Filling of joints between RCC plinth beam / floor slab and wall panel of external walls, toilet / bath room / wet areas walls on all floor and parapet wall over roof slab, stair case head room at the time of erection of GFRG panels with Grout RW/equivalent sealant compound after the erection of panel before the infill of concrete in panel cavities and fine finish. This applies for all horizontal and vertical joints between GFRG wall and slab panels

Item number
26.58
Analysis basis
48 metre
Priced inputs
4
Derived rate
₹49.30/ METRE
D-01/RATE ANALYSISITEM 26.58

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.58 (Filling of joints between RCC plinth beam / floor slab and wall panel of external walls, toilet / bath room / wet areas walls on all floor and parapet wall over roof slab, stair case head room at the time of erection of GFRG panels with Grout RW/equivalent sealant compound after the erection of panel before the infill of concrete in panel cavities and fine finish. This applies for all horizontal and vertical joints between GFRG wall and slab panels) is derived from 4 priced inputs for 48 metre and works out to ₹49.30 per metre after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 26.58DETAIL OF COST FOR 48 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8520MATElastobar / equivalentkg1300.00300.00
0367MATOPC CementPortland Cement (OPC-43 Grade)tonne0.0025,156.0010.31
9999MAT100 mesh silica, water, technical supervision, etcL.S.32.276.81
0123LABMason (Brick layer) 1st classMason 1st classday1.5897.001,345.50
BUILD-UP TO RATE
TOTAL
1,662.62
Add 1% water charges
+16.63
TOTAL
1,679.25
Add GST on “X” (multiplying factor 0.2127)
+357.18
TOTAL
2,036.43
Add 15% CPOH on “Y”
+305.46
TOTAL
2,341.89
Add Cess @1% on “Z”
+23.42
Cost of 48 metre
2,365.31
Cost of 1 metre
49.28
SAY
₹49.30
D-02/SOURCEPRINTED PAGE 1989
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1989

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1989. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.