CPWD Analysis of Rates · New Technologies and Materials
Supplying and fixing 10 Gauge weld mesh of size 100mm x100 mm for floor/roof slab concrete screed over the micro beams as reinforcement. The weld mesh shall be fixed as per drawing
- Item number
- 26.55
- Analysis basis
- Detail of cost for 9sqm (3mx3m)
- Priced inputs
- 3
- Derived rate
- ₹254.75 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.55 — Supplying and fixing 10 Gauge weld mesh of size 100mm x100 mm for floor/roof slab concrete screed over the micro beams as reinforcement. The weld mesh shall be fixed as per drawing — is derived from 3 priced inputs and works out to ₹254.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Mesh area = 9.00sqm, Add wastage @ 5%
- = 0.45sqm, Total area = 9.45 sqm
- Labour for filling the quarry dust
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1223 | Steel weld meshMaterial | sqm | 9.45 | 150.00 | 1,417.50 |
| 0103 | Blacksmith 2nd classLabour | day | 0.125 | 816.00 | 102.00 |
| 0114 | BeldarLabour | day | 0.125 | 736.00 | 92.00 |
- TOTAL
- 1,611.50
- Add 1% water charges
- 16.12
- TOTAL
- 1,627.62
- Add GST on “X” (multiplying factor 0.2127)
- 346.19
- TOTAL
- 1,973.81
- Add 15% CPOH on “Y”
- 296.07
- TOTAL
- 2,269.88
- Add Cess @1% on “Z”
- 22.70
- Cost of 9 sqm
- 2,292.58
- Cost of 1 sqm
- 254.73
- Say
- 254.75
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1988. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.