Providing, mixing and applying bonding coat of approved adhesive on chipped portion of RCC as per specifications and direction of Engineer-In-charge complete in all respect

Epoxy bonding adhesive having coverage 2.20 sqm/kg of approved make
Item number
26.31.2
Analysis basis
2.20 Sqm
Priced inputs
3
Derived rate
₹285.20/ SQM
D-01/RATE ANALYSISITEM 26.31.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.31.2 (Providing, mixing and applying bonding coat of approved adhesive on chipped portion of RCC as per specifications and direction of Engineer-In-charge complete in all respect Epoxy bonding adhesive having coverage 2.20 sqm/kg of approved make) is derived from 3 priced inputs for 2.20 Sqm and works out to ₹285.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 26.31.2DETAILS OF COST FOR 2.20 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7913MATEpoxykg1380.00380.00
9999MATApplication charge for applying bonding coat of EpoxyL.S.18.52.2742.00
9999MATCost of brushes etc.L.S.8.42.2719.07
BUILD-UP TO RATE
TOTAL
441.07
Add 1 % Water charges on “W”
+4.41
TOTAL
445.48
Add GST on “X” (multiplying factor 0.2127)
+94.75
TOTAL
540.23
Add 15% CPOH on “Y”
+81.03
TOTAL
621.26
Add Cess @ 1% on “Z”
+6.21
Cost for 2.20 sqm
627.47
Rate per sqm
285.21
SAY
₹285.20
D-02/SOURCEPRINTED PAGE 1950
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1950

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1950. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.