Providing, erecting, maintaining and removing temporary protective screens made out of specified fabric with all necessary fixing arrangement to ensure that it remains in position for the work duration as required by the Engineer-in-charge
- Item number
- 26.36.1
- Analysis basis
- 10 sqm
- Priced inputs
- 2
- Derived rate
- ₹54.25/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.36.1 (Providing, erecting, maintaining and removing temporary protective screens made out of specified fabric with all necessary fixing arrangement to ensure that it remains in position for the work duration as required by the Engineer-in-charge Wooven PVC cloth) is derived from 2 priced inputs for 10 sqm and works out to ₹54.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- For fixing and removal after complete of
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7915 | MAT | Wooven PVC clothWoven PVC cloth | sqm | 10 | 28.00 | 280.00 |
| 9999 | MAT | Fixing double scaffolding outside | L.S. | 11 | 2.27 | 24.97 |
- Total Material
- 304.97
- work @25%
- +76.24
- TOTAL
- 381.21
- Add 1 % Water charges on “W”
- +3.81
- TOTAL
- 385.02
- Add GST on “X” (multiplying factor 0.2127)
- +81.89
- TOTAL
- 466.91
- Add 15% CPOH on “Y”
- +70.04
- TOTAL
- 536.95
- Add Cess @ 1% on “Z”
- +5.37
- Rate for 10 sqm
- +542.32
- Rate for 1 sqm
- +54.23
- SAY
- ₹54.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1957
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1957. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.