Skip to main content

Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/honey-comb area of concrete/masonry by suitable gun/pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-inCharge. (The payment shall be made on the basis of actual weight of approved grout injected.)

Stirrer mixed Acrylic Polymer of approved make @ 2% of weight of cement used) modified Cement slurry made with non shrink compound in concrete/RCC work
Item number
26.35.1
Analysis basis
100 kg
Priced inputs
7
Derived rate
₹119.30/ KG
D-01/RATE ANALYSISITEM 26.35.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.35.1 (Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/honey-comb area of concrete/masonry by suitable gun/pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-inCharge. (The payment shall be made on the basis of actual weight of approved grout injected.) Stirrer mixed Acrylic Polymer of approved make @ 2% of weight of cement used) modified Cement slurry made with non shrink compound in concrete/RCC work) is derived from 7 priced inputs for 100 kg and works out to ₹119.30 per kg after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • mixed cement grout
  • Considering 1 kg of cement grout mixed
  • with non shrink polymer compound with
  • cement @ 2% of cement
ANALYSIS OF RATES · ITEM 26.35.1DETAIL OF COST FOR 100 KG ACRYLIC POLYMER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7927MATAcrylic Polymer chemical for crackskg235.0070.00
0367MATPortland Cement (OPC-43 grade)tonne0.15,156.00515.60
9977MATCarriage of materialsL.S.12.272.27
9999MATInjecting charges of Stirrer mixed polymer grout Gun, rubber, pipe and other accessories hire charges of plant, machinery including necessary fuel and transportation of siteL.S.2,2502.275,107.50
0122LABForemanMason (for plaster of paris work) 1st classday1897.00897.00
0157LABNozzlemanOperator (Pile/ Special machine)day1897.00897.00
0157LABPump OperatorOperator (Pile/ Special machine)day1897.00897.00
BUILD-UP TO RATE
TOTAL
8,386.37
Add 1 % Water charges on “W”
+83.86
TOTAL
8,470.23
Add GST on “X” (multiplying factor 0.2127)
+1,801.62
TOTAL
10,271.85
Add 15% CPOH on “Y”
+1,540.78
TOTAL
11,812.63
Add Cess @ 1% on “Z”
+118.13
Cost of 100 kg
11,930.76
Cost of 1 kg
119.31
SAY
₹119.30
D-02/SOURCEPRINTED PAGE 1955
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1955

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1955. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.