Providing and fixing internal wall panels on Light gauge steel frame work with 12.5mm thick gypsum plaster board conforming IS 2095:2011 fixed on cement board as per standard sizes fixed with self-drilling / taping screws / fasteners @ 60cm c/c of approved make, Screws shall be of counter sunk rib head of 1.60mm to 4 mm thick or 8 to 10 gauge of length varying from 25 to 45 mm. Proper taping and jointing to be done using fiber mesh tape and epoxy and acrylic based jointing compound for seamless finish.(cost of frame work to be paid for separately

Cement Fiber Board 8 mm thick of Type B, Category III as per IS 14862:2000 (High pressure Steam Cured)
Item number
26.43.1
Analysis basis
10 Sqm
Priced inputs
7
Derived rate
₹2,221.05/ SQM
D-01/RATE ANALYSISITEM 26.43.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.43.1 (Providing and fixing internal wall panels on Light gauge steel frame work with 12.5mm thick gypsum plaster board conforming IS 2095:2011 fixed on cement board as per standard sizes fixed with self-drilling / taping screws / fasteners @ 60cm c/c of approved make, Screws shall be of counter sunk rib head of 1.60mm to 4 mm thick or 8 to 10 gauge of length varying from 25 to 45 mm. Proper taping and jointing to be done using fiber mesh tape and epoxy and acrylic based jointing compound for seamless finish.(cost of frame work to be paid for separately Cement Fiber Board 8 mm thick of Type B, Category III as per IS 14862:2000 (High pressure Steam Cured)) is derived from 7 priced inputs for 10 Sqm and works out to ₹2,221.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • LABOUR (For cutting & fixing cement board
  • and Gypsum board)
ANALYSIS OF RATES · ITEM 26.43.1DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0237MATMulti purpose fibre (high impact poly propelene reinforced) cement board 8 mm thick Type B, Category III as per IS 14862:2000 fiber cement board 2x10=20 sqm + 2.00 (Add for wastage @10 %) = 22.00 sqmMulti purpose fibre (high impact poly propelene reinforced) cement board 8 mm thick, Type-B, Category-III as per IS 14862:2000Sqm22240.005,280.00
2635MATGI screws of gauge 10, length 25 mm for fixing cement fiber board to C section Tapping and finishing Cement board jointsGI Screws of gauge 10, length 25 mm for fixing cement fibre board to C sectioneach803.30264.00
0241MAT12.5 mm thick Gypsum plaster board 2x10 = 20 sqm + 2.00(Add for wastage @ 10%) = 22.00 sqm12.5 mm thick Gypsum plaster boardSqm22180.003,960.00
2635MATGI screws of gauge 10, length 25 mm for fixing cement fiber board to C section Tapping and finishing Cement board jointsGI Screws of gauge 10, length 25 mm for fixing cement fibre board to C sectioneach803.30264.00
SUBFilling the grove of 2 mm to 3 mm between 8 mm thick cement bonded particle board and 12.5 mm thick gypsum plastic boardRate as per item Sub A/R 2Sqm10248.752,487.50
0112LABCarpenter 2nd classday1.11816.00905.76
0114LABBeldarday3.33736.002,450.88
BUILD-UP TO RATE
TOTAL
15,612.14
Add 1 % Water charges on “W”
+156.12
TOTAL
15,768.26
Add GST on “X” (multiplying factor 0.2127)
+3,353.91
TOTAL
19,122.17
Add 15% CPOH on “Y”
+2,868.33
TOTAL
21,990.50
Add Cess @ 1% on “Z”
+219.91
Cost of 10 sqm
22,210.41
Cost of 1 sqm
2,221.04
SAY
₹2,221.05
D-02/SOURCEPRINTED PAGE 1967
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1967

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1967. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.