CPWD Analysis of Rates · New Technologies and Materials

Cleaning of exposed concrete surface of sticking material including loose and foreign material by sand blasting with coarse sand followed by and including cleaning with oil free air blast as per direction of Engineer in charge

Item number
26.37
Analysis basis
Details of cost for 10 Sqm
Priced inputs
5
Derived rate
382.40 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.37 Cleaning of exposed concrete surface of sticking material including loose and foreign material by sand blasting with coarse sand followed by and including cleaning with oil free air blast as per direction of Engineer in charge — is derived from 5 priced inputs for 10 Sqm and works out to ₹382.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0089Hire charges of sand blasting equipment (14 sqm per day)Hire charges of sand blasting equipmentMachineryday0.7450.00315.00
0090Hire charges of compressorMachineryday0.7550.00385.00
0982Coarse sand (zone III)Materialcum11,450.001,450.00
0114BeldarLabourday0.7736.00515.20
9999SundriesMaterialL.S.102.2722.70
TOTAL
2,687.90
Add 1 % Water charges on “W”
26.88
TOTAL
2,714.78
Add GST on “X” (multiplying factor 0.2127)
577.43
TOTAL
3,292.21
Add 15% CPOH on “Y”
493.83
TOTAL
3,786.04
Add Cess @ 1% on “Z”
37.86
Cost of 10 sqm
3,823.90
Cost of 1 sqm
382.39
Say
382.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1957. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works