Providing and inserting 12mm dia galvanised steel injection nipple in honey comb area and along crack line including drilling of holes of required diametre (20mm to 30mm) up to depth from 30mm to 80mm at required spacing and making the hole & crack dust free by blowing compressed air, sealing the distance between injection nipple with adhesive chemical of approved make and allow it to cure complete as per direction of Engineer-In-Charge

Item number
26.39
Analysis basis
20.00 Nos
Priced inputs
7
Derived rate
₹236.90/ HOLE
D-01/RATE ANALYSISITEM 26.39

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.39 (Providing and inserting 12mm dia galvanised steel injection nipple in honey comb area and along crack line including drilling of holes of required diametre (20mm to 30mm) up to depth from 30mm to 80mm at required spacing and making the hole & crack dust free by blowing compressed air, sealing the distance between injection nipple with adhesive chemical of approved make and allow it to cure complete as per direction of Engineer-In-Charge) is derived from 7 priced inputs for 20.00 Nos and works out to ₹236.90 per hole after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (750 mm deep & 20 mm Dia Hole)
  • Volume of hole =20x(3.14/4)
  • x2.00x2.00x7.5=471 cub cm.
  • Adhesive @ 40% of 471 ml=188.40 ml, Say
  • 188 ml
  • (One Bit done 20 Holes only)
ANALYSIS OF RATES · ITEM 26.39DETAILS OF COST FOR 20.00 NOS HOLE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7921MATAdhesive chemicalml1882.00376.00
7922MATBit of drilling machine for Hole upto 30mm diaBit of drilling machine for Hole upto 30 mm diaeach1550.00550.00
7923MATGI injection nipple 12mm dia, 75mm longGI injection nipple 12 mm dia, 75 mm longeach2050.001,000.00
7924MATBlowing compressed air for cleaning holes upto 30mm diaBlowing compressed air for cleaning holes upto 30 mm diaeach2010.00200.00
0155LABMason (average)day0.5857.00428.50
0115LABCoolieday0.5736.00368.00
0101LABBhistiday0.5816.00408.00
BUILD-UP TO RATE
TOTAL
3,330.50
Add 1 % Water charges on “W”
+33.31
TOTAL
3,363.81
Add GST on “X” (multiplying factor 0.2127)
+715.48
TOTAL
4,079.29
Add 15% CPOH on “Y”
+611.89
TOTAL
4,691.18
Add Cess @ 1% on “Z”
+46.91
Cost of 20 Nos hole
4,738.09
Cost of 1 hole
236.90
SAY
₹236.90
D-02/SOURCEPRINTED PAGE 1960
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1960

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1960. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.