CPWD Analysis of Rates · New Technologies and Materials

Water proofing treatment of RCC sunshade with Zycosil/equivalent water proofing Solution (1 litre of Zycosil/equivalent & 20 litres of water stirred first & 2 litres of Zycoprime/equivalent added and stirred (total 23 litres)) till it meets the saturation level and testing as per RILEM or by water drops test in which water drops do not absorb but drops remain or rolls

Item number
26.60
Analysis basis
Detail of cost for 40 sqm
Priced inputs
4
Derived rate
136.45 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.60 Water proofing treatment of RCC sunshade with Zycosil/equivalent water proofing Solution (1 litre of Zycosil/equivalent & 20 litres of water stirred first & 2 litres of Zycoprime/equivalent added and stirred (total 23 litres)) till it meets the saturation level and testing as per RILEM or by water drops test in which water drops do not absorb but drops remain or rolls — is derived from 4 priced inputs for 40 sqm and works out to ₹136.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
8519Zycosil / equivalentMateriallitre11,440.001,440.00
8518Zycoprime /equivalentZycoprime / equivalentMateriallitre2170.00340.00
9999Water, technical supervision, etc.MaterialL.S.72.2715.89
0131PainterLabourday2.5816.002,040.00
TOTAL
3,835.89
Add 1% water charges
38.36
TOTAL
3,874.25
Add GST on “X” (multiplying factor 0.2127)
824.05
TOTAL
4,698.30
Add 15% CPOH on “Y”
704.75
TOTAL
5,403.05
Add Cess @1% on “Z”
54.03
Cost of 40 sqm
5,457.08
Cost of 1 sqm
136.43
Say
136.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1991. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.