Centering and shuttering with 12mm thick shuttering plywood conforming to IS 4990:2011 and removal of form at all heights. Plywood will be supported on lock bars

Suspended floors, roofs, landings, balconies and access platform
Item number
26.64.1
Analysis basis
135 sqm
Priced inputs
3
Derived rate
₹106.80/ SQM
D-01/RATE ANALYSISITEM 26.64.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.64.1 (Centering and shuttering with 12mm thick shuttering plywood conforming to IS 4990:2011 and removal of form at all heights. Plywood will be supported on lock bars Suspended floors, roofs, landings, balconies and access platform) is derived from 3 priced inputs for 135 sqm and works out to ₹106.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Assuming 12mm thick plywood will become
  • unserviceable after use of 10 times
  • Area of roof = 135 sqm + Add wastage @
  • 5% = 6.75 sqm. Total = 141.75 sqm.
  • Qty taken for cost using once = 141.75/10 =
  • 14.175 sqm
  • LABOUR (Reference item no 5.9.20)
ANALYSIS OF RATES · ITEM 26.64.1DETAIL OF COST FOR 135 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8659MAT12mm thick waterproofing plywood conforming to IS 4990:2011Water proof ply 12 mm thicksqm14.175578.008,193.15
0112LABCarpenter 2nd classday1.25816.001,020.00
0114LABBeldarday1.25736.00920.00
BUILD-UP TO RATE
Total
10,133.15
Add 1 % Water charges on “W”
+101.33
TOTAL
10,234.48
Add GST on “X” (multiplying factor 0.2127)
+2,176.87
TOTAL
12,411.35
Add 15% CPOH on “Y”
+1,861.70
TOTAL
14,273.05
Add Cess @ 1% on “Z”
+142.73
Cost of 135 sqm
14,415.78
Cost of 1 sqm
106.78
SAY
₹106.80
D-02/SOURCEPRINTED PAGE 1993
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1993

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1993. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.