Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/honey-comb area of concrete/masonry by suitable gun/pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-inCharge. (The payment shall be made on the basis of actual weight of approved grout injected.)

Stirrer mixed SBR Polymer (of approved make) modified Cement slurry made with Shrinkage Compensating Cement in concrete/RCC work
Item number
26.35.2
Analysis basis
100kg of
Priced inputs
7
Derived rate
₹124.00/ KG
D-01/RATE ANALYSISITEM 26.35.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.35.2 (Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/honey-comb area of concrete/masonry by suitable gun/pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-inCharge. (The payment shall be made on the basis of actual weight of approved grout injected.) Stirrer mixed SBR Polymer (of approved make) modified Cement slurry made with Shrinkage Compensating Cement in concrete/RCC work) is derived from 7 priced inputs for 100kg of and works out to ₹124.00 per kg after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • mixed cement grout
ANALYSIS OF RATES · ITEM 26.35.2DETAIL OF COST FOR 100KG OF SBR POLYMER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7914MATSBR Polymer for crackSBR Polymerkg2200.00400.00
0367MATPortland Cement (OPC-43 grade)tonne0.15,156.00515.60
9977MATCarriage of materialsL.S.12.272.27
9999MATInjecting charges of Stirrer mixed polymer grout Gun, rubber, pipe and other accessories hire charges of plant, machinery including necessary fuel and transportation of site Rs 4000/- per day including plant shall be used of doing approximate v Hence cost per sqm (4000/50 = 80)L.S.2,2502.275,107.50
0122LABForemanMason (for plaster of paris work) 1st classday1897.00897.00
0157LABNozzle OperatorOperator (Pile/ Special machine)day1897.00897.00
0157LABPump OperatorOperator (Pile/ Special machine)day1897.00897.00
BUILD-UP TO RATE
TOTAL
8,716.37
Add 1 % Water charges on “W”
+87.16
TOTAL
8,803.53
Add GST on “X” (multiplying factor 0.2127)
+1,872.51
TOTAL
10,676.04
Add 15% CPOH on “Y”
+1,601.41
TOTAL
12,277.45
Add Cess @ 1% on “Z”
+122.77
Cost of 100 kg
12,400.22
Cost of 1 kg
124.00
SAY
₹124.00
D-02/SOURCEPRINTED PAGE 1956
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1956

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1956. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.