Sub A/R-1

Item number
26.48/Sub-AR-1
Priced inputs
6
Derived rate
₹12,805.90
D-01/RATE ANALYSISITEM 26.48/Sub-AR-1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.48/Sub-AR-1 (Sub A/R-1) is derived from 6 priced inputs and works out to ₹12,805.90 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Material cost
  • Part-1 : Aluminium formwork
  • 4mm thick sheet of aluminium alloy grade
  • 6061 (type-6) for the contact face area of
  • 100 sqm
  • the sheet/plate requirement including framing flanges and specials = 100 + 120 = 220
  • sqm
  • 220 sqm @ 10.72 kg/sqm = 2358.40 Kg
  • Total = 2358.40 + 117.82 = 2476.32 Kg
  • Aluminium formwork weight without wastage
  • = 2358.40 Kg
  • Accossories like pins, wedges and wall ties
  • to time repalcement of damaged members
  • Part-2: M S working platform on external
  • face (required while fixing & removing )
  • 10x6.00 mtr @ 4.50 Kg/mtrs = 270 Kg (Rate
  • as per item no 10.2 SH:10 Steel work}
  • 7x2x11.45 = 160mtr + 45 mtr (railing guards)
  • = 205 mtr @ 1.25 Kg/mtr = 256.25 Kg (Rate
  • as per item no.10.16.1 SH:10 Steel work )
  • Add 5% extra waste = 117.92 Kg
  • Add cost towards maintenance and time
ANALYSIS OF RATES · ITEM 26.48/Sub-AR-1
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
5780MAT4mm thick sheet of aluminium alloy grade 6061 (type-6) for aluminuum formwork4 mm thick sheet of aluminium alloy grade 6061 (type-6) for aluminuum formworkKg2,476.32260.006,43,843.20
5781MATFabrication cost for formwork panels and special including computerised designing for fabrication and mock testing before transportation to site of workFabrication cost for formwork panels and special including computerised designing for fabrication and mock testing before transportation to site of work.Kg2,358.437.0087,260.80
5782MATPackaging and carting of aluminium sheet/ plate to the site of workPackaging and cartage of aluminium sheet/plate to the site of workTonne2.365,400.0012,744.00
SUBM.S angle iron bracket of size 50x50x6 mm (Rate i/c priming coat)Rate as per item 10.2Kg270133.7036,099.00
SUBM.S. Square tube panel of tubes 25x25mm, 1.8mm thick (Rate i/c priming coat)Rate as per item 10.16.1Kg256.25194.4049,815.00
7343MATTelescopic adjustabe props 3 m ( 2.02-3.75 m)Adjustable telescopic prop 3 m (2.02-3.75 m)each301,051.0031,530.00
BUILD-UP TO RATE
@ 5% of ( E )
+32,192.16
@5% ( E )
+32,192.16
TOTAL
9,25,676.32
Add 1 % Water charges on “W-A”
+8,397.62
TOTAL
9,34,073.94
Add GST on “X-A” (multiplying factor 0.2127)
+1,80,403.62
TOTAL
11,14,477.56
Add 15% CPOH on “Y-A”
+1,54,284.53
TOTAL
12,68,762.09
Add Cess @ 1% on “Z-A”
+11,828.48
Cost of 100 sqm for 100 Uses
12,80,590.57
Cost of 100 sqm using Once
12,805.91
SAY
₹12,805.90
D-02/SOURCEPRINTED PAGE 1974
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1974

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1974. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.