Skip to main content

Cleaning of exposed concrete surface of sticking material including loose and foreign material by sand blasting with coarse sand followed by and including cleaning with oil free air blast as per direction of Engineer in charge

Item number
26.37
Analysis basis
10 Sqm
Priced inputs
5
Derived rate
₹382.40/ SQM
D-01/RATE ANALYSISITEM 26.37

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.37 (Cleaning of exposed concrete surface of sticking material including loose and foreign material by sand blasting with coarse sand followed by and including cleaning with oil free air blast as per direction of Engineer in charge) is derived from 5 priced inputs for 10 Sqm and works out to ₹382.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 26.37DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0089MACHHire charges of sand blasting equipment (14 sqm per day)Hire charges of sand blasting equipmentday0.7450.00315.00
0090MACHHire charges of compressorday0.7550.00385.00
0982MATCoarse sand (zone III)cum11,450.001,450.00
0114LABBeldarday0.7736.00515.20
9999MATSundriesL.S.102.2722.70
BUILD-UP TO RATE
TOTAL
2,687.90
Add 1 % Water charges on “W”
+26.88
TOTAL
2,714.78
Add GST on “X” (multiplying factor 0.2127)
+577.43
TOTAL
3,292.21
Add 15% CPOH on “Y”
+493.83
TOTAL
3,786.04
Add Cess @ 1% on “Z”
+37.86
Cost of 10 sqm
3,823.90
Cost of 1 sqm
382.39
SAY
₹382.40
D-02/SOURCEPRINTED PAGE 1957
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1957

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1957. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.