CPWD Analysis of Rates · New Technologies and Materials
Providing, mixing and applying bonding coat of approved adhesive on chipped portion of RCC as per specifications and direction of Engineer-In-charge complete in all respect
SBR Polymer (@10% of cement weight) modified cementitious bond coat @ 2.2 kg cement per sqm of surface area mixed with specified proportion of approved polymer
- Item number
- 26.31.1
- Analysis basis
- Details of Cost for 10.00 Sqm bonding coat
- Priced inputs
- 5
- Derived rate
- ₹141.20 / Sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.31.1 — Providing, mixing and applying bonding coat of approved adhesive on chipped portion of RCC as per specifications and direction of Engineer-In-charge complete in all respect SBR Polymer (@10% of cement weight) modified cementitious bond coat @ 2.2 kg cement per sqm of surface area mixed with specified proportion of approved polymer — is derived from 5 priced inputs for 10.00 Sqm and works out to ₹141.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- @ 10% of cement weight= 22.00kgx10%
- =2.2 kg
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0367 | Portland Cement (OPC-43 grade)Material | tonne | 0.022 | 5,156.00 | 113.43 |
| 7914 | SBR PolymerMaterial | kg | 2.2 | 200.00 | 440.00 |
| 0155 | Mason (average)Labour | day | 0.27 | 857.00 | 231.39 |
| 0115 | CoolieLabour | day | 0.27 | 736.00 | 198.72 |
| 9999 | Scaffolding and sundries (8.06/2=4.03)Material | L.S. | 4.03 | 2.27 | 9.15 |
- TOTAL
- 992.69
- Add 1 % Water charges on “W”
- 9.93
- TOTAL
- 1,002.62
- Add GST on “X” (multiplying factor 0.2127)
- 213.26
- TOTAL
- 1,215.88
- Add 15% CPOH on “Y”
- 182.38
- TOTAL
- 1,398.26
- Add Cess @ 1% on “Z”
- 13.98
- Cost for 10.00 sqm
- 1,412.24
- Rate per sqm
- 141.22
- Say
- 141.20
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1949. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.