Application of ZMB 60/equivalent solution (100 Kg ZMB 60/equivalent, 1 litre ZMB Nano Thinner, 20 litre water & 1 Litre Zycoprime/equivalent = 122 litre/kg) over already applied coat of Zycosil/equivalent & Zycoprime/equivalent solution on the top of all the RCC plinth beams by brush/spray coat before erection of GFRG over RCC plinth beams in GF. In the case of upper floors 150 mm wide on floor slab for all the external walls, bath/toilet/wet areas (3 hrs drying time) before erection of wall panel on upper floors including erection of parapet wall
- Item number
- 26.56
- Analysis basis
- Detail of cost for 122sqm
- Priced inputs
- 5
- Derived rate
- ₹371.25/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.56 (Application of ZMB 60/equivalent solution (100 Kg ZMB 60/equivalent, 1 litre ZMB Nano Thinner, 20 litre water & 1 Litre Zycoprime/equivalent = 122 litre/kg) over already applied coat of Zycosil/equivalent & Zycoprime/equivalent solution on the top of all the RCC plinth beams by brush/spray coat before erection of GFRG over RCC plinth beams in GF. In the case of upper floors 150 mm wide on floor slab for all the external walls, bath/toilet/wet areas (3 hrs drying time) before erection of wall panel on upper floors including erection of parapet wall) is derived from 5 priced inputs and works out to ₹371.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8516 | MAT | ZMB 60 / equivalentZMB 60/equivalent | kg | 100 | 130.00 | 13,000.00 |
| 8517 | MAT | ZMB Thinner | litre | 1 | 250.00 | 250.00 |
| 8518 | MAT | Zycoprime / equivalent | litre | 1 | 170.00 | 170.00 |
| 9999 | MAT | Water, brush, technical supervision etc. | L.S. | 78 | 2.27 | 177.06 |
| 0123 | LAB | Mason (Brick layer) 1st classMason 1st class | day | 20.333 | 897.00 | 18,238.70 |
- TOTAL
- 31,835.76
- Add 1% water charges
- +318.36
- TOTAL
- 32,154.12
- Add GST on “X” (multiplying factor 0.2127)
- +6,839.18
- TOTAL
- 38,993.30
- Add 15% CPOH on “Y”
- +5,849.00
- TOTAL
- 44,842.30
- Add Cess @1% on “Z”
- +448.42
- Cost of 122 sqm
- 45,290.72
- Cost of 1 sqm
- 371.24
- SAY
- ₹371.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1988
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1988. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.