CPWD Analysis of Rates · New Technologies and Materials
Filling of joints between RCC plinth beam / floor slab and wall panel of external walls, toilet / bath room / wet areas walls on all floor and parapet wall over roof slab, stair case head room at the time of erection of GFRG panels with Grout RW/equivalent sealant compound after the erection of panel before the infill of concrete in panel cavities and fine finish. This applies for all horizontal and vertical joints between GFRG wall and slab panels
- Item number
- 26.58
- Analysis basis
- Detail of cost for 48 metre
- Priced inputs
- 4
- Derived rate
- ₹49.30 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.58 — Filling of joints between RCC plinth beam / floor slab and wall panel of external walls, toilet / bath room / wet areas walls on all floor and parapet wall over roof slab, stair case head room at the time of erection of GFRG panels with Grout RW/equivalent sealant compound after the erection of panel before the infill of concrete in panel cavities and fine finish. This applies for all horizontal and vertical joints between GFRG wall and slab panels — is derived from 4 priced inputs for 48 metre and works out to ₹49.30 per metre after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8520 | Elastobar / equivalentMaterial | kg | 1 | 300.00 | 300.00 |
| 0367 | OPC CementPortland Cement (OPC-43 Grade)Material | tonne | 0.002 | 5,156.00 | 10.31 |
| 9999 | 100 mesh silica, water, technical supervision, etcMaterial | L.S. | 3 | 2.27 | 6.81 |
| 0123 | Mason (Brick layer) 1st classMason 1st classLabour | day | 1.5 | 897.00 | 1,345.50 |
- TOTAL
- 1,662.62
- Add 1% water charges
- 16.63
- TOTAL
- 1,679.25
- Add GST on “X” (multiplying factor 0.2127)
- 357.18
- TOTAL
- 2,036.43
- Add 15% CPOH on “Y”
- 305.46
- TOTAL
- 2,341.89
- Add Cess @1% on “Z”
- 23.42
- Cost of 48 metre
- 2,365.31
- Cost of 1 metre
- 49.28
- Say
- 49.30
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1989. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works