Providing and fixing in position, 130 mm thick factory made Expanded Polystyrene Core (EPS Core) wall panels consisting of EPS core sandwiched between two Engineered sheets of welded wire fabric mesh duly finished with shortcrete materials on outer faces. The fabric mesh shall be made of 3 mm dia zinc coated G.I. wire mesh with 50 mm pitch in both the directions and on both faces of the wall and connected by GI wire of 3 mm dia at alternate row by welding. The EPS core shall consist of 60 mm thick EPS of density not less than 16 kg/ cum. Both the outer faces of the panel shall be finished by applying the layer of 35 mm thick cement mortar 1:3 {1 cement: 3 coarse sand (not having more than 40% stone chips of size upto 6 mm)} with the help of shotcreting/guniting equipment etc at a pressure not less than 1 bar (100KN/m2) and both surfaces finished with trowel. Fixing operations of wall panels shall be completed in all respect as per drawings and specifications and under the overall direction of the Engineer-in-charge

Item number
26.66
Analysis basis
Details of cost for 1.20x3.00m= 3.60 sqm
Priced inputs
7
Derived rate
2,673.70 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.66 Providing and fixing in position, 130 mm thick factory made Expanded Polystyrene Core (EPS Core) wall panels consisting of EPS core sandwiched between two Engineered sheets of welded wire fabric mesh duly finished with shortcrete materials on outer faces. The fabric mesh shall be made of 3 mm dia zinc coated G.I. wire mesh with 50 mm pitch in both the directions and on both faces of the wall and connected by GI wire of 3 mm dia at alternate row by welding. The EPS core shall consist of 60 mm thick EPS of density not less than 16 kg/ cum. Both the outer faces of the panel shall be finished by applying the layer of 35 mm thick cement mortar 1:3 {1 cement: 3 coarse sand (not having more than 40% stone chips of size upto 6 mm)} with the help of shotcreting/guniting equipment etc at a pressure not less than 1 bar (100KN/m2) and both surfaces finished with trowel. Fixing operations of wall panels shall be completed in all respect as per drawings and specifications and under the overall direction of the Engineer-in-charge — is derived from 7 priced inputs and works out to ₹2,673.70 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Area of EPS panel = 3.60 sqm + Add wastage @5%. Total = 3.78 sqm
  • Cement mortar 1:3 (1cement:3 coarse sand)
  • 2x1.20x3.00x0.035= 0.252 cum
  • 10 mm TMT bars 8 nos of 0.60 metre long.
  • Total length = 4.8 m @ 0.617 kg/metre. Total
  • weight = 2.96 kg
CodeInputUnitQuantityRate (INR)Amount (INR)
8020Factory made EPS Core wall panel /roof panel sandwiched between two Engineered welded wire fabric mesh of 3 mm dia G.I. wire mesh, with 50 mm pitch in both the directions, connected by G.I. wire of 3mm dia at alternate row by weldingFactory made EPS Core wall panel /roof panel sandwiched between two Engineered welded wire fabric mesh of 3 mm dia G.I. wire mesh, with 50 mm pitch in both the directions, connected by G.I. wire of 3 mm dia at alternate row by weldingMaterialsqm3.78621.002,347.38
9999Add for L-shape, U-shape & straight lap meshMaterialL.S.2082.27472.16
Rate as per Item No.3.8 of SH: MortarRate as per item 3.8Sub-analysiscum0.2524,881.951,230.25
Rate as per 5.22.6 (SH:5 Reinforced Cement Concrete)Rate as per item 5.22.6Sub-analysiskg2.96107.85319.24
9999Tag screw with washers for wire mesh fixingMaterialL.S.782.27177.06
9999For fixing wall with foundationMaterialL.S.312.152.27708.58
9999For carrying out shotcreting, shoring, leveling, and finishing the surface with trowelMaterialL.S.707.52.271,606.03
Total
6,860.70
Add 1 % Water charges on “W-A”
65.41
TOTAL
6,926.11
Add GST on “X-A” (multiplying factor 0.2127)
1,405.28
TOTAL
8,331.39
Add 15% CPOH on “Y-A”
1,201.82
TOTAL
9,533.21
Add Cess @ 1% on “Z-A”
92.14
Cost of 3.6 sqm
9,625.35
Cost of 1 sqm
2,673.71
Say
2,673.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1995. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works