CPWD Analysis of Rates · New Technologies and Materials
Providing and fixing special adjustable lockbars of mild steel E-250 to support the temporary plywood for work between joists during construction as per design & directions of the Engineer-in-charge
- Item number
- 26.63
- Analysis basis
- Detail of cost for 298.75 kg
- Priced inputs
- 4
- Derived rate
- ₹27.10 / kg
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.63 — Providing and fixing special adjustable lockbars of mild steel E-250 to support the temporary plywood for work between joists during construction as per design & directions of the Engineer-in-charge — is derived from 4 priced inputs for 298.75 kg and works out to ₹27.10 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- Assuming special adjustable lock bar of mild
- steel will become unserviceable after use of
- 50 times
- Taking salvage value after full use of material @ 35% of cost
- Lock bar of size 1230mmx75mmx10mm
- 45 Nos x 4.35kg/each = 195.75 kg.
- Lock bar of size 930mmx75mmx10mm
- 30 Nos x 3.3kg/each = 99.00 kg.
- Total weight = 298.75 kgs
- Assuming 50 repetition, Qty taken for cost of
- using once = 298.75/50= 5.975 kgs
- Considering salvage value @ 35%, Quantity
- = 5.975x(100-35)/100 = 3.88 kgs
- LABOUR (Reference item no 10.1)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7336 | Lock Bar (E 250) - 10 thick MS PlateMaterial | kgs | 3.88 | 83.00 | 322.04 |
| 0116 | Fitter (grade 1)Labour | day | 1.49 | 897.00 | 1,336.53 |
| 0103 | Blacksmith 2nd classLabour | day | 2.24 | 816.00 | 1,827.84 |
| 0114 | BeldarLabour | day | 2.99 | 736.00 | 2,200.64 |
- Total
- 5,687.05
- Add 1 % Water charges on “W”
- 56.87
- TOTAL
- 5,743.92
- Add GST on “X” (multiplying factor 0.2127)
- 1,221.73
- TOTAL
- 6,965.65
- Add 15% CPOH on “Y”
- 1,044.85
- TOTAL
- 8,010.50
- Add Cess @ 1% on “Z”
- 80.11
- Cost of 298.75 kg
- 8,090.61
- Cost of 1 kg
- 27.08
- Say
- 27.10
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1993. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.