CPWD Analysis of Rates · New Technologies and Materials
Application of ZMB 60/equivalent solution (100 Kg ZMB 60/equivalent, 1 litre ZMB Nano Thinner, 20 litre water & 1 Litre Zycoprime/equivalent = 122 litre/kg) over already applied coat of Zycosil/equivalent & Zycoprime/equivalent solution on the top of all the RCC plinth beams by brush/spray coat before erection of GFRG over RCC plinth beams in GF. In the case of upper floors 150 mm wide on floor slab for all the external walls, bath/toilet/wet areas (3 hrs drying time) before erection of wall panel on upper floors including erection of parapet wall
- Item number
- 26.56
- Analysis basis
- Detail of cost for 122sqm
- Priced inputs
- 5
- Derived rate
- ₹371.25 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.56 — Application of ZMB 60/equivalent solution (100 Kg ZMB 60/equivalent, 1 litre ZMB Nano Thinner, 20 litre water & 1 Litre Zycoprime/equivalent = 122 litre/kg) over already applied coat of Zycosil/equivalent & Zycoprime/equivalent solution on the top of all the RCC plinth beams by brush/spray coat before erection of GFRG over RCC plinth beams in GF. In the case of upper floors 150 mm wide on floor slab for all the external walls, bath/toilet/wet areas (3 hrs drying time) before erection of wall panel on upper floors including erection of parapet wall — is derived from 5 priced inputs and works out to ₹371.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8516 | ZMB 60 / equivalentZMB 60/equivalentMaterial | kg | 100 | 130.00 | 13,000.00 |
| 8517 | ZMB ThinnerMaterial | litre | 1 | 250.00 | 250.00 |
| 8518 | Zycoprime / equivalentMaterial | litre | 1 | 170.00 | 170.00 |
| 9999 | Water, brush, technical supervision etc.Material | L.S. | 78 | 2.27 | 177.06 |
| 0123 | Mason (Brick layer) 1st classMason 1st classLabour | day | 20.333 | 897.00 | 18,238.70 |
- TOTAL
- 31,835.76
- Add 1% water charges
- 318.36
- TOTAL
- 32,154.12
- Add GST on “X” (multiplying factor 0.2127)
- 6,839.18
- TOTAL
- 38,993.30
- Add 15% CPOH on “Y”
- 5,849.00
- TOTAL
- 44,842.30
- Add Cess @1% on “Z”
- 448.42
- Cost of 122 sqm
- 45,290.72
- Cost of 1 sqm
- 371.24
- Say
- 371.25
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1988. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.