CPWD Analysis of Rates · New Technologies and Materials

Providing, erecting, laying and fixing in position in 3.5 to 4 mm thick bamboo mat corrugated sheet (BMCS) as per IS: 15476-2004 in roofing with self drilling screws along with EPDM washers complete or with galvanized iron J or L hooks 8mm dia G.I. plain and bitumen washers etc, all complete as per direction of Engineer-in-Charge

Item number
26.6A
Analysis basis
Details of cost for 181.30sqm area.
Priced inputs
10
Derived rate
6,012.10 / sqm area

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.6A Providing, erecting, laying and fixing in position in 3.5 to 4 mm thick bamboo mat corrugated sheet (BMCS) as per IS: 15476-2004 in roofing with self drilling screws along with EPDM washers complete or with galvanized iron J or L hooks 8mm dia G.I. plain and bitumen washers etc, all complete as per direction of Engineer-in-Charge — is derived from 10 priced inputs for 181.30sqm area and works out to ₹6,012.10 per sqm area after water charges, GST, CPOH and cess. The full build-up is below.

  • Consider a sheet of 18mx9m (external dimension of plinth). Area of roof = 18.5x9.8m
  • = 181.30 sqm.
  • MATERIAL:
  • Sheets used = 2x 19 nos (2.44m x 1.05m)
  • & 4x19 nos (1.83mx 1.05m). Total area
  • = (2x19x2.44x1.05)+(4x19x1.83x1.05) =
  • 243.39sqm, Add wastage @ 3% = 7.30
  • sqm, Total area = 250.69 sqm.
  • Weight of sheets, For 2.44mx1.05m sheet
  • size, 12kg/Nos x 38 nos = 456 kgs, For
  • 1.83m x 1.05m sheet size, 9kgs/Nos x 76
  • Nos = 684 kgs. Total weight of sheet =
  • 456+684 = 1140 kgs = 1.14 tonne
  • LABOUR:
CodeInputUnitQuantityRate (INR)Amount (INR)
8144Bamboo Mat corrugated sheets 3.5 to 4mm thick conforming to IS 15476:2004Bamboo Mat corrugated sheets 3.5 to 4 mm thick conforming to IS 15476:2004Materialsqm250.692,891.007,24,744.79
2358Carriage of Bamboo Mat corrugated sheets and accessoriesMaterialtonne1.1417,700.0020,178.00
1023Galvanized steel J or L hooks 8mm diaGalvanised steel J or L hooks 8 mm diaMaterial10 Nos68.4130.008,892.00
1208Bitumen washerMaterial100 Nos6.8430.00205.20
1209G.I. plain washer thickMaterial100 Nos6.8435.00239.40
9977Carriage of bolts and washersMaterialL.S.11.582.2726.29
9999SundriesMaterialL.S.56.782.27128.89
0130MistryLabourday3897.002,691.00
0112Carpenter 2nd classLabourday3816.002,448.00
0114BeldarLabourday9736.006,624.00
TOTAL
7,66,177.57
Add 1 % Water charges on “W”
7,661.78
TOTAL
7,73,839.35
Add GST on “X” (multiplying factor 0.2127)
1,64,595.63
TOTAL
9,38,434.98
Add 15% CPOH on “Y”
1,40,765.25
TOTAL
10,79,200.23
Add Cess @ 1% on “Z”
10,792.00
Cost of 181.30 sqm
10,89,992.23
Cost of 1sqm
6,012.09
Say
6,012.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1911. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.