CPWD Analysis of Rates · New Technologies and Materials
Fill the groove (i.e. 2-3mm gap between board and 12.5mm thick gypsum plaster boards with epoxy based sealing compound, Acrylic based sealing compound, Non woven reinforcement Tape as per direction of Engineer in charge.(Use a flexible knife so that no air bubble is entrapped. Allow 1-2 hours gap. Once hard tacky or set, apply a coat of Acrylic based sealing compound paste to flash fill the beveled area. After 2-4 hours go on to repeat a skin coat with Acrylic based sealing compound to securely embed the 40mm width (non woven reinforcement Tape. Use only flexible steel knife, such as provided with packs, to avoid air entrapment within compound. After overnight drying shrinkage apply a coat of acrylic based sealing compound to compensate shrinkage. Finally cover the bevel portion with any suitable overall skin coat with a desired full surfaceleveler material)
- Item number
- 26.42.2/Sub-AR-1/Sub-AR-2
- Analysis basis
- Details of cost for 1 Sqm
- Priced inputs
- 5
- Derived rate
- ₹248.75 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.42.2/Sub-AR-1/Sub-AR-2 — Fill the groove (i.e. 2-3mm gap between board and 12.5mm thick gypsum plaster boards with epoxy based sealing compound, Acrylic based sealing compound, Non woven reinforcement Tape as per direction of Engineer in charge.(Use a flexible knife so that no air bubble is entrapped. Allow 1-2 hours gap. Once hard tacky or set, apply a coat of Acrylic based sealing compound paste to flash fill the beveled area. After 2-4 hours go on to repeat a skin coat with Acrylic based sealing compound to securely embed the 40mm width (non woven reinforcement Tape. Use only flexible steel knife, such as provided with packs, to avoid air entrapment within compound. After overnight drying shrinkage apply a coat of acrylic based sealing compound to compensate shrinkage. Finally cover the bevel portion with any suitable overall skin coat with a desired full surfaceleveler material) — is derived from 5 priced inputs for 1 Sqm and works out to ₹248.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1248 | Epoxy based sealing CompoundMaterial | kg | 0.14 | 535.00 | 74.90 |
| 1249 | Acrylic based sealing compoundMaterial | kg | 0.26 | 500.00 | 130.00 |
| 1250 | Non woven reinforcement TapeMaterial | metre | 25 | 0.14 | 3.50 |
| 0112 | Carpenter 2nd classLabour | day | 0.026 | 816.00 | 21.22 |
| 0114 | BeldarLabour | day | 0.026 | 736.00 | 19.14 |
- Cost of 1 sqm
- 248.76
- Say
- 248.75
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1967. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works