Providing, mixing and applying SBR polymer (of approved make) modified Cement mortar in proportion of 1:4 (1 cement: 4 graded coarse sand with polymer minimum 2% by wt. of cement used) as per specifications and directions of Engineer-in-charge. Note: Measurement and payment: The pre-measurement of thickness shall be done just after the surface preparation is completed and Payment under this item shall be made only after proper wet curing has been done and surface has been satisfactorily evaluated by sounding / tapping with a blunt metal instrument and/or the 75mm size cube crushing strength at the end of 28 days to be not less than 30 N/Sqmm2)

25 mm average thickness in 2 layers
Item number
26.32.2
Analysis basis
10 Sqm
Priced inputs
6
Derived rate
₹587.35/ SQM
D-01/RATE ANALYSISITEM 26.32.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.32.2 (Providing, mixing and applying SBR polymer (of approved make) modified Cement mortar in proportion of 1:4 (1 cement: 4 graded coarse sand with polymer minimum 2% by wt. of cement used) as per specifications and directions of Engineer-in-charge. Note: Measurement and payment: The pre-measurement of thickness shall be done just after the surface preparation is completed and Payment under this item shall be made only after proper wet curing has been done and surface has been satisfactorily evaluated by sounding / tapping with a blunt metal instrument and/or the 75mm size cube crushing strength at the end of 28 days to be not less than 30 N/Sqmm2) 25 mm average thickness in 2 layers) is derived from 6 priced inputs for 10 Sqm and works out to ₹587.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1:4 (1 cement : 4 coarse
  • sand) =(0.144/12)x25=0.30 Cum
  • Cement 0.30x0.38 = 0.114 MT OR 114 kg
  • @ 2% of weight of cement 114kgx2%
  • =2.28kg
ANALYSIS OF RATES · ITEM 26.32.2DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.3.9 of SH: MORTARSRate as per item 3.9cum0.34,211.701,263.51
7914MATSBR Polymerkg2.28200.00456.00
0155LABMason (average)day0.94857.00805.58
0115LABCoolieday1.02736.00750.72
0101LABBhistiday1.01816.00824.16
9999MATScaffolding and sundriesL.S.12.612.2728.62
BUILD-UP TO RATE
TOTAL
4,128.59
Add 1 % Water charges on “W”
+41.29
TOTAL
4,169.88
Add GST on “X” (multiplying factor 0.2127)
+886.93
TOTAL
5,056.81
Add 15% CPOH on “Y”
+758.52
TOTAL
5,815.33
Add Cess @ 1% on “Z”
+58.15
Cost for 10 sqm
5,873.48
Rate per sqm
587.35
SAY
₹587.35
D-02/SOURCEPRINTED PAGE 1951
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1951

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1951. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.