CPWD Analysis of Rates · New Technologies and Materials

Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/honey-comb area of concrete/masonry by suitable gun/pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-inCharge. (The payment shall be made on the basis of actual weight of approved grout injected.)

Epoxy injection grout in concrete/RCC work of approved make

Item number
26.35.3
Analysis basis
Details of cost for10kg Epoxy grout
Priced inputs
5
Derived rate
553.40 / kg

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.35.3 Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/honey-comb area of concrete/masonry by suitable gun/pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-inCharge. (The payment shall be made on the basis of actual weight of approved grout injected.) Epoxy injection grout in concrete/RCC work of approved make — is derived from 5 priced inputs and works out to ₹553.40 per kg after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7913EpoxyMaterialkg10380.003,800.00
0092Hire charges of Plant and machinery, it can inject - 350kg/dayHire charges of plant and Machinery that can inject 350 kg/dayMachineryday0.03250.007.50
0114BeldarLabourday0.06736.0044.16
0157Nozzle OperatorOperator (Pile/ Special machine)Labourday0.03897.0026.91
9999Sundries (gloves gogles etc.)MaterialL.S.52.2711.35
TOTAL
3,889.92
Add 1 % Water charges on “W”
38.90
TOTAL
3,928.82
Add GST on “X” (multiplying factor 0.2127)
835.66
TOTAL
4,764.48
Add 15% CPOH on “Y”
714.67
TOTAL
5,479.15
Add Cess @ 1% on “Z”
54.79
Cost of 10 kg
5,533.94
Cost of 1 kg
553.39
Say
553.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1956. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works