Filling the groove (i.e. 2-3mm gap between and 9mm thick fiber cement boards with epoxy based sealing compound or with silicon sealant. Second layer is fixed over it in a staggered pattern

Item number
26.42.2/Sub-AR-1
Analysis basis
10 Sqm
Priced inputs
3
Derived rate
₹95.40/ SQM
D-01/RATE ANALYSISITEM 26.42.2/Sub-AR-1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.42.2/Sub-AR-1 (Filling the groove (i.e. 2-3mm gap between and 9mm thick fiber cement boards with epoxy based sealing compound or with silicon sealant. Second layer is fixed over it in a staggered pattern) is derived from 3 priced inputs for 10 Sqm and works out to ₹95.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 26.42.2/Sub-AR-1DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1248MATEpoxy based sealing Compoundkg1.4535.00749.00
0112LABCarpenter 2nd classday0.132816.00107.71
0114LABBeldarday0.132736.0097.15
BUILD-UP TO RATE
Cost of 10 sqm
953.86
Cost of 1 sqm
95.39
SAY
₹95.40
D-02/SOURCEPRINTED PAGE 1966
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1966

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1966. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.