Providing and fixing roofing consist of 0.8 mm thick galvanized steel deck sheet conforming to IS 277:1992 used as permanent shuttering over which MS wire mesh 3mm laid at 100x100 mm grid including edge trim covered with concrete. This metal deck will be supported on structural steel beam with shear studs. (Structural steel like Beam, column, joists etc. & concrete of different grade as per design will be paid separately)
- Item number
- 26.65
- Analysis basis
- 10 sqm
- Priced inputs
- 10
- Derived rate
- ₹1,525.60/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.65 (Providing and fixing roofing consist of 0.8 mm thick galvanized steel deck sheet conforming to IS 277:1992 used as permanent shuttering over which MS wire mesh 3mm laid at 100x100 mm grid including edge trim covered with concrete. This metal deck will be supported on structural steel beam with shear studs. (Structural steel like Beam, column, joists etc. & concrete of different grade as per design will be paid separately)) is derived from 10 priced inputs for 10 sqm and works out to ₹1,525.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Weight of GI sheet for 10sqm = 76.7 kgs +
- Length wire mesh 200metre/10 sqm.
- Weight of wire @ 0.06 kg/m. total weight
- = 12 kgs + Add wastage @ 5% = 0.6 kgs.
- Labour for sheeting (Ref item no 26.19.1)
- Labour for laying wire mesh (Ref item no
- 5.22.2)
- Add wastage @ 3% = 2.3 kg. Total = 79.00 kg
- Total 12.6 kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8019 | MAT | GI sheet 0.8 mm thick conforming to IS 277:1992 | kg | 79 | 69.00 | 5,451.00 |
| 1217 | MAT | GI Wire mesh 100x100 mm | kg | 12.6 | 75.00 | 945.00 |
| 1218 | MAT | Shear studM.S. Shear stud | each | 40 | 50.00 | 2,000.00 |
| 9999 | MAT | Nails/Tagged screws | L.S. | 138.7 | 2.27 | 314.85 |
| 9999 | MAT | Labour for fixing shear stud | L.S. | 462.4 | 2.27 | 1,049.65 |
| 0130 | LAB | Mistry | day | 0.108 | 897.00 | 96.88 |
| 0112 | LAB | Carpenter 2nd class | day | 0.432 | 816.00 | 352.51 |
| 0114 | LAB | Beldar | day | 0.432 | 736.00 | 317.95 |
| 0102 | LAB | Blacksmith 1st class | day | 0.12 | 897.00 | 107.64 |
| 0114 | LAB | Beldar | day | 0.12 | 736.00 | 88.32 |
- Total
- 10,723.80
- Add 1 % Water charges on “W”
- +107.24
- TOTAL
- 10,831.04
- Add GST on “X” (multiplying factor 0.2127)
- +2,303.76
- TOTAL
- 13,134.80
- Add 15% CPOH on “Y”
- +1,970.22
- TOTAL
- 15,105.02
- Add Cess @ 1% on “Z”
- +151.05
- Cost of 10 sqm
- 15,256.07
- Cost of 1 sqm
- 1,525.61
- SAY
- ₹1,525.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1994
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1994. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.