CPWD Analysis of Rates · New Technologies and Materials

Providing & fixing in position 65 mm thick factory made door frame of Phenol bonded Bamboo wood (superior class, interior use), in approved colour, texture and finish.The bamboo wood shall have minimum density of 1000 Kg/cum, minimum hardness 1000 Kgf. The door frame shall have tenon & mortise interlocking system, to be fixed to the wall with 100 mm size G.I screws all a complete as per direction of Engineer-in charge

Item number
26.6
Analysis basis
Detail of cost for 33 cudm
Priced inputs
3
Derived rate
325.95 / cudm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.6 Providing & fixing in position 65 mm thick factory made door frame of Phenol bonded Bamboo wood (superior class, interior use), in approved colour, texture and finish.The bamboo wood shall have minimum density of 1000 Kg/cum, minimum hardness 1000 Kgf. The door frame shall have tenon & mortise interlocking system, to be fixed to the wall with 100 mm size G.I screws all a complete as per direction of Engineer-in charge — is derived from 3 priced inputs for 33 cudm and works out to ₹325.95 per cudm after water charges, GST, CPOH and cess. The full build-up is below.

  • 2x206.75x9.5x6.5 cm = 0.0255 cum +
  • 1x117.50x9.5x6.5 cm = 0.0072 cum
  • Total = 0.033 cum = 33 cudm
  • + 0.001 cum (Add for wastage @ 5%)
  • Grand total = 0.034 cum = 34 Cudm
CodeInputUnitQuantityRate (INR)Amount (INR)
8030Superior class Bamboo wood door frame 65 mm thickSuperior class Bamboo wood door frame 65 mm thick,Material10 cudm3.42,018.756,863.75
0111Carpenter 1st classLabourday0.72897.00645.84
0114BeldarLabourday0.07736.0051.52
TOTAL
7,561.11
Add 1 % Water charges on “W”
75.61
TOTAL
7,636.72
Add GST on “X” (multiplying factor 0.2127)
1,624.33
TOTAL
9,261.05
Add 15% CPOH on “Y”
1,389.16
TOTAL
10,650.21
Add Cess @ 1% on “Z”
106.50
Cost of 33 cudm
10,756.71
Cost of 1 cudm
325.96
Say
325.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1911. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works