Skip to main content

CPWD Analysis of Rates · New Technologies and Materials

Laying of GFRG panel as roof / floor slab panel and staircase panel using suitable crane as per instructions of Engineer-in-Charge, including providing support system with 25mm x 300mm400 mm wide plywood, as runner with proper prop below proposed micro beams including (a) Cutting of top flange of panel to 180 mm wide (leaving 25mm projection on either side) to provide RCC embedded micro beam as per cutting drawings and structural drawings. (b) Reinforcement for micro beams and tie beams to be provided in position with proper anchorage as per structural drawings. (c) Provision for Electrical cabling, fan hooks and laying of pipes for plumbing work. (d) Concreting of Tie beam, micro beam and top of GFRG panels (50 mm thick) with M-25 cement concrete mix using coarse aggregate of size less than 20 mm including laying of 10 gauge 100x100 size weld mesh with 25 mm effective cover from the panel top

Item number
26.54
Analysis basis
Detail of cost for 9 sqm (3mx3m wall panel)
Priced inputs
5
Derived rate
287.40 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.54 Laying of GFRG panel as roof / floor slab panel and staircase panel using suitable crane as per instructions of Engineer-in-Charge, including providing support system with 25mm x 300mm400 mm wide plywood, as runner with proper prop below proposed micro beams including (a) Cutting of top flange of panel to 180 mm wide (leaving 25mm projection on either side) to provide RCC embedded micro beam as per cutting drawings and structural drawings. (b) Reinforcement for micro beams and tie beams to be provided in position with proper anchorage as per structural drawings. (c) Provision for Electrical cabling, fan hooks and laying of pipes for plumbing work. (d) Concreting of Tie beam, micro beam and top of GFRG panels (50 mm thick) with M-25 cement concrete mix using coarse aggregate of size less than 20 mm including laying of 10 gauge 100x100 size weld mesh with 25 mm effective cover from the panel top — is derived from 5 priced inputs for 9 sqm and works out to ₹287.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Providing runner & support system in place
  • for
  • placing panel in position with 40mm bearing
  • on
  • walls( 4 Skilled persons for 1/2 Hrs /1/16
  • days)
  • Lifting panel from stack by crane and placing in position with 40 mm bearing on walls
  • 4 skilled labour for 1 hrs
  • Cutting & removal of top flange to protruding
  • 25mm
  • on either sides for keying panel into RCC
  • micro beams in position (every 3rd cavities
  • runner/span in place beneath) and providing
  • concealed beam reinforcement in position,
  • side shuttering for slab for external side(with
  • 6mm grove) also to be provided (mean
  • while providing fan hooks, electrical cabling,
  • piping etc by coordinate task by concerned
  • skilled persons, 4 skilled labour for 1 hrs
CodeInputUnitQuantityRate (INR)Amount (INR)
0123Mason (Brick layer) 1st classMason 1st classLabourday0.25897.00224.25
0123Mason (Brick layer) 1st classMason 1st classLabourday0.5897.00448.50
0123Mason (Brick layer) 1st classMason 1st classLabourday0.5897.00448.50
9999Hire charges for runner and support system and side shuttering for external side of slab for 5 daysMaterialL.S.292.2765.83
0037Mobile craneMachineryday0.1255,050.00631.25
TOTAL
1,818.33
Add 1% water charges
18.18
TOTAL
1,836.51
Add GST on “X” (multiplying factor 0.2127)
390.63
TOTAL
2,227.14
Add 15% CPOH on “Y”
334.07
TOTAL
2,561.21
Add Cess @1% on “Z”
25.61
Cost of 9 sqm
2,586.82
Cost of 1 sqm
287.42
Say
287.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1987. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works