CPWD Analysis of Rates · New Technologies and Materials

Providing and fixing of customized Aluminium form work for monolithic construction on RCC members with repetitive usage made up of aluminium sheets/plates of minimum 4mm thickness and grade 6061 (Type-6). The formwork comprises of (a) wall panel, roccker, kicker and internal soffit corner, external soffit corner, external corner, internal corner etc., (b) beam components i.e, beam side panel, prop head for soffit beam, beams soffit panel, beam soffit bulk head and (c) deck components i.e. deck panel, deck prop, prop length, deck mid, soffit length, deck beam bar. The panels are held in position by a simple pin and wedge system that passes thorugh holes in the out side rib of each panel. The tolerance of finished panel shall not be less than (-1 mm) and shall conform to IS 14987-1999. Pins and wedges to be made of high grade hot dipped galvansied mild steel. This form work also comprises of M.S. angle iron, “Z” shaped brackets braced diagonally at 0.90 to 1.00 metre centre to centre on extrenal wall face just the level below on which to lay M.S. square tube panels (Challis) and guard railing supports to form working platform and 40 mm dia G.I./M.S. telescopic adjustable props to support deck formwork and beam soffit panels including de-shuttering the formwork from odd/even level to be shifted/lifted to next alterante odd/even level before which the points and shuttering surface to be thoroughly cleaned, pins greasing and shuttering surface oiling propoerly before fixing all complete including sealing of gap between kicker plates of wall panel and floors (if any) as per design of formwork as provided by shuttering supplier and as per direction of the Engineer-in-charge including filling and finishing the holes of varied sizes and shapes (left by keys/pins of aluminium form work shuttering while deshuttering) with GP-2 cementitious polymer compound mixed with water in ratio prescribed by manufacturer to form consistent workable enough for pushing it in the holes upto full depth of wall using appropriate tools and finishing smooth all complete as per directions of the Engineer-in-charge

Item number
26.48
Analysis basis
Detail of cost for 100 sqm (Assuming 100
Priced inputs
12
Derived rate
451.35 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.48 Providing and fixing of customized Aluminium form work for monolithic construction on RCC members with repetitive usage made up of aluminium sheets/plates of minimum 4mm thickness and grade 6061 (Type-6). The formwork comprises of (a) wall panel, roccker, kicker and internal soffit corner, external soffit corner, external corner, internal corner etc., (b) beam components i.e, beam side panel, prop head for soffit beam, beams soffit panel, beam soffit bulk head and (c) deck components i.e. deck panel, deck prop, prop length, deck mid, soffit length, deck beam bar. The panels are held in position by a simple pin and wedge system that passes thorugh holes in the out side rib of each panel. The tolerance of finished panel shall not be less than (-1 mm) and shall conform to IS 14987-1999. Pins and wedges to be made of high grade hot dipped galvansied mild steel. This form work also comprises of M.S. angle iron, “Z” shaped brackets braced diagonally at 0.90 to 1.00 metre centre to centre on extrenal wall face just the level below on which to lay M.S. square tube panels (Challis) and guard railing supports to form working platform and 40 mm dia G.I./M.S. telescopic adjustable props to support deck formwork and beam soffit panels including de-shuttering the formwork from odd/even level to be shifted/lifted to next alterante odd/even level before which the points and shuttering surface to be thoroughly cleaned, pins greasing and shuttering surface oiling propoerly before fixing all complete including sealing of gap between kicker plates of wall panel and floors (if any) as per design of formwork as provided by shuttering supplier and as per direction of the Engineer-in-charge including filling and finishing the holes of varied sizes and shapes (left by keys/pins of aluminium form work shuttering while deshuttering) with GP-2 cementitious polymer compound mixed with water in ratio prescribed by manufacturer to form consistent workable enough for pushing it in the holes upto full depth of wall using appropriate tools and finishing smooth all complete as per directions of the Engineer-in-charge — is derived from 12 priced inputs for 100 sqm and works out to ₹451.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • repetitions)
  • Aluminium formwork & MS working platform
  • 100 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
Cost for using onceRate as per item Sub A/R-1Sub-analysis100 sqm112,805.9012,805.90
Deduct salvage value of aluminium form work and working platform with 100 repetitions @30% of bare material cost using once (marked as ‘ S ‘ below )Rate as per item Sub A/R-3Sub-analysisNaNNaN-2,120.35
5772Grease to be applied to pins for 100 sqm @ 5pins/sqm. using 25gm grease /pin = 100x5x25 gm = 12.50 KgGreaseMaterialKg12.5195.002,437.50
9999Add replacement of lost/ damaged accessoriesMaterialL.S.98.852.27224.39
5773Shuttering oil for panels @ 20sqm /ltr = 100/20 = 5.00 ltrShutttering oilMateriallitre595.00475.00
9999Add sundries for gaps filling with sealants etc. and T& P including pully, ropes and misc. toolsMaterialL.S.4002.27908.00
9999Add for PVC sleeve and plastic cover for wall tiesMaterialL.S.5002.271,135.00
0116FitterFitter (grade 1)Labourday5897.004,485.00
0117Assistant FitterAssistant Fitter or 2nd class FitterLabourday5816.004,080.00
0155Mason (Average)Labourday2857.001,714.00
0114BeldarLabourday10736.007,360.00
Add for filling and finishing the holes of aluminium form work with GP-2Rate as per item Sub A/R-2Sub-analysiseach2259.002,025.00
TOTAL
35,529.44
Add 1 % Water charges on “W-A”
227.24
TOTAL
35,756.68
Add GST on “X” (multiplying factor 0.2127)
4,881.63
TOTAL
40,638.31
Add 15% CPOH on “Y-A”
4,174.86
TOTAL
44,813.17
Add Cess @ 1% on “Z-A”
320.07
Cost of 100.00 sqm
45,133.24
Cost of 1.00 sqm
451.33
Say
451.35

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1973. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.