CPWD Analysis of Rates · New Technologies and Materials
Providing and fixing hard drawn steel wire fabric of size 75 x25 mm mesh or other suitable size wire mesh to be fixed & firmly anchored to the concrete surface by means of “L” shaped mild steel shear key welded with existing reinforcement including the cost of materials, labour, tool & plants as approved by Engineer-in-charge
- Item number
- 26.40
- Analysis basis
- Details of cost for 10.00 sqm ( i.e 77.50 kg.)
- Priced inputs
- 6
- Derived rate
- ₹902.55 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.40 — Providing and fixing hard drawn steel wire fabric of size 75 x25 mm mesh or other suitable size wire mesh to be fixed & firmly anchored to the concrete surface by means of “L” shaped mild steel shear key welded with existing reinforcement including the cost of materials, labour, tool & plants as approved by Engineer-in-charge — is derived from 6 priced inputs for 10.00 sqm and works out to ₹902.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- key to be provided at 0.5 mtr centre to centre in each direction
- = 25 nos
- 25x0.10x0.617=1.55 kg
- 75x25mm, weight 7.75kg/sqm
- 75x25 mm = 10.00 sqm + Add 5%
- wastage = 0.50 sqm Total = 10.50 sqm
- Total no. of Shear key of MS Bar in 10sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7925 | L shaped 100mm long, 10mm dia mild steel shear keyL shaped 100 mm long, 10 mm dia mild steel shear keyMaterial | kg | 1.55 | 90.00 | 139.50 |
| 0091 | Welding charges of shear key to existing reinforcementMachinery | each | 25 | 5.00 | 125.00 |
| 1021 | Hard drawn steel wire fabricHard drawn steel wire fabric 75 x 25 mm mesh of weight not less than 7.75 kg/sqmMaterial | sqm | 10.5 | 430.00 | 4,515.00 |
| 9977 | Carriage at siteMaterial | L.S. | 5.61 | 2.27 | 12.73 |
| 0103 | Blacksmith 2nd classLabour | day | 1 | 816.00 | 816.00 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
- TOTAL
- 6,344.23
- Add 1 % Water charges on “W”
- 63.44
- TOTAL
- 6,407.67
- Add GST on “X” (multiplying factor 0.2127)
- 1,362.91
- TOTAL
- 7,770.58
- Add 15% CPOH on “Y”
- 1,165.59
- TOTAL
- 8,936.17
- Add Cess @ 1% on “Z”
- 89.36
- Cost of 10 sqm
- 9,025.53
- Cost of 1 sqm
- 902.55
- Say
- 902.55
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1961. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works