Providing, mixing and applying bonding coat of approved adhesive on chipped portion of RCC as per specifications and direction of Engineer-In-charge complete in all respect
- Item number
- 26.31.2
- Analysis basis
- 2.20 Sqm
- Priced inputs
- 3
- Derived rate
- ₹285.20/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.31.2 (Providing, mixing and applying bonding coat of approved adhesive on chipped portion of RCC as per specifications and direction of Engineer-In-charge complete in all respect Epoxy bonding adhesive having coverage 2.20 sqm/kg of approved make) is derived from 3 priced inputs for 2.20 Sqm and works out to ₹285.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7913 | MAT | Epoxy | kg | 1 | 380.00 | 380.00 |
| 9999 | MAT | Application charge for applying bonding coat of Epoxy | L.S. | 18.5 | 2.27 | 42.00 |
| 9999 | MAT | Cost of brushes etc. | L.S. | 8.4 | 2.27 | 19.07 |
- TOTAL
- 441.07
- Add 1 % Water charges on “W”
- +4.41
- TOTAL
- 445.48
- Add GST on “X” (multiplying factor 0.2127)
- +94.75
- TOTAL
- 540.23
- Add 15% CPOH on “Y”
- +81.03
- TOTAL
- 621.26
- Add Cess @ 1% on “Z”
- +6.21
- Cost for 2.20 sqm
- 627.47
- Rate per sqm
- 285.21
- SAY
- ₹285.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1950
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1950. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.