Skip to main content

CPWD Analysis of Rates · New Technologies and Materials

Providing and inserting 12mm dia galvanised steel injection nipple in honey comb area and along crack line including drilling of holes of required diametre (20mm to 30mm) up to depth from 30mm to 80mm at required spacing and making the hole & crack dust free by blowing compressed air, sealing the distance between injection nipple with adhesive chemical of approved make and allow it to cure complete as per direction of Engineer-In-Charge

Item number
26.39
Analysis basis
Details of cost for 20.00 Nos Hole
Priced inputs
7
Derived rate
236.90 / hole

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.39 Providing and inserting 12mm dia galvanised steel injection nipple in honey comb area and along crack line including drilling of holes of required diametre (20mm to 30mm) up to depth from 30mm to 80mm at required spacing and making the hole & crack dust free by blowing compressed air, sealing the distance between injection nipple with adhesive chemical of approved make and allow it to cure complete as per direction of Engineer-In-Charge — is derived from 7 priced inputs for 20.00 Nos and works out to ₹236.90 per hole after water charges, GST, CPOH and cess. The full build-up is below.

  • (750 mm deep & 20 mm Dia Hole)
  • Volume of hole =20x(3.14/4)
  • x2.00x2.00x7.5=471 cub cm.
  • Adhesive @ 40% of 471 ml=188.40 ml, Say
  • 188 ml
  • (One Bit done 20 Holes only)
CodeInputUnitQuantityRate (INR)Amount (INR)
7921Adhesive chemicalMaterialml1882.00376.00
7922Bit of drilling machine for Hole upto 30mm diaBit of drilling machine for Hole upto 30 mm diaMaterialeach1550.00550.00
7923GI injection nipple 12mm dia, 75mm longGI injection nipple 12 mm dia, 75 mm longMaterialeach2050.001,000.00
7924Blowing compressed air for cleaning holes upto 30mm diaBlowing compressed air for cleaning holes upto 30 mm diaMaterialeach2010.00200.00
0155Mason (average)Labourday0.5857.00428.50
0115CoolieLabourday0.5736.00368.00
0101BhistiLabourday0.5816.00408.00
TOTAL
3,330.50
Add 1 % Water charges on “W”
33.31
TOTAL
3,363.81
Add GST on “X” (multiplying factor 0.2127)
715.48
TOTAL
4,079.29
Add 15% CPOH on “Y”
611.89
TOTAL
4,691.18
Add Cess @ 1% on “Z”
46.91
Cost of 20 Nos hole
4,738.09
Cost of 1 hole
236.90
Say
236.90

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1960. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works