Water proofing treatment of Vertical joints (of external side and internal side) between door frame, window & ventilator frames (on all four sides) of outer wall over the Zycosil/equivalent & Zycoprime/equivalent solution already applied (before the installation of door / window / ventilator frames in position) and fine finish with Grout RW/equivalent
- Item number
- 26.59
- Analysis basis
- 40 sqm
- Priced inputs
- 8
- Derived rate
- ₹49.95/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.59 (Water proofing treatment of Vertical joints (of external side and internal side) between door frame, window & ventilator frames (on all four sides) of outer wall over the Zycosil/equivalent & Zycoprime/equivalent solution already applied (before the installation of door / window / ventilator frames in position) and fine finish with Grout RW/equivalent) is derived from 8 priced inputs for 40 sqm and works out to ₹49.95 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 10mm thick strip
- 1.50x4000/48=125.00 day
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8519 | MAT | Zycosil / equivalent | litre | 1 | 1,440.00 | 1,440.00 |
| 8518 | MAT | Zycoprime / equivalent | litre | 2 | 170.00 | 340.00 |
| 9999 | MAT | Water, technical supervision, etc. | L.S. | 6 | 2.27 | 13.62 |
| 0123 | LAB | Mason (Brick layer) 1st classMason 1st class | day | 0.286 | 897.00 | 256.54 |
| 8520 | MAT | Elastobar / equivalent (1.00x4000/48=83.33 kg)Elastobar / equivalent | kg | 83.33 | 300.00 | 24,999.00 |
| 0367 | MAT | OPC Cement(0.0015x4000/48=0.125 tonne)Portland Cement (OPC-43 Grade) | tonne | 0.125 | 5,156.00 | 644.50 |
| 9999 | MAT | 100 mesh silica, water, technical supervision, etc.(3.00x4000/48=250.00) | L.S. | 250 | 2.27 | 567.50 |
| 0123 | LAB | Mason (Brick layer) 1st classMason 1st class | day | 125 | 897.00 | 1,12,125.00 |
- TOTAL
- 1,40,386.16
- Add 1% water charges
- +1,403.86
- TOTAL
- 1,41,790.02
- Add GST on “X” (multiplying factor 0.2127)
- +30,158.74
- TOTAL
- 1,71,948.76
- Add 15% CPOH on “Y”
- +25,792.31
- TOTAL
- 1,97,741.07
- Add Cess @1% on “Z”
- +1,977.41
- Cost of 4000 metre
- 1,99,718.48
- Cost of 1 metre
- 49.93
- SAY
- ₹49.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1990
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1990. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.