After erection of GFRG wall panels, seal all GFRG wall joints with paper tape temporarily. Water proofing treatment of vertical joints with Zycosil/equivalent water proofing Solution (1 litre of Zycosil/equivalent & 20 litres of water stirred first & 2 litres of Zycoprime/equivalent added and stirred (total 23 litre)) with 50 ml syringe till the gap and in filled concrete is completely saturated. After removing the paper seal, seal off the vertical joints with water proofing material “Grout RW/equivalent “ (Sealing cost excluded.)

Item number
26.57
Analysis basis
Detail of cost for 30 metre
Priced inputs
4
Derived rate
92.45 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.57 After erection of GFRG wall panels, seal all GFRG wall joints with paper tape temporarily. Water proofing treatment of vertical joints with Zycosil/equivalent water proofing Solution (1 litre of Zycosil/equivalent & 20 litres of water stirred first & 2 litres of Zycoprime/equivalent added and stirred (total 23 litre)) with 50 ml syringe till the gap and in filled concrete is completely saturated. After removing the paper seal, seal off the vertical joints with water proofing material “Grout RW/equivalent “ (Sealing cost excluded.) — is derived from 4 priced inputs for 30 metre and works out to ₹92.45 per metre after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
8519Zycosil /equivalentZycosil / equivalentMateriallitre0.2611,440.00375.84
8518Zycoprime / equivalentMateriallitre0.522170.0088.74
9999water, syringe, etc.MaterialL.S.1602.27363.20
0123Mason (Brick layer) 1st classMason 1st classLabourday1.25897.001,121.25
TOTAL
1,949.03
Add 1% water charges
19.49
TOTAL
1,968.52
Add GST on “X” (multiplying factor 0.2127)
418.70
TOTAL
2,387.22
Add 15% CPOH on “Y”
358.08
TOTAL
2,745.30
Add Cess @1% on “Z”
27.45
Cost of 30 metre
2,772.75
Cost of 1 metre
92.43
Say
92.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1989. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.