Cleaning of exposed concrete surface of sticking material including loose and foreign material by sand blasting with coarse sand followed by and including cleaning with oil free air blast as per direction of Engineer in charge
- Item number
- 26.37
- Analysis basis
- 10 Sqm
- Priced inputs
- 5
- Derived rate
- ₹382.40/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.37 (Cleaning of exposed concrete surface of sticking material including loose and foreign material by sand blasting with coarse sand followed by and including cleaning with oil free air blast as per direction of Engineer in charge) is derived from 5 priced inputs for 10 Sqm and works out to ₹382.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0089 | MACH | Hire charges of sand blasting equipment (14 sqm per day)Hire charges of sand blasting equipment | day | 0.7 | 450.00 | 315.00 |
| 0090 | MACH | Hire charges of compressor | day | 0.7 | 550.00 | 385.00 |
| 0982 | MAT | Coarse sand (zone III) | cum | 1 | 1,450.00 | 1,450.00 |
| 0114 | LAB | Beldar | day | 0.7 | 736.00 | 515.20 |
| 9999 | MAT | Sundries | L.S. | 10 | 2.27 | 22.70 |
- TOTAL
- 2,687.90
- Add 1 % Water charges on “W”
- +26.88
- TOTAL
- 2,714.78
- Add GST on “X” (multiplying factor 0.2127)
- +577.43
- TOTAL
- 3,292.21
- Add 15% CPOH on “Y”
- +493.83
- TOTAL
- 3,786.04
- Add Cess @ 1% on “Z”
- +37.86
- Cost of 10 sqm
- 3,823.90
- Cost of 1 sqm
- 382.39
- SAY
- ₹382.40
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1957
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1957. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.