Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/honey-comb area of concrete/masonry by suitable gun/pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-inCharge. (The payment shall be made on the basis of actual weight of approved grout injected.)
- Item number
- 26.35.3
- Analysis basis
- Details of cost for10kg Epoxy grout
- Priced inputs
- 5
- Derived rate
- ₹553.40/ KG
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.35.3 (Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/honey-comb area of concrete/masonry by suitable gun/pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-inCharge. (The payment shall be made on the basis of actual weight of approved grout injected.) Epoxy injection grout in concrete/RCC work of approved make) is derived from 5 priced inputs and works out to ₹553.40 per kg after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7913 | MAT | Epoxy | kg | 10 | 380.00 | 3,800.00 |
| 0092 | MACH | Hire charges of Plant and machinery, it can inject - 350kg/dayHire charges of plant and Machinery that can inject 350 kg/day | day | 0.03 | 250.00 | 7.50 |
| 0114 | LAB | Beldar | day | 0.06 | 736.00 | 44.16 |
| 0157 | LAB | Nozzle OperatorOperator (Pile/ Special machine) | day | 0.03 | 897.00 | 26.91 |
| 9999 | MAT | Sundries (gloves gogles etc.) | L.S. | 5 | 2.27 | 11.35 |
- TOTAL
- 3,889.92
- Add 1 % Water charges on “W”
- +38.90
- TOTAL
- 3,928.82
- Add GST on “X” (multiplying factor 0.2127)
- +835.66
- TOTAL
- 4,764.48
- Add 15% CPOH on “Y”
- +714.67
- TOTAL
- 5,479.15
- Add Cess @ 1% on “Z”
- +54.79
- Cost of 10 kg
- 5,533.94
- Cost of 1 kg
- 553.39
- SAY
- ₹553.40
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1956
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1956. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate