Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/honey-comb area of concrete/masonry by suitable gun/pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-inCharge. (The payment shall be made on the basis of actual weight of approved grout injected.)

Stirrer mixed SBR Polymer (of approved make) modified Cement slurry made with Shrinkage Compensating Cement in concrete/RCC work

Item number
26.35.2
Analysis basis
Detail of cost for 100kg of SBR Polymer
Priced inputs
7
Derived rate
124.00 / kg

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.35.2 Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/honey-comb area of concrete/masonry by suitable gun/pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-inCharge. (The payment shall be made on the basis of actual weight of approved grout injected.) Stirrer mixed SBR Polymer (of approved make) modified Cement slurry made with Shrinkage Compensating Cement in concrete/RCC work — is derived from 7 priced inputs for 100kg of and works out to ₹124.00 per kg after water charges, GST, CPOH and cess. The full build-up is below.

  • mixed cement grout
CodeInputUnitQuantityRate (INR)Amount (INR)
7914SBR Polymer for crackSBR PolymerMaterialkg2200.00400.00
0367Portland Cement (OPC-43 grade)Materialtonne0.15,156.00515.60
9977Carriage of materialsMaterialL.S.12.272.27
9999Injecting charges of Stirrer mixed polymer grout Gun, rubber, pipe and other accessories hire charges of plant, machinery including necessary fuel and transportation of site Rs 4000/- per day including plant shall be used of doing approximate v Hence cost per sqm (4000/50 = 80)MaterialL.S.2,2502.275,107.50
0122ForemanMason (for plaster of paris work) 1st classLabourday1897.00897.00
0157Nozzle OperatorOperator (Pile/ Special machine)Labourday1897.00897.00
0157Pump OperatorOperator (Pile/ Special machine)Labourday1897.00897.00
TOTAL
8,716.37
Add 1 % Water charges on “W”
87.16
TOTAL
8,803.53
Add GST on “X” (multiplying factor 0.2127)
1,872.51
TOTAL
10,676.04
Add 15% CPOH on “Y”
1,601.41
TOTAL
12,277.45
Add Cess @ 1% on “Z”
122.77
Cost of 100 kg
12,400.22
Cost of 1 kg
124.00
Say
124.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1956. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.