CPWD Analysis of Rates · New Technologies and Materials

Application of ZMB 60/equivalent solution (100 Kg ZMB 60/equivalent, 1 litre ZMB Nano Thinner, 20 litre water & 1 Litre Zycoprime/equivalent = 122 litre/kg) over already applied coat of Zycosil/equivalent & Zycoprime/equivalent solution on the top of all the RCC plinth beams by brush/spray coat before erection of GFRG over RCC plinth beams in GF. In the case of upper floors 150 mm wide on floor slab for all the external walls, bath/toilet/wet areas (3 hrs drying time) before erection of wall panel on upper floors including erection of parapet wall

Item number
26.56
Analysis basis
Detail of cost for 122sqm
Priced inputs
5
Derived rate
371.25 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.56 Application of ZMB 60/equivalent solution (100 Kg ZMB 60/equivalent, 1 litre ZMB Nano Thinner, 20 litre water & 1 Litre Zycoprime/equivalent = 122 litre/kg) over already applied coat of Zycosil/equivalent & Zycoprime/equivalent solution on the top of all the RCC plinth beams by brush/spray coat before erection of GFRG over RCC plinth beams in GF. In the case of upper floors 150 mm wide on floor slab for all the external walls, bath/toilet/wet areas (3 hrs drying time) before erection of wall panel on upper floors including erection of parapet wall — is derived from 5 priced inputs and works out to ₹371.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
8516ZMB 60 / equivalentZMB 60/equivalentMaterialkg100130.0013,000.00
8517ZMB ThinnerMateriallitre1250.00250.00
8518Zycoprime / equivalentMateriallitre1170.00170.00
9999Water, brush, technical supervision etc.MaterialL.S.782.27177.06
0123Mason (Brick layer) 1st classMason 1st classLabourday20.333897.0018,238.70
TOTAL
31,835.76
Add 1% water charges
318.36
TOTAL
32,154.12
Add GST on “X” (multiplying factor 0.2127)
6,839.18
TOTAL
38,993.30
Add 15% CPOH on “Y”
5,849.00
TOTAL
44,842.30
Add Cess @1% on “Z”
448.42
Cost of 122 sqm
45,290.72
Cost of 1 sqm
371.24
Say
371.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1988. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.