Providing, erecting, maintaining and removing temporary protective screens made out of specified fabric with all necessary fixing arrangement to ensure that it remains in position for the work duration as required by the Engineer-in-charge

Wooven PVC cloth
Item number
26.36.1
Analysis basis
10 sqm
Priced inputs
2
Derived rate
₹54.25/ SQM
D-01/RATE ANALYSISITEM 26.36.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.36.1 (Providing, erecting, maintaining and removing temporary protective screens made out of specified fabric with all necessary fixing arrangement to ensure that it remains in position for the work duration as required by the Engineer-in-charge Wooven PVC cloth) is derived from 2 priced inputs for 10 sqm and works out to ₹54.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • For fixing and removal after complete of
ANALYSIS OF RATES · ITEM 26.36.1DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7915MATWooven PVC clothWoven PVC clothsqm1028.00280.00
9999MATFixing double scaffolding outsideL.S.112.2724.97
BUILD-UP TO RATE
Total Material
304.97
work @25%
+76.24
TOTAL
381.21
Add 1 % Water charges on “W”
+3.81
TOTAL
385.02
Add GST on “X” (multiplying factor 0.2127)
+81.89
TOTAL
466.91
Add 15% CPOH on “Y”
+70.04
TOTAL
536.95
Add Cess @ 1% on “Z”
+5.37
Rate for 10 sqm
+542.32
Rate for 1 sqm
+54.23
SAY
₹54.25
D-02/SOURCEPRINTED PAGE 1957
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1957

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1957. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.