CPWD Analysis of Rates · New Technologies and Materials

Filling of joints between RCC plinth beam / floor slab and wall panel of external walls, toilet / bath room / wet areas walls on all floor and parapet wall over roof slab, stair case head room at the time of erection of GFRG panels with Grout RW/equivalent sealant compound after the erection of panel before the infill of concrete in panel cavities and fine finish. This applies for all horizontal and vertical joints between GFRG wall and slab panels

Item number
26.58
Analysis basis
Detail of cost for 48 metre
Priced inputs
4
Derived rate
49.30 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.58 Filling of joints between RCC plinth beam / floor slab and wall panel of external walls, toilet / bath room / wet areas walls on all floor and parapet wall over roof slab, stair case head room at the time of erection of GFRG panels with Grout RW/equivalent sealant compound after the erection of panel before the infill of concrete in panel cavities and fine finish. This applies for all horizontal and vertical joints between GFRG wall and slab panels — is derived from 4 priced inputs for 48 metre and works out to ₹49.30 per metre after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
8520Elastobar / equivalentMaterialkg1300.00300.00
0367OPC CementPortland Cement (OPC-43 Grade)Materialtonne0.0025,156.0010.31
9999100 mesh silica, water, technical supervision, etcMaterialL.S.32.276.81
0123Mason (Brick layer) 1st classMason 1st classLabourday1.5897.001,345.50
TOTAL
1,662.62
Add 1% water charges
16.63
TOTAL
1,679.25
Add GST on “X” (multiplying factor 0.2127)
357.18
TOTAL
2,036.43
Add 15% CPOH on “Y”
305.46
TOTAL
2,341.89
Add Cess @1% on “Z”
23.42
Cost of 48 metre
2,365.31
Cost of 1 metre
49.28
Say
49.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1989. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.