Sub A/R-1

Item number
26.48/Sub-AR-1
Priced inputs
6
Derived rate
12,805.90

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.48/Sub-AR-1 Sub A/R-1 — is derived from 6 priced inputs and works out to ₹12,805.90 after water charges, GST, CPOH and cess. The full build-up is below.

  • Material cost
  • Part-1 : Aluminium formwork
  • 4mm thick sheet of aluminium alloy grade
  • 6061 (type-6) for the contact face area of
  • 100 sqm
  • the sheet/plate requirement including framing flanges and specials = 100 + 120 = 220
  • sqm
  • 220 sqm @ 10.72 kg/sqm = 2358.40 Kg
  • Total = 2358.40 + 117.82 = 2476.32 Kg
  • Aluminium formwork weight without wastage
  • = 2358.40 Kg
  • Accossories like pins, wedges and wall ties
  • to time repalcement of damaged members
  • Part-2: M S working platform on external
  • face (required while fixing & removing )
  • 10x6.00 mtr @ 4.50 Kg/mtrs = 270 Kg (Rate
  • as per item no 10.2 SH:10 Steel work}
  • 7x2x11.45 = 160mtr + 45 mtr (railing guards)
  • = 205 mtr @ 1.25 Kg/mtr = 256.25 Kg (Rate
  • as per item no.10.16.1 SH:10 Steel work )
  • Add 5% extra waste = 117.92 Kg
  • Add cost towards maintenance and time
CodeInputUnitQuantityRate (INR)Amount (INR)
57804mm thick sheet of aluminium alloy grade 6061 (type-6) for aluminuum formwork4 mm thick sheet of aluminium alloy grade 6061 (type-6) for aluminuum formworkMaterialKg2,476.32260.006,43,843.20
5781Fabrication cost for formwork panels and special including computerised designing for fabrication and mock testing before transportation to site of workFabrication cost for formwork panels and special including computerised designing for fabrication and mock testing before transportation to site of work.MaterialKg2,358.437.0087,260.80
5782Packaging and carting of aluminium sheet/ plate to the site of workPackaging and cartage of aluminium sheet/plate to the site of workMaterialTonne2.365,400.0012,744.00
M.S angle iron bracket of size 50x50x6 mm (Rate i/c priming coat)Rate as per item 10.2Sub-analysisKg270133.7036,099.00
M.S. Square tube panel of tubes 25x25mm, 1.8mm thick (Rate i/c priming coat)Rate as per item 10.16.1Sub-analysisKg256.25194.4049,815.00
7343Telescopic adjustabe props 3 m ( 2.02-3.75 m)Adjustable telescopic prop 3 m (2.02-3.75 m)Materialeach301,051.0031,530.00
@ 5% of ( E )
32,192.16
@5% ( E )
32,192.16
TOTAL
9,25,676.32
Add 1 % Water charges on “W-A”
8,397.62
TOTAL
9,34,073.94
Add GST on “X-A” (multiplying factor 0.2127)
1,80,403.62
TOTAL
11,14,477.56
Add 15% CPOH on “Y-A”
1,54,284.53
TOTAL
12,68,762.09
Add Cess @ 1% on “Z-A”
11,828.48
Cost of 100 sqm for 100 Uses
12,80,590.57
Cost of 100 sqm using Once
12,805.91
Say
12,805.90

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1974. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.