Skip to main content

Providing and fixing roofing consist of 0.8 mm thick galvanized steel deck sheet conforming to IS 277:1992 used as permanent shuttering over which MS wire mesh 3mm laid at 100x100 mm grid including edge trim covered with concrete. This metal deck will be supported on structural steel beam with shear studs. (Structural steel like Beam, column, joists etc. & concrete of different grade as per design will be paid separately)

Item number
26.65
Analysis basis
10 sqm
Priced inputs
10
Derived rate
₹1,525.60/ SQM
D-01/RATE ANALYSISITEM 26.65

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.65 (Providing and fixing roofing consist of 0.8 mm thick galvanized steel deck sheet conforming to IS 277:1992 used as permanent shuttering over which MS wire mesh 3mm laid at 100x100 mm grid including edge trim covered with concrete. This metal deck will be supported on structural steel beam with shear studs. (Structural steel like Beam, column, joists etc. & concrete of different grade as per design will be paid separately)) is derived from 10 priced inputs for 10 sqm and works out to ₹1,525.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Weight of GI sheet for 10sqm = 76.7 kgs +
  • Length wire mesh 200metre/10 sqm.
  • Weight of wire @ 0.06 kg/m. total weight
  • = 12 kgs + Add wastage @ 5% = 0.6 kgs.
  • Labour for sheeting (Ref item no 26.19.1)
  • Labour for laying wire mesh (Ref item no
  • 5.22.2)
  • Add wastage @ 3% = 2.3 kg. Total = 79.00 kg
  • Total 12.6 kg
ANALYSIS OF RATES · ITEM 26.65DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8019MATGI sheet 0.8 mm thick conforming to IS 277:1992kg7969.005,451.00
1217MATGI Wire mesh 100x100 mmkg12.675.00945.00
1218MATShear studM.S. Shear studeach4050.002,000.00
9999MATNails/Tagged screwsL.S.138.72.27314.85
9999MATLabour for fixing shear studL.S.462.42.271,049.65
0130LABMistryday0.108897.0096.88
0112LABCarpenter 2nd classday0.432816.00352.51
0114LABBeldarday0.432736.00317.95
0102LABBlacksmith 1st classday0.12897.00107.64
0114LABBeldarday0.12736.0088.32
BUILD-UP TO RATE
Total
10,723.80
Add 1 % Water charges on “W”
+107.24
TOTAL
10,831.04
Add GST on “X” (multiplying factor 0.2127)
+2,303.76
TOTAL
13,134.80
Add 15% CPOH on “Y”
+1,970.22
TOTAL
15,105.02
Add Cess @ 1% on “Z”
+151.05
Cost of 10 sqm
15,256.07
Cost of 1 sqm
1,525.61
SAY
₹1,525.60
D-02/SOURCEPRINTED PAGE 1994
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1994

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1994. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.