Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/honey-comb area of concrete/masonry by suitable gun/pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-inCharge. (The payment shall be made on the basis of actual weight of approved grout injected.)
- Item number
- 26.35.2
- Analysis basis
- 100kg of
- Priced inputs
- 7
- Derived rate
- ₹124.00/ KG
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.35.2 (Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/honey-comb area of concrete/masonry by suitable gun/pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-inCharge. (The payment shall be made on the basis of actual weight of approved grout injected.) Stirrer mixed SBR Polymer (of approved make) modified Cement slurry made with Shrinkage Compensating Cement in concrete/RCC work) is derived from 7 priced inputs for 100kg of and works out to ₹124.00 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- mixed cement grout
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7914 | MAT | SBR Polymer for crackSBR Polymer | kg | 2 | 200.00 | 400.00 |
| 0367 | MAT | Portland Cement (OPC-43 grade) | tonne | 0.1 | 5,156.00 | 515.60 |
| 9977 | MAT | Carriage of materials | L.S. | 1 | 2.27 | 2.27 |
| 9999 | MAT | Injecting charges of Stirrer mixed polymer grout Gun, rubber, pipe and other accessories hire charges of plant, machinery including necessary fuel and transportation of site Rs 4000/- per day including plant shall be used of doing approximate v Hence cost per sqm (4000/50 = 80) | L.S. | 2,250 | 2.27 | 5,107.50 |
| 0122 | LAB | ForemanMason (for plaster of paris work) 1st class | day | 1 | 897.00 | 897.00 |
| 0157 | LAB | Nozzle OperatorOperator (Pile/ Special machine) | day | 1 | 897.00 | 897.00 |
| 0157 | LAB | Pump OperatorOperator (Pile/ Special machine) | day | 1 | 897.00 | 897.00 |
- TOTAL
- 8,716.37
- Add 1 % Water charges on “W”
- +87.16
- TOTAL
- 8,803.53
- Add GST on “X” (multiplying factor 0.2127)
- +1,872.51
- TOTAL
- 10,676.04
- Add 15% CPOH on “Y”
- +1,601.41
- TOTAL
- 12,277.45
- Add Cess @ 1% on “Z”
- +122.77
- Cost of 100 kg
- 12,400.22
- Cost of 1 kg
- 124.00
- SAY
- ₹124.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1956
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1956. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.