Application of ZMB 60/equivalent solution (100 Kg ZMB 60/equivalent, 1 litre ZMB Nano Thinner, 20 litre water & 1 Litre Zycoprime/equivalent = 122 litre/kg) over already applied coat of Zycosil/equivalent & Zycoprime/equivalent solution on the top of all the RCC plinth beams by brush/spray coat before erection of GFRG over RCC plinth beams in GF. In the case of upper floors 150 mm wide on floor slab for all the external walls, bath/toilet/wet areas (3 hrs drying time) before erection of wall panel on upper floors including erection of parapet wall

Item number
26.56
Analysis basis
Detail of cost for 122sqm
Priced inputs
5
Derived rate
₹371.25/ SQM
D-01/RATE ANALYSISITEM 26.56

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.56 (Application of ZMB 60/equivalent solution (100 Kg ZMB 60/equivalent, 1 litre ZMB Nano Thinner, 20 litre water & 1 Litre Zycoprime/equivalent = 122 litre/kg) over already applied coat of Zycosil/equivalent & Zycoprime/equivalent solution on the top of all the RCC plinth beams by brush/spray coat before erection of GFRG over RCC plinth beams in GF. In the case of upper floors 150 mm wide on floor slab for all the external walls, bath/toilet/wet areas (3 hrs drying time) before erection of wall panel on upper floors including erection of parapet wall) is derived from 5 priced inputs and works out to ₹371.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 26.56DETAIL OF COST FOR 122SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8516MATZMB 60 / equivalentZMB 60/equivalentkg100130.0013,000.00
8517MATZMB Thinnerlitre1250.00250.00
8518MATZycoprime / equivalentlitre1170.00170.00
9999MATWater, brush, technical supervision etc.L.S.782.27177.06
0123LABMason (Brick layer) 1st classMason 1st classday20.333897.0018,238.70
BUILD-UP TO RATE
TOTAL
31,835.76
Add 1% water charges
+318.36
TOTAL
32,154.12
Add GST on “X” (multiplying factor 0.2127)
+6,839.18
TOTAL
38,993.30
Add 15% CPOH on “Y”
+5,849.00
TOTAL
44,842.30
Add Cess @1% on “Z”
+448.42
Cost of 122 sqm
45,290.72
Cost of 1 sqm
371.24
SAY
₹371.25
D-02/SOURCEPRINTED PAGE 1988
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1988

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1988. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.