Providing and fixing in position, 230mm thick factory made Expanded Polystyrene Core (EPS Core) roof/floor panels made of 3 mm dia G.I. wire mesh with 50 mm pitch in both the directions and on both faces of panel, kept at 120-135 mm gap and connected by the zig zag G.I. wire of 3 mm dia at alternate row by welding (at an angle ranging from 50-70 degree). The EPS core shall consist of 100 mm thick EPS of density not less than 20kg/ per cum. The bottom side of the panel shall be finished by applying a layer of 60-65 mm thick cement mortar 1: 3 {1 cement: 3 coarse sand (not having more than 40% stone chips of size upto 6 mm)} À with the help of shotcreting equipment etc at a pressure of not less than 1 bar (100Kn/ m2) and surface finished with trowel. The top face of the panel shall be provided and finished by applying 70-75 mm thick layer of cement concrete 1:1.5: 3 (1 cement :1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size). Fixing operations of roof/floor panels shall be completed in all respect as per drawings and specifications and under the overall direction of the Engineer-in-charge

Item number
26.47
Analysis basis
Details of cost for 1.20x3.00m= 3.60 sqm
Priced inputs
5
Derived rate
₹4,701.60/ SQM
D-01/RATE ANALYSISITEM 26.47

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.47 (Providing and fixing in position, 230mm thick factory made Expanded Polystyrene Core (EPS Core) roof/floor panels made of 3 mm dia G.I. wire mesh with 50 mm pitch in both the directions and on both faces of panel, kept at 120-135 mm gap and connected by the zig zag G.I. wire of 3 mm dia at alternate row by welding (at an angle ranging from 50-70 degree). The EPS core shall consist of 100 mm thick EPS of density not less than 20kg/ per cum. The bottom side of the panel shall be finished by applying a layer of 60-65 mm thick cement mortar 1: 3 {1 cement: 3 coarse sand (not having more than 40% stone chips of size upto 6 mm)} À with the help of shotcreting equipment etc at a pressure of not less than 1 bar (100Kn/ m2) and surface finished with trowel. The top face of the panel shall be provided and finished by applying 70-75 mm thick layer of cement concrete 1:1.5: 3 (1 cement :1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size). Fixing operations of roof/floor panels shall be completed in all respect as per drawings and specifications and under the overall direction of the Engineer-in-charge) is derived from 5 priced inputs and works out to ₹4,701.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 3.60 sqm + 0.18 sqm (Add for wastage
  • @5%)Total = 3.78 sqm
  • Cement mortar 1:3 (1cement:3 coarse sand)
  • 60mm thick on the bottom of roof slab
  • =1x1.2x3.00x0.060= 0.216cum
  • Cement concrete 1:1.5:3
  • 70mm thick on the top of roof slab
  • =1x1.20x3.00x0.07= 0.252 cum
ANALYSIS OF RATES · ITEM 26.47DETAILS OF COST FOR 1.20X3.00M= 3.60 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8013MATFactory made EPS Core wallpanel /roof panel sandwiched between two Engineered welded wire fabric mesh of 3 mm dia G.I. wire mesh,with 50 mm pitch in both the directions, kept at 120-135 mm gap and interconnected by the zig zag G.I. wire of 3 mm dia at alternate row by welding. sqm 3.78Factory made EPS Core wall panel /roof panel sandwiched between two Engineered welded wire fabric mesh of 3 mm dia G.I. wire mesh,with 50 mm pitch in both the directions, kept at 120-135 mm gap and interconnected by the zig zag G.I. wire of 3 mm dia at alternate row by welding.sqm3.781,708.006,456.24
SUBRate as per Item No.3.8 of SH: MortarRate as per item 3.8cum0.2164,881.951,054.50
SUBRate as per Item No.5.3 of SH: Reinforced Cement ConcreteRate as per item 5.3cum0.25211,505.502,899.39
9999MATAdd for L-shape, U-shape & straight lap meshL.S.202.322.27459.27
9999MATFor providing concreting, shotcreting, shoring, leveling, plastering and finishing the surface with trowelL.S.832.362.271,889.46
BUILD-UP TO RATE
TOTAL
12,758.86
Add 1 % Water charges on “W-A”
+98.59
TOTAL
12,857.45
Add GST on “X-A” (multiplying factor 0.2127)
+2,118.08
TOTAL
14,975.53
Add 15% CPOH on “Y-A”
+1,811.42
TOTAL
16,786.95
Add Cess @ 1% on “Z-A”
+138.88
Cost of 3.60 sqm
16,925.83
Cost of 1 sqm
4,701.62
SAY
₹4,701.60
D-02/SOURCEPRINTED PAGE 1972
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1972

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1972. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.