Supplying and fixing 10 Gauge weld mesh of size 100mm x100 mm for floor/roof slab concrete screed over the micro beams as reinforcement. The weld mesh shall be fixed as per drawing

Item number
26.55
Analysis basis
Detail of cost for 9sqm (3mx3m)
Priced inputs
3
Derived rate
₹254.75/ SQM
D-01/RATE ANALYSISITEM 26.55

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.55 (Supplying and fixing 10 Gauge weld mesh of size 100mm x100 mm for floor/roof slab concrete screed over the micro beams as reinforcement. The weld mesh shall be fixed as per drawing) is derived from 3 priced inputs and works out to ₹254.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Mesh area = 9.00sqm, Add wastage @ 5%
  • = 0.45sqm, Total area = 9.45 sqm
  • Labour for filling the quarry dust
ANALYSIS OF RATES · ITEM 26.55DETAIL OF COST FOR 9SQM (3MX3M)
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1223MATSteel weld meshsqm9.45150.001,417.50
0103LABBlacksmith 2nd classday0.125816.00102.00
0114LABBeldarday0.125736.0092.00
BUILD-UP TO RATE
TOTAL
1,611.50
Add 1% water charges
+16.12
TOTAL
1,627.62
Add GST on “X” (multiplying factor 0.2127)
+346.19
TOTAL
1,973.81
Add 15% CPOH on “Y”
+296.07
TOTAL
2,269.88
Add Cess @1% on “Z”
+22.70
Cost of 9 sqm
2,292.58
Cost of 1 sqm
254.73
SAY
₹254.75
D-02/SOURCEPRINTED PAGE 1988
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1988

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1988. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.