CPWD Analysis of Rates · New Technologies and Materials

Providing and fixing roofing consist of 0.8 mm thick galvanized steel deck sheet conforming to IS 277:1992 used as permanent shuttering over which MS wire mesh 3mm laid at 100x100 mm grid including edge trim covered with concrete. This metal deck will be supported on structural steel beam with shear studs. (Structural steel like Beam, column, joists etc. & concrete of different grade as per design will be paid separately)

Item number
26.65
Analysis basis
Detail of cost for 10 sqm
Priced inputs
10
Derived rate
1,525.60 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.65 Providing and fixing roofing consist of 0.8 mm thick galvanized steel deck sheet conforming to IS 277:1992 used as permanent shuttering over which MS wire mesh 3mm laid at 100x100 mm grid including edge trim covered with concrete. This metal deck will be supported on structural steel beam with shear studs. (Structural steel like Beam, column, joists etc. & concrete of different grade as per design will be paid separately) — is derived from 10 priced inputs for 10 sqm and works out to ₹1,525.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Weight of GI sheet for 10sqm = 76.7 kgs +
  • Length wire mesh 200metre/10 sqm.
  • Weight of wire @ 0.06 kg/m. total weight
  • = 12 kgs + Add wastage @ 5% = 0.6 kgs.
  • Labour for sheeting (Ref item no 26.19.1)
  • Labour for laying wire mesh (Ref item no
  • 5.22.2)
  • Add wastage @ 3% = 2.3 kg. Total = 79.00 kg
  • Total 12.6 kg
CodeInputUnitQuantityRate (INR)Amount (INR)
8019GI sheet 0.8 mm thick conforming to IS 277:1992Materialkg7969.005,451.00
1217GI Wire mesh 100x100 mmMaterialkg12.675.00945.00
1218Shear studM.S. Shear studMaterialeach4050.002,000.00
9999Nails/Tagged screwsMaterialL.S.138.72.27314.85
9999Labour for fixing shear studMaterialL.S.462.42.271,049.65
0130MistryLabourday0.108897.0096.88
0112Carpenter 2nd classLabourday0.432816.00352.51
0114BeldarLabourday0.432736.00317.95
0102Blacksmith 1st classLabourday0.12897.00107.64
0114BeldarLabourday0.12736.0088.32
Total
10,723.80
Add 1 % Water charges on “W”
107.24
TOTAL
10,831.04
Add GST on “X” (multiplying factor 0.2127)
2,303.76
TOTAL
13,134.80
Add 15% CPOH on “Y”
1,970.22
TOTAL
15,105.02
Add Cess @ 1% on “Z”
151.05
Cost of 10 sqm
15,256.07
Cost of 1 sqm
1,525.61
Say
1,525.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1994. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.