After erection of GFRG wall panels, seal all GFRG wall joints with paper tape temporarily. Water proofing treatment of vertical joints with Zycosil/equivalent water proofing Solution (1 litre of Zycosil/equivalent & 20 litres of water stirred first & 2 litres of Zycoprime/equivalent added and stirred (total 23 litre)) with 50 ml syringe till the gap and in filled concrete is completely saturated. After removing the paper seal, seal off the vertical joints with water proofing material “Grout RW/equivalent “ (Sealing cost excluded.)

Item number
26.57
Analysis basis
30 metre
Priced inputs
4
Derived rate
₹92.45/ METRE
D-01/RATE ANALYSISITEM 26.57

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.57 (After erection of GFRG wall panels, seal all GFRG wall joints with paper tape temporarily. Water proofing treatment of vertical joints with Zycosil/equivalent water proofing Solution (1 litre of Zycosil/equivalent & 20 litres of water stirred first & 2 litres of Zycoprime/equivalent added and stirred (total 23 litre)) with 50 ml syringe till the gap and in filled concrete is completely saturated. After removing the paper seal, seal off the vertical joints with water proofing material “Grout RW/equivalent “ (Sealing cost excluded.)) is derived from 4 priced inputs for 30 metre and works out to ₹92.45 per metre after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 26.57DETAIL OF COST FOR 30 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8519MATZycosil /equivalentZycosil / equivalentlitre0.2611,440.00375.84
8518MATZycoprime / equivalentlitre0.522170.0088.74
9999MATwater, syringe, etc.L.S.1602.27363.20
0123LABMason (Brick layer) 1st classMason 1st classday1.25897.001,121.25
BUILD-UP TO RATE
TOTAL
1,949.03
Add 1% water charges
+19.49
TOTAL
1,968.52
Add GST on “X” (multiplying factor 0.2127)
+418.70
TOTAL
2,387.22
Add 15% CPOH on “Y”
+358.08
TOTAL
2,745.30
Add Cess @1% on “Z”
+27.45
Cost of 30 metre
2,772.75
Cost of 1 metre
92.43
SAY
₹92.45
D-02/SOURCEPRINTED PAGE 1989
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1989

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1989. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.