Providing and fixing in position, 200 mm thick factory made Expanded Polystyrene Core (EPS Core) wall panels consisting of EPS core sandwiched between two Engineered sheets of welded wire fabric mesh duly finished with shortcrete materials on outer faces. The fabric mesh shall be made of 3 mm dia G.I. wire mesh with 50 mm pitch in both the directions and on both faces of the wall, kept at 120-135 mm gap and connected by the zig zag G.I. wire of 3 mm dia at alternate row by welding (at an angle ranging from 50-70 degree) . The EPS core shall consist of 100 mm thick EPS of density not less than 20 kg/ per cum. Both the outer faces of the panel shall be finished by applying the layer of 50 mm thick cement mortar 1:3 {1 cement: 3 coarse sand (not having more than 40% stone chips of size upto 6 mm)} À with the help of shotcreting/guniting equipment etc at a pressure not less than 1 bar (100Kn/m2) and both surfaces finished with trowel. Fixing operations of wall panels shall be completed in all respect as per drawings and specifications and under the overall direction of the Engineerin-charge

Item number
26.46
Analysis basis
Details of cost for 1.20x3.00m= 3.60 sqm
Priced inputs
5
Derived rate
4,347.15 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.46 Providing and fixing in position, 200 mm thick factory made Expanded Polystyrene Core (EPS Core) wall panels consisting of EPS core sandwiched between two Engineered sheets of welded wire fabric mesh duly finished with shortcrete materials on outer faces. The fabric mesh shall be made of 3 mm dia G.I. wire mesh with 50 mm pitch in both the directions and on both faces of the wall, kept at 120-135 mm gap and connected by the zig zag G.I. wire of 3 mm dia at alternate row by welding (at an angle ranging from 50-70 degree) . The EPS core shall consist of 100 mm thick EPS of density not less than 20 kg/ per cum. Both the outer faces of the panel shall be finished by applying the layer of 50 mm thick cement mortar 1:3 {1 cement: 3 coarse sand (not having more than 40% stone chips of size upto 6 mm)} À with the help of shotcreting/guniting equipment etc at a pressure not less than 1 bar (100Kn/m2) and both surfaces finished with trowel. Fixing operations of wall panels shall be completed in all respect as per drawings and specifications and under the overall direction of the Engineerin-charge — is derived from 5 priced inputs and works out to ₹4,347.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 3.60 sqm + 0.18 sqm (Add for wastage
  • @5%)Total = 3.78 sqm
  • Cement mortar 1:3 (1cement:3 coarse sand)
  • 2x1.20x3.00x0.05= 0.36 cum
  • 10 mm TMT bars (2 nos.75 mm long)
  • Aluminium C-channels (100mmx150mm
  • long)
CodeInputUnitQuantityRate (INR)Amount (INR)
8013Factory made EPS Core wallpanel /roof panel sandwiched between two Engineered welded wire fabric mesh of 3 mm dia G.I. wire mesh,with 50 mm pitch in both the directions, kept at 120-135 mm gap and interconnected by the zig zag G.I. wire of 3 mm dia at alternate row by weldingFactory made EPS Core wall panel /roof panel sandwiched between two Engineered welded wire fabric mesh of 3 mm dia G.I. wire mesh,with 50 mm pitch in both the directions, kept at 120-135 mm gap and interconnected by the zig zag G.I. wire of 3 mm dia at alternate row by welding.Materialsqm3.781,708.006,456.24
9999Add for L-shape,U-shape & straight lap meshMaterialL.S.2082.27472.16
Rate as per Item No.3.8 of SH: MortarRate as per item 3.8Sub-analysiscum0.364,881.951,757.50
9999For fixing wall with foundationMaterialL.S.312.152.27708.58
9999For carrying out shotcreting, shoring, leveling, and finishing the surface with trowelMaterialL.S.707.52.271,606.03
TOTAL
11,000.51
Add 1 % Water charges on “W”
110.01
TOTAL
11,110.52
Add GST on “X” (multiplying factor 0.2127)
2,363.21
TOTAL
13,473.73
Add 15% CPOH on “Y”
2,021.06
TOTAL
15,494.79
Add Cess @ 1% on “Z”
154.95
Cost of 3.60 sqm
15,649.74
Cost of 1 sqm
4,347.15
Say
4,347.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1971. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.