CPWD Analysis of Rates · New Technologies and Materials

Supplying and fixing 10 Gauge weld mesh of size 100mm x100 mm for floor/roof slab concrete screed over the micro beams as reinforcement. The weld mesh shall be fixed as per drawing

Item number
26.55
Analysis basis
Detail of cost for 9sqm (3mx3m)
Priced inputs
3
Derived rate
254.75 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.55 Supplying and fixing 10 Gauge weld mesh of size 100mm x100 mm for floor/roof slab concrete screed over the micro beams as reinforcement. The weld mesh shall be fixed as per drawing — is derived from 3 priced inputs and works out to ₹254.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Mesh area = 9.00sqm, Add wastage @ 5%
  • = 0.45sqm, Total area = 9.45 sqm
  • Labour for filling the quarry dust
CodeInputUnitQuantityRate (INR)Amount (INR)
1223Steel weld meshMaterialsqm9.45150.001,417.50
0103Blacksmith 2nd classLabourday0.125816.00102.00
0114BeldarLabourday0.125736.0092.00
TOTAL
1,611.50
Add 1% water charges
16.12
TOTAL
1,627.62
Add GST on “X” (multiplying factor 0.2127)
346.19
TOTAL
1,973.81
Add 15% CPOH on “Y”
296.07
TOTAL
2,269.88
Add Cess @1% on “Z”
22.70
Cost of 9 sqm
2,292.58
Cost of 1 sqm
254.73
Say
254.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1988. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.