CPWD Analysis of Rates · New Technologies and Materials

Providing & fixing in position Phenol bonded Bamboo wood panelling of 10mm thick, in 25 to 40 mm thick panelled or panelled & glazed shutters for doors, windows, clerestorey windows, in approved colour, texture & finish. The bamboowood planks shall have minimum density of 1000 Kg/cum & minimum Hardness 1000 Kgf. The panels shall have profiled interlocking system locked in place with bamboo pins all complete as per direction of the Engineer in-charge. (area of opening for panel inserts excluding portion inside grooves or rebates to be measured)

Item number
26.5
Analysis basis
Details of cost for shutters of a door with
Priced inputs
3
Derived rate
4,555.75 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.5 Providing & fixing in position Phenol bonded Bamboo wood panelling of 10mm thick, in 25 to 40 mm thick panelled or panelled & glazed shutters for doors, windows, clerestorey windows, in approved colour, texture & finish. The bamboowood planks shall have minimum density of 1000 Kg/cum & minimum Hardness 1000 Kgf. The panels shall have profiled interlocking system locked in place with bamboo pins all complete as per direction of the Engineer in-charge. (area of opening for panel inserts excluding portion inside grooves or rebates to be measured) — is derived from 3 priced inputs for shutters of and works out to ₹4,555.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 2/3rd panelling…
  • 200 x 108 cm = 2.16 sqm
  • Panel area = 4x45.1x36.55cm = 0.66 sqm
  • 4x47.2x38.65x1.0cm = 0.0073cum + 0.0007
  • sqm (Add Wastage @10%)
  • Total = 0.008 cum OR 8 cudm
CodeInputUnitQuantityRate (INR)Amount (INR)
8029Bamboo wood panelling (10mm thick)Bamboo wood panelling (10 mm thick)Material10 cudm0.82,018.751,615.00
0156Carpenter (average)Labourday0.57857.00488.49
9999SundriesMaterialL.S.4.422.2710.03
TOTAL
2,113.52
Add 1 % Water charges on “W”
21.14
TOTAL
2,134.66
Add GST on “X” (multiplying factor 0.2127)
454.04
TOTAL
2,588.70
Add 15% CPOH on “Y”
388.31
TOTAL
2,977.01
Add Cess @ 1% on “Z”
29.77
Cost of 0.66 sqm
3,006.78
Cost of 1 sqm
4,555.73
Say
4,555.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1910. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.