CPWD Analysis of Rates · New Technologies and Materials
Providing and fixing in position, 200 mm thick factory made Expanded Polystyrene Core (EPS Core) wall panels consisting of EPS core sandwiched between two Engineered sheets of welded wire fabric mesh duly finished with shortcrete materials on outer faces. The fabric mesh shall be made of 3 mm dia G.I. wire mesh with 50 mm pitch in both the directions and on both faces of the wall, kept at 120-135 mm gap and connected by the zig zag G.I. wire of 3 mm dia at alternate row by welding (at an angle ranging from 50-70 degree) . The EPS core shall consist of 100 mm thick EPS of density not less than 20 kg/ per cum. Both the outer faces of the panel shall be finished by applying the layer of 50 mm thick cement mortar 1:3 {1 cement: 3 coarse sand (not having more than 40% stone chips of size upto 6 mm)} À with the help of shotcreting/guniting equipment etc at a pressure not less than 1 bar (100Kn/m2) and both surfaces finished with trowel. Fixing operations of wall panels shall be completed in all respect as per drawings and specifications and under the overall direction of the Engineerin-charge
- Item number
- 26.46
- Analysis basis
- Details of cost for 1.20x3.00m= 3.60 sqm
- Priced inputs
- 5
- Derived rate
- ₹4,347.15 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.46 — Providing and fixing in position, 200 mm thick factory made Expanded Polystyrene Core (EPS Core) wall panels consisting of EPS core sandwiched between two Engineered sheets of welded wire fabric mesh duly finished with shortcrete materials on outer faces. The fabric mesh shall be made of 3 mm dia G.I. wire mesh with 50 mm pitch in both the directions and on both faces of the wall, kept at 120-135 mm gap and connected by the zig zag G.I. wire of 3 mm dia at alternate row by welding (at an angle ranging from 50-70 degree) . The EPS core shall consist of 100 mm thick EPS of density not less than 20 kg/ per cum. Both the outer faces of the panel shall be finished by applying the layer of 50 mm thick cement mortar 1:3 {1 cement: 3 coarse sand (not having more than 40% stone chips of size upto 6 mm)} À with the help of shotcreting/guniting equipment etc at a pressure not less than 1 bar (100Kn/m2) and both surfaces finished with trowel. Fixing operations of wall panels shall be completed in all respect as per drawings and specifications and under the overall direction of the Engineerin-charge — is derived from 5 priced inputs and works out to ₹4,347.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 3.60 sqm + 0.18 sqm (Add for wastage
- @5%)Total = 3.78 sqm
- Cement mortar 1:3 (1cement:3 coarse sand)
- 2x1.20x3.00x0.05= 0.36 cum
- 10 mm TMT bars (2 nos.75 mm long)
- Aluminium C-channels (100mmx150mm
- long)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8013 | Factory made EPS Core wallpanel /roof panel sandwiched between two Engineered welded wire fabric mesh of 3 mm dia G.I. wire mesh,with 50 mm pitch in both the directions, kept at 120-135 mm gap and interconnected by the zig zag G.I. wire of 3 mm dia at alternate row by weldingFactory made EPS Core wall panel /roof panel sandwiched between two Engineered welded wire fabric mesh of 3 mm dia G.I. wire mesh,with 50 mm pitch in both the directions, kept at 120-135 mm gap and interconnected by the zig zag G.I. wire of 3 mm dia at alternate row by welding.Material | sqm | 3.78 | 1,708.00 | 6,456.24 |
| 9999 | Add for L-shape,U-shape & straight lap meshMaterial | L.S. | 208 | 2.27 | 472.16 |
| Rate as per Item No.3.8 of SH: MortarRate as per item 3.8Sub-analysis | cum | 0.36 | 4,881.95 | 1,757.50 | |
| 9999 | For fixing wall with foundationMaterial | L.S. | 312.15 | 2.27 | 708.58 |
| 9999 | For carrying out shotcreting, shoring, leveling, and finishing the surface with trowelMaterial | L.S. | 707.5 | 2.27 | 1,606.03 |
- TOTAL
- 11,000.51
- Add 1 % Water charges on “W”
- 110.01
- TOTAL
- 11,110.52
- Add GST on “X” (multiplying factor 0.2127)
- 2,363.21
- TOTAL
- 13,473.73
- Add 15% CPOH on “Y”
- 2,021.06
- TOTAL
- 15,494.79
- Add Cess @ 1% on “Z”
- 154.95
- Cost of 3.60 sqm
- 15,649.74
- Cost of 1 sqm
- 4,347.15
- Say
- 4,347.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1971. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works