CPWD Analysis of Rates · New Technologies and Materials
Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/honey-comb area of concrete/masonry by suitable gun/pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-inCharge. (The payment shall be made on the basis of actual weight of approved grout injected.)
Stirrer mixed Acrylic Polymer of approved make @ 2% of weight of cement used) modified Cement slurry made with non shrink compound in concrete/RCC work
- Item number
- 26.35.1
- Analysis basis
- Detail of cost for 100 kg Acrylic polymer
- Priced inputs
- 7
- Derived rate
- ₹119.30 / kg
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.35.1 — Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/honey-comb area of concrete/masonry by suitable gun/pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-inCharge. (The payment shall be made on the basis of actual weight of approved grout injected.) Stirrer mixed Acrylic Polymer of approved make @ 2% of weight of cement used) modified Cement slurry made with non shrink compound in concrete/RCC work — is derived from 7 priced inputs for 100 kg and works out to ₹119.30 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- mixed cement grout
- Considering 1 kg of cement grout mixed
- with non shrink polymer compound with
- cement @ 2% of cement
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7927 | Acrylic Polymer chemical for cracksMaterial | kg | 2 | 35.00 | 70.00 |
| 0367 | Portland Cement (OPC-43 grade)Material | tonne | 0.1 | 5,156.00 | 515.60 |
| 9977 | Carriage of materialsMaterial | L.S. | 1 | 2.27 | 2.27 |
| 9999 | Injecting charges of Stirrer mixed polymer grout Gun, rubber, pipe and other accessories hire charges of plant, machinery including necessary fuel and transportation of siteMaterial | L.S. | 2,250 | 2.27 | 5,107.50 |
| 0122 | ForemanMason (for plaster of paris work) 1st classLabour | day | 1 | 897.00 | 897.00 |
| 0157 | NozzlemanOperator (Pile/ Special machine)Labour | day | 1 | 897.00 | 897.00 |
| 0157 | Pump OperatorOperator (Pile/ Special machine)Labour | day | 1 | 897.00 | 897.00 |
- TOTAL
- 8,386.37
- Add 1 % Water charges on “W”
- 83.86
- TOTAL
- 8,470.23
- Add GST on “X” (multiplying factor 0.2127)
- 1,801.62
- TOTAL
- 10,271.85
- Add 15% CPOH on “Y”
- 1,540.78
- TOTAL
- 11,812.63
- Add Cess @ 1% on “Z”
- 118.13
- Cost of 100 kg
- 11,930.76
- Cost of 1 kg
- 119.31
- Say
- 119.30
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1955. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works