Cess @ 1% on “Z”
884.72
Cost of 18.50 metre
89,357.01
Cost of 1 metre
4,830.11
Say
4,830.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1912. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works