Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/honey-comb area of concrete/masonry by suitable gun/pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-inCharge. (The payment shall be made on the basis of actual weight of approved grout injected.)

Epoxy injection grout in concrete/RCC work of approved make
Item number
26.35.3
Analysis basis
Details of cost for10kg Epoxy grout
Priced inputs
5
Derived rate
₹553.40/ KG
D-01/RATE ANALYSISITEM 26.35.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.35.3 (Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/honey-comb area of concrete/masonry by suitable gun/pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-inCharge. (The payment shall be made on the basis of actual weight of approved grout injected.) Epoxy injection grout in concrete/RCC work of approved make) is derived from 5 priced inputs and works out to ₹553.40 per kg after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 26.35.3DETAILS OF COST FOR10KG EPOXY GROUT
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7913MATEpoxykg10380.003,800.00
0092MACHHire charges of Plant and machinery, it can inject - 350kg/dayHire charges of plant and Machinery that can inject 350 kg/dayday0.03250.007.50
0114LABBeldarday0.06736.0044.16
0157LABNozzle OperatorOperator (Pile/ Special machine)day0.03897.0026.91
9999MATSundries (gloves gogles etc.)L.S.52.2711.35
BUILD-UP TO RATE
TOTAL
3,889.92
Add 1 % Water charges on “W”
+38.90
TOTAL
3,928.82
Add GST on “X” (multiplying factor 0.2127)
+835.66
TOTAL
4,764.48
Add 15% CPOH on “Y”
+714.67
TOTAL
5,479.15
Add Cess @ 1% on “Z”
+54.79
Cost of 10 kg
5,533.94
Cost of 1 kg
553.39
SAY
₹553.40
D-02/SOURCEPRINTED PAGE 1956
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1956

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1956. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.