CPWD Analysis of Rates · New Technologies and Materials
Laying of GFRG panel as roof / floor slab panel and staircase panel using suitable crane as per instructions of Engineer-in-Charge, including providing support system with 25mm x 300mm400 mm wide plywood, as runner with proper prop below proposed micro beams including (a) Cutting of top flange of panel to 180 mm wide (leaving 25mm projection on either side) to provide RCC embedded micro beam as per cutting drawings and structural drawings. (b) Reinforcement for micro beams and tie beams to be provided in position with proper anchorage as per structural drawings. (c) Provision for Electrical cabling, fan hooks and laying of pipes for plumbing work. (d) Concreting of Tie beam, micro beam and top of GFRG panels (50 mm thick) with M-25 cement concrete mix using coarse aggregate of size less than 20 mm including laying of 10 gauge 100x100 size weld mesh with 25 mm effective cover from the panel top
- Item number
- 26.54
- Analysis basis
- Detail of cost for 9 sqm (3mx3m wall panel)
- Priced inputs
- 5
- Derived rate
- ₹287.40 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.54 — Laying of GFRG panel as roof / floor slab panel and staircase panel using suitable crane as per instructions of Engineer-in-Charge, including providing support system with 25mm x 300mm400 mm wide plywood, as runner with proper prop below proposed micro beams including (a) Cutting of top flange of panel to 180 mm wide (leaving 25mm projection on either side) to provide RCC embedded micro beam as per cutting drawings and structural drawings. (b) Reinforcement for micro beams and tie beams to be provided in position with proper anchorage as per structural drawings. (c) Provision for Electrical cabling, fan hooks and laying of pipes for plumbing work. (d) Concreting of Tie beam, micro beam and top of GFRG panels (50 mm thick) with M-25 cement concrete mix using coarse aggregate of size less than 20 mm including laying of 10 gauge 100x100 size weld mesh with 25 mm effective cover from the panel top — is derived from 5 priced inputs for 9 sqm and works out to ₹287.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Providing runner & support system in place
- for
- placing panel in position with 40mm bearing
- on
- walls( 4 Skilled persons for 1/2 Hrs /1/16
- days)
- Lifting panel from stack by crane and placing in position with 40 mm bearing on walls
- 4 skilled labour for 1 hrs
- Cutting & removal of top flange to protruding
- 25mm
- on either sides for keying panel into RCC
- micro beams in position (every 3rd cavities
- runner/span in place beneath) and providing
- concealed beam reinforcement in position,
- side shuttering for slab for external side(with
- 6mm grove) also to be provided (mean
- while providing fan hooks, electrical cabling,
- piping etc by coordinate task by concerned
- skilled persons, 4 skilled labour for 1 hrs
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0123 | Mason (Brick layer) 1st classMason 1st classLabour | day | 0.25 | 897.00 | 224.25 |
| 0123 | Mason (Brick layer) 1st classMason 1st classLabour | day | 0.5 | 897.00 | 448.50 |
| 0123 | Mason (Brick layer) 1st classMason 1st classLabour | day | 0.5 | 897.00 | 448.50 |
| 9999 | Hire charges for runner and support system and side shuttering for external side of slab for 5 daysMaterial | L.S. | 29 | 2.27 | 65.83 |
| 0037 | Mobile craneMachinery | day | 0.125 | 5,050.00 | 631.25 |
- TOTAL
- 1,818.33
- Add 1% water charges
- 18.18
- TOTAL
- 1,836.51
- Add GST on “X” (multiplying factor 0.2127)
- 390.63
- TOTAL
- 2,227.14
- Add 15% CPOH on “Y”
- 334.07
- TOTAL
- 2,561.21
- Add Cess @1% on “Z”
- 25.61
- Cost of 9 sqm
- 2,586.82
- Cost of 1 sqm
- 287.42
- Say
- 287.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1987. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.