Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/honey-comb area of concrete/masonry by suitable gun/pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-inCharge. (The payment shall be made on the basis of actual weight of approved grout injected.)
- Item number
- 26.35.1
- Analysis basis
- 100 kg
- Priced inputs
- 7
- Derived rate
- ₹119.30/ KG
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.35.1 (Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/honey-comb area of concrete/masonry by suitable gun/pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-inCharge. (The payment shall be made on the basis of actual weight of approved grout injected.) Stirrer mixed Acrylic Polymer of approved make @ 2% of weight of cement used) modified Cement slurry made with non shrink compound in concrete/RCC work) is derived from 7 priced inputs for 100 kg and works out to ₹119.30 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- mixed cement grout
- Considering 1 kg of cement grout mixed
- with non shrink polymer compound with
- cement @ 2% of cement
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7927 | MAT | Acrylic Polymer chemical for cracks | kg | 2 | 35.00 | 70.00 |
| 0367 | MAT | Portland Cement (OPC-43 grade) | tonne | 0.1 | 5,156.00 | 515.60 |
| 9977 | MAT | Carriage of materials | L.S. | 1 | 2.27 | 2.27 |
| 9999 | MAT | Injecting charges of Stirrer mixed polymer grout Gun, rubber, pipe and other accessories hire charges of plant, machinery including necessary fuel and transportation of site | L.S. | 2,250 | 2.27 | 5,107.50 |
| 0122 | LAB | ForemanMason (for plaster of paris work) 1st class | day | 1 | 897.00 | 897.00 |
| 0157 | LAB | NozzlemanOperator (Pile/ Special machine) | day | 1 | 897.00 | 897.00 |
| 0157 | LAB | Pump OperatorOperator (Pile/ Special machine) | day | 1 | 897.00 | 897.00 |
- TOTAL
- 8,386.37
- Add 1 % Water charges on “W”
- +83.86
- TOTAL
- 8,470.23
- Add GST on “X” (multiplying factor 0.2127)
- +1,801.62
- TOTAL
- 10,271.85
- Add 15% CPOH on “Y”
- +1,540.78
- TOTAL
- 11,812.63
- Add Cess @ 1% on “Z”
- +118.13
- Cost of 100 kg
- 11,930.76
- Cost of 1 kg
- 119.31
- SAY
- ₹119.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1955
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1955. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.