Designing, Providing, installing and fixing factory finished customed design pregalvanized high tensile steel joists manufactured from G350 Z275 conforming to IS:277-1992, minimum coating of galvanizing 275 gm/sqm, minimum yield stress 35 MPa & minimum tensile strength of 380 MPa placed 1.23 metre apart to support the load of slab etc as per the design & directions of Engineer-in-Charge

Item number
26.62
Analysis basis
Detail of cost for 212.816 kg
Priced inputs
4
Derived rate
182.05 / kg

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.62 Designing, Providing, installing and fixing factory finished customed design pregalvanized high tensile steel joists manufactured from G350 Z275 conforming to IS:277-1992, minimum coating of galvanizing 275 gm/sqm, minimum yield stress 35 MPa & minimum tensile strength of 380 MPa placed 1.23 metre apart to support the load of slab etc as per the design & directions of Engineer-in-Charge — is derived from 4 priced inputs for 212.816 kg and works out to ₹182.05 per kg after water charges, GST, CPOH and cess. The full build-up is below.

  • Covered area = 5.57x4.2m = 23.394 sqm
  • (a) 250 series Joist (G 350) - 3mm thick Galvanised = 4 Nos x4.18 metre length =
  • 16.72 metre @ 10.59 kg/metre = 177.06 kg
  • (b) Joist Shoe plate (E 250) - 12 mm thick
  • MS Plate (Galvanised with 55 microns) =
  • 2 Nos in each joist x 4 No. joist = 8 No’s @
  • 2.4kg/each = 19.2kg
  • (c) Bolts (M16 - Gr 8.8s), (Galvanised)
  • (16 X 40 bolts With washer & Nuts)= 6No’s
  • in each joist x 4 No. joists=24 Nos 24
  • No’∅s@0.135kg/each = 3.24 kg
  • (d) Hanging Angle at corners to support lock
  • bars L 75x40x1.6 (Galvanised) = 2x4.18
  • metre =8.36 metre @ 1.60kg/metre =
  • 13.376 kg
  • Total weight = 177.06+19.2+3.24+13.376 =
  • 212.816 kgs
  • LABOUR (Reference item no 10.1)
CodeInputUnitQuantityRate (INR)Amount (INR)
1012Pregalvanized high tensile steelPregalvanized high tensile steel conforming to IS:277-199Materialkg212.816110.0023,409.76
0116Fitter (grade 1)Labourday1.064897.00954.41
0103Blacksmith 2nd classLabourday1.596816.001,302.34
0114BeldarLabourday2.128736.001,566.21
Total
27,232.72
Add 1 % Water charges on “W”
272.33
TOTAL
27,505.05
Add GST on “X” (multiplying factor 0.2127)
5,850.32
TOTAL
33,355.37
Add 15% CPOH on “Y”
5,003.31
TOTAL
38,358.68
Add Cess @ 1% on “Z”
383.59
Cost of 212.816 kg
38,742.27
Cost of 1 kg
182.05
Say
182.05

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1992. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.