CPWD Analysis of Rates · New Technologies and Materials
Providing and fixing in position, 230mm thick factory made Expanded Polystyrene Core (EPS Core) roof/floor panels made of 3 mm dia G.I. wire mesh with 50 mm pitch in both the directions and on both faces of panel, kept at 120-135 mm gap and connected by the zig zag G.I. wire of 3 mm dia at alternate row by welding (at an angle ranging from 50-70 degree). The EPS core shall consist of 100 mm thick EPS of density not less than 20kg/ per cum. The bottom side of the panel shall be finished by applying a layer of 60-65 mm thick cement mortar 1: 3 {1 cement: 3 coarse sand (not having more than 40% stone chips of size upto 6 mm)} À with the help of shotcreting equipment etc at a pressure of not less than 1 bar (100Kn/ m2) and surface finished with trowel. The top face of the panel shall be provided and finished by applying 70-75 mm thick layer of cement concrete 1:1.5: 3 (1 cement :1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size). Fixing operations of roof/floor panels shall be completed in all respect as per drawings and specifications and under the overall direction of the Engineer-in-charge
- Item number
- 26.47
- Analysis basis
- Details of cost for 1.20x3.00m= 3.60 sqm
- Priced inputs
- 5
- Derived rate
- ₹4,701.60 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.47 — Providing and fixing in position, 230mm thick factory made Expanded Polystyrene Core (EPS Core) roof/floor panels made of 3 mm dia G.I. wire mesh with 50 mm pitch in both the directions and on both faces of panel, kept at 120-135 mm gap and connected by the zig zag G.I. wire of 3 mm dia at alternate row by welding (at an angle ranging from 50-70 degree). The EPS core shall consist of 100 mm thick EPS of density not less than 20kg/ per cum. The bottom side of the panel shall be finished by applying a layer of 60-65 mm thick cement mortar 1: 3 {1 cement: 3 coarse sand (not having more than 40% stone chips of size upto 6 mm)} À with the help of shotcreting equipment etc at a pressure of not less than 1 bar (100Kn/ m2) and surface finished with trowel. The top face of the panel shall be provided and finished by applying 70-75 mm thick layer of cement concrete 1:1.5: 3 (1 cement :1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size). Fixing operations of roof/floor panels shall be completed in all respect as per drawings and specifications and under the overall direction of the Engineer-in-charge — is derived from 5 priced inputs and works out to ₹4,701.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 3.60 sqm + 0.18 sqm (Add for wastage
- @5%)Total = 3.78 sqm
- Cement mortar 1:3 (1cement:3 coarse sand)
- 60mm thick on the bottom of roof slab
- =1x1.2x3.00x0.060= 0.216cum
- Cement concrete 1:1.5:3
- 70mm thick on the top of roof slab
- =1x1.20x3.00x0.07= 0.252 cum
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8013 | Factory made EPS Core wallpanel /roof panel sandwiched between two Engineered welded wire fabric mesh of 3 mm dia G.I. wire mesh,with 50 mm pitch in both the directions, kept at 120-135 mm gap and interconnected by the zig zag G.I. wire of 3 mm dia at alternate row by welding. sqm 3.78Factory made EPS Core wall panel /roof panel sandwiched between two Engineered welded wire fabric mesh of 3 mm dia G.I. wire mesh,with 50 mm pitch in both the directions, kept at 120-135 mm gap and interconnected by the zig zag G.I. wire of 3 mm dia at alternate row by welding.Material | sqm | 3.78 | 1,708.00 | 6,456.24 |
| Rate as per Item No.3.8 of SH: MortarRate as per item 3.8Sub-analysis | cum | 0.216 | 4,881.95 | 1,054.50 | |
| Rate as per Item No.5.3 of SH: Reinforced Cement ConcreteRate as per item 5.3Sub-analysis | cum | 0.252 | 11,505.50 | 2,899.39 | |
| 9999 | Add for L-shape, U-shape & straight lap meshMaterial | L.S. | 202.32 | 2.27 | 459.27 |
| 9999 | For providing concreting, shotcreting, shoring, leveling, plastering and finishing the surface with trowelMaterial | L.S. | 832.36 | 2.27 | 1,889.46 |
- TOTAL
- 12,758.86
- Add 1 % Water charges on “W-A”
- 98.59
- TOTAL
- 12,857.45
- Add GST on “X-A” (multiplying factor 0.2127)
- 2,118.08
- TOTAL
- 14,975.53
- Add 15% CPOH on “Y-A”
- 1,811.42
- TOTAL
- 16,786.95
- Add Cess @ 1% on “Z-A”
- 138.88
- Cost of 3.60 sqm
- 16,925.83
- Cost of 1 sqm
- 4,701.62
- Say
- 4,701.60
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1972. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works